| 1 | Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means (Scarifying the existing granular road surface to a depth of 50 mm and disposal of scarified material with all lifts and leads upto 1000 metres.) |
| 2 | Granular Sub-base with Well Graded Material (CBR>30 or more) (Table:- 4OO-1 & Table 400-2) : Construction of granular sub-base by providing well graded material like natural sand crushed gravel or crushed stone having CBR >30, spreading in uniform layers with motor grader on prepared surface, mixing by plant mix method at OMC, and compacting with vibratory rollers of 80 to 100 kN static weight to achieve the desired density, complete as per Clause 401 of Specification. For grading- I Material |
| 3 | Granular Sub-base with Well Graded Material (CBR>30 or more) (Table:- 4OO-1 & Table 400-2 : Construction of granular sub-base by providing well graded material like natural sand crushed gravel or crushed stone having CBR >30, spreading in uniform layers with motor grader on prepared surface, mixing by plant mix method at OMC, and compacting with vibratory rollers of 80 to 100 kN static weight to achieve the desired density, complete as per Clause 401 of Specification. For grading- III Material |
| 4 | Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 26.5 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing as per clause 601 of specifications complete in all respect. |
| 5 | Cement Concrete Pavement ( Construction of un-reinforced, dowel jointed, plain cement concrete pavement (minimum flexural strength - 4.5 Mpa) over a prepared sub base with cement @ 400 kg per cum (minimum), coarse and fine aggregate conforming to IS 383,maximum size of coarse aggregate not exceeding 31.5 mm, mixed in a batching and mixing plant as per approved mix design,transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, admixtures as approved,curing compound, finishing to lines and grades as per drawing as per IRC 15 2011 and as per relevant clauses of section 602 of specifications complete but excluding cost of steel in dowel bar and tie rods etc |
| 6 | Supplying, fitting and placing Mild steel reinforcement complete in sub-structure as per drawing and technical specification and as per relevant clause of section 1600 |
| 7 | Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and technical specifications and as per relevant clause of section 1600 |
| 8 | Embankment Construction with Material Obtained from Borrow Pits (Construction of embankment with approved material having CBR>7 obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-1, 300-2 and as per relevant clauses of section - 300 ) |
| 9 | Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material as per relevant clauses of section 300 & 2100 ) Oridinary soil Mechanical Means depth upto 3 m |
| 10 | Plain/Reinforced cement concrete in open foundation including formwork, shuttering etc. complete as per drawing and technical specifications and as per relevant clauses of section 1500, 1700 & 2100 PCC Grade M15 |
| 11 | Plain/Reinforced cement concrete in open foundation including formwork, shuttering etc. complete as per drawing and technical specifications and as per relevant clauses of section 1500, 1700 & 2100 RCC Grade M30 Using Batching Plant, Transit Mixer and Concrete Pump |
| 12 | Plain/Reinforced cement concrete in sub-structure including formwork, shuttering etc. complete as per drawing and technical specifications RCC Grade M30, Height upto 5m, With Batching Plant, Transit Mixer and Concrete Pump |
| 13 | Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per drawing and technical specifications and as per relevant clauses of section 1600 |
| 14 | Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC/PVC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing face. Complete as per drawing and Technical specifications. |
| 15 | Sand Filling in Foundation Trenches as per Drawing & Technical Specification |
| 16 | Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure including formwork, shuttering etc. as per drawing and Technical Specification and as per relevant clauses of sections 1500, 1700 & 2300 RCC Grade M 30 Using Batching Plant, Transit Mixer and Concrete Pump. For solid slab super-structure height upto 5 m |
| 17 | Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications as per relevant clause of section 1600. |
| 18 | PCC M15 Grade leveling course below approach slab complete as per drawing and Technical specification and as per relevant clauses of section 1700. |
| 19 | Reinforced cement concrete approach slab (Grade of concrete M-30) including reinforcement and formwork complete as per drawing and Technical specification and as per relevant clauses 1500, 1700 and clause 2704 of specifications |
| 20 | Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per drawing and Technical Specifications and as per relevant clauses of sections 1500, 1700 and clause 2702 of specifications |
| 21 | Filler Joint - Providing & fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing & Technical Specification. |
| 22 | Filler Joint - Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply supported spans not exceeding 10 m to cater for a horizontal movement upto 20 mm, covered with sealant complete as per drawing and technical specifications |
| 23 | Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2 of MoRTH specifications to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return wall to the full height compacted to a firm condition complete as per drawing and technical specification. |
| 24 | Painting on concrete surface (Providing and applying 2 coats of water based cement paint to unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m. ) |
| 25 | Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces |
| 26 | Total impact of GST plus Labour Cess [@ 1 % (BOCW Cess to be deducted from the RA bill as per the value of the work progress)] for the purpose of CTC Please Enable Macros to View BoQ information |