| 1 | Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m.Ground floor |
| 2 | In 1st floor |
| 3 | In 2nd floor |
| 4 | In 3rd floor |
| 5 | In 4th floor |
| 6 | In 5th floor |
| 7 | In 6th floor |
| 8 | In 7th floor |
| 9 | In 8th floor |
| 10 | Cutting holes and subsequent mending good damages.Diameter exceeding 300 mm. but not exceeding 450 mm.In concrete work (plain or R.C.) [Cement-7.5 Kg/Mtr] |
| 11 | Cutting chase upto 125 x 150 mm. and subsequent mending of damages.in brick wall [Cement-3.6 Kg/Mtr] In concrete work (plain or R.C.) [Cement-7.5 Kg/Mtr] |
| 12 | Dismantling R.C. floor, roof, beams etc. including cutting rods and removing rubbish as directed within a lead of 75 m. including stacking of steel bars. (gr floor) |
| 13 | In 1st floor |
| 14 | In 2nd floor |
| 15 | In 3rd floor |
| 16 | In 4th floor |
| 17 | In 5th floor |
| 18 | In 6th floor |
| 19 | In 7th floor |
| 20 | In 8th floor |
| 21 | Dismantling artificial stone flooring upto 50 mm. thick by carefully chiselling without damaging the base and removing rubbish as directed within a lead of 75 m. |
| 22 | In 1st floor |
| 23 | In 2nd floor |
| 24 | In 3rd floor |
| 25 | In 4th floor |
| 26 | In 5th floor |
| 27 | In 6th floor |
| 28 | In 7th floor |
| 29 | In 8th floor |
| 30 | Labour for lowering and stacking after dismantling in parts R.S. joists, channels, angles, tees, plates etc.complete as directed.From 1st floor level |
| 31 | 2nd floor |
| 32 | In 3rd floor |
| 33 | In 4th floor |
| 34 | In 5th floor |
| 35 | In 6th floor |
| 36 | In 7th floor |
| 37 | Stripping off worn out plaster and raking out joints of walls, celings etc. upto any height and in any floor including removing rubbish within a lead of 75m as directed. |
| 38 | Cleaning the concrete surface by removing dirt and debris, marking defective locations and removing loose concrete by careful stripping untill hard surface is exposed, cutting the concrete to regular shape, wire brushing the exposed surface and removing debris from site complete as per direction of the Engineer - in - Charge. (8th floor) |
| 39 | Taking out old damaged tarfelt from the roof, parapet etc. preparing the roof surfaces by removing all spoils, blisters, moss etc. from the working site and disposal of the samebeyond the compound and cleaning the site in all respect as per direction of Engineer-in-Charge. |
| 40 | Brick work with 1st class bricks in cement mortar (1:4)In superstructure, ground floor |
| 41 | In 1st floor |
| 42 | In 2nd floor |
| 43 | In 3rd floor |
| 44 | In 4th floor |
| 45 | In 5th floor |
| 46 | In 6th floor |
| 47 | In 7th floor |
| 48 | In 8th floor |
| 49 | M.S. structural works in columns, beams etc. with simple rolled structural members (e.g. joists, angle, channel sections conforming to IS: 226, IS: 808 & SP (6)- 1964 connected to one another with bracket, gussets, cleats as per design, direction of Engineer-incharge complete including cutting to requisite shape and length, fabrication with necessary bolting, metal arc welding conforming to IS: 816- 1969 & IS: 1995 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour required for the work including all incidental chages such as electricity charges, labour insurance charges etc. Payment to be made on the basis of calculated weight of structural members only in finished work as per IS specified weight. Payment for gusset, bracket, cleat, rivets, bolts and nuts may be make by adding the actual weight of such items with the weight of finished structural members or 7% of weight for finished structural members weighing not less than 22.5 Kg. / m. or 15 % of weight for finished structal members weighing less than 22.5 Kg. / m. may be increased allow for bracket, cleat, rivet, bolts and nuts etc. and no seperate payment being made for these items, as per direction of Engineer In Charge. The rates are considered for a height of erection 8m./2nd floor level from the ground. Add 1.5% extra over the rate for each additional floor or 4m. beyond initial 8m. or part thereof.For built up sections / srtuctural members of specified sections weighing not less than 22.5 Kg./m |
| 50 | In 1st floor |
| 51 | In 2nd floor |
| 52 | In 3rd floor |
| 53 | In 4th floor |
| 54 | In 5th floor |
| 55 | In 6th floor |
| 56 | In 7th floor |
| 57 | In 8th floor |
| 58 | Labour for hoisting and placing in proper position (up to 1st floor level) departmental R.S. joists, channels, angles. Tees, plates etc. including fitting and fixing same with bolts and nuts, if necessary (but excluding cost of such bolts and nuts) from 1st floor level |
| 59 | 2nd floor |
| 60 | In 3rd floor |
| 61 | In 4th floor |
| 62 | In 5th floor |
| 63 | In 6th floor |
| 64 | In 7th floor |
| 65 | In 8th floor |
| 66 | Supplying fitting and fixing I.R.C. fabric mesh with covering battens including cost of screws etc complete (excluding the cost of battens).In ground floor.25mm x 25mm x 2.7mm x 2.7mm. |
| 67 | 1st floor |
| 68 | 2nd floor |
| 69 | In 3rd floor |
| 70 | In 4th floor |
| 71 | In 5th floor |
| 72 | In 6th floor |
| 73 | In 7th floor |
| 74 | Welding in M.S. structural work with gas or electric:Tack Weld |
| 75 | Providing and inserting nipples with approved fixing compound after drilling holes for grouting as per Technical specifications including subsequent cutting/removal and sealing of the hole as necessary of nipples after completion of grouting with Cement/Epoxy. |
| 76 | Sealing of cracks / porous concrete by injection process through nipples/Grouting complete as per Technical specification.Cement Grout |
| 77 | Guniting concrete surface with cement mortar (25 mm nominal thick) applied with compressor after cleaning surface and spraying with epoxycomplete as per Technical specification. |
| 78 | Applying 2 coats of Acrylic Polymer Modified Paint (Equivalent to MASTER CRETE M-81 of Choksey or similar specified product) having water proofing cum bonding properties for specific use in terrace, toilet blocks, swimming pools, water tank, basement etc over prepared surface (Surface preparation cost to be paid separately) to prevent leakage underneath by mixing in proportion (1 litre liquid compound : 2 Kg of cement) as per Manufacturer's specification complete in all respect including materials and labour as per direction of Engineer-in-Charge. |
| 79 | Applying 2 coats of bonding agent with synthetic multi functional rubber emulsion having adhesive and water proofing properties by mixing with water in proportion (1 bonding agent : 4 water : 6 cement) as per Manufacturer's specification [Cement to be supplied by the Department] |
| 80 | Labour for taking out door and window frame including shutter for repair or replacement of different parts of the frame & refixing the same including mending good all damaes complete. (Concrete and brick work for mending damage will be paid separately)Upto area 2.5 Sq.m |
| 81 | Cement concrete (1:1.5:3) with graded stone chips 5.6 mm size with hexagonal square mesh wire netting, I.R.C. fabric mesh or X.P. M. fitted and fixed after tying the existing reinforcement on concrete without distributing the same and with proper scarping and cleaning the reinforcement and disturbed concrete with wire brush etc. after applying a coat of cement including the cost of wire netting I.R.C or X. P. M. & cost of all handling and scaffolding complete as per direction of Engineer-in -charge.37.5 mm thick |
| 82 | Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement,if any, in ground floor as per relevant IS codes.Pakur Variety (gr floor) |
| 83 | In 1st floor |
| 84 | In 2nd floor |
| 85 | In 3rd floor |
| 86 | In 4th floor |
| 87 | In 5th floor |
| 88 | In 6th floor |
| 89 | In 7th floor |
| 90 | 8th floor |
| 91 | Ordinary Cement concrete (mix 1:2:4) with graded stone chips (6mm nominal size) excluding shuttering and reinforcement,if any, in gound floor as per relevant IS codes.Pakur variety |
| 92 | Supplying,fitting & fixing granite slab 15mm to 18mm thick in floor, lobby, stair, landing and treads etc. over 20mm (avg) thick base of cement morter (1:2) laid with white cement slurry @ 4.40Kg per Square meter before placing of granite and jointed with white cement slurry @ 2.0 Kg per square meter with necessary pigments and complete as per direction of Engineer-in-charge including cost of all materials, labours, curing and roughening of concrete surface complete.In ground floorArea of each Granite slab 0.6 to 1.0 Square meter |
| 93 | 1st floor |
| 94 | 2nd floor |
| 95 | In 3rd floor |
| 96 | In 4th floor |
| 97 | In 5th floor |
| 98 | In 6th floor |
| 99 | In 7th floor |
| 100 | Artificial stone in floor, dado, staircase etc with cement concrete (1:2:4) with stone chips, laid in panels as directed with topping made with ordinary or white cement (as necessary) and marble dust in proportion (1:2) including smooth finishing and rounding off corners including raking out joints or roughening of concrete surface and application of cement slurry before flooring works using cement @ 1.75 kg/sq.m all complete including all materials and labour.20 mm thick |
| 101 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar includingPlaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chippingWith 1:4 cement mortar20 mm thick (gr floor) |
| 102 | 1st floor |
| 103 | 2nd floor |
| 104 | In 3rd floor |
| 105 | In 4th floor |
| 106 | In 5th floor |
| 107 | In 6th floor |
| 108 | In 7th floor |
| 109 | In 8th floor |
| 110 | 10 mm thick plaster |
| 111 | Roof treatment by application of ready-to-use, non toxic, water based, cold applied, single component, elastomeric in-situ seamless onolithic, acrylic modified bituminous liquid waterproofing membrane (Tarfelt LM or any other equivalent product) after preparing the surface by cleaning and repairing the roof cracks by cement & sand mortar (1/4), preferably with anti-shrinkage mortar (repair by mortar to be paid separately), if any. Apply two coats @ 0.70 kg/sqm per coat without dilution with water) after application of a priming coat (diluted with water in the ratio of 50 50 and apply @ 400 grm/sqm of the mixture) (Time gap between coats--after priming coat allow it to touch dry, after applying 1st coat wait for 12 hours then apply 2nd coat paint and after 2nd coat allow 36 hrs for any further work) including the cost of aterials and base cleaning, tools & plants complete as per direction of Engineer in-charge. (Conduct ponding test after 7 days of curing at ambient temperature) (Cover layer not required and not to be used over existing APP/Terfelt/Metal Pitched roof) |
| 112 | Supplying, fitting and fixing steel rolling shutter profile type with 18 B.G . of approved type steel latche section 75mm wide, fitted with coil wire spring to necessiate the fitting of required Nos. of C.I. Pulleys on heavy type solid drawn seamless steel tube complete with locking arrangements both inside and outside specially builtup side guide channels including providing a hood for the steel rolling shutter in the room, painting two coats of approved aluminium paint over a coat of red lead primer complete. |
| 113 | Supplying, fitting and fixing Stainless Steel railing consist of 38mm dia and 900mm height vertical balustrade at every two alternative steps, 50mm dia top rail, 3 (three) nos 19mm dia horizontal Strainless steel pipe and base/cover plate with Strainless Steel GRADE 304 containing 7.5% nickle (Interior Grade) Brushed/Mat finish, complete as per direction of the Engineer-in-charge. Weight of Strainless Steel railing per metre 6.5 Kg (approx)8th floor |
| 114 | Supplying,fitting & fixing of 2-Track / 3-Track Aluminium sliding Window of all Aluminium sections viz. window frame (top,bottom & side frame), shutter (top, bottom, side & interlock member) made of aluminium alloy extrusions conforming to IS 733-1983 & IS 1285-1975, annodised conforming to IS 1868-1983, fitted with all other accessories viz. PVC roller, EPDM asket, maruti lock, screws etc. including labour charges for fitting & fixing of aluminium 2-track/3-track sliding window with fixing of glass (excluding cost of glass) all complete as per architectural drawings and direction of Engineer-in-charge.10-12 Micron thickness Annodizing filmNatural whiteFor 2-Track window : Members for Bottom frame @ 0.875 Kg per Mtr. and for Top and Side frame @ 0.778 Kg per Mtr. and for shutter Bottom and Top member @ 0.472 Kg per Mtr., Style side member @ 0.493 Kg per Mtr. and Interlock member @ 0.612 Kg per Mtr |
| 115 | Supplying, fitting & fixing of Aluminium fixed partion wall of all aluminium sections viz top, bottom and side member, intermediate member, glazing clip made of Aluminium Alloy Extrusions conforming to IS: 733-1983 and IS: 1285-1975, annodized conforming to IS:1868- 1983, fitted with all other accessories viz. EPDM gusket,cleat, angle screws etc. including labour charges for fitting and fixing of aluminium fixed partition wall with glass / panel board all complete as per architectural drawings and direction of Engineer-in-charge. (Excluding cost of glass/ panel board,10-12 Micron thickness Annodizing film.Natural white.For unsupported length of vertical member above 1.50m. height of both ends of vertical member restrained but panel above 0.90 sqm(unit wt of Top, bottom & side member @ 1.978; intermediate member @ 2.055; glazing clip @ 0.167 kg/m respectively)3rd floor |
| 116 | Supplying best Indian sheet glass panes set in putty and fitted and fixed with nails and putty complete. (In all floors for internal wall & upto 6 m height for external wall)4 mm thick |
| 117 | Removing loose scales, blisters etc. from old painted surface and thoroughly smoothening the surface to make the same suitable for receiving fresh coat of paint. |
| 118 | Rendering the surface of walls and ceiling with white cement based wall putty of approved make and brand (1.5mm thick) |
| 119 | Colour washing with any shade with Stainers, as required including cleaning and smoothening surface thoroughly :Internal surface (All floors)Two coats (on new works only).Yellow, pink |
| 120 | Priming one coat on timber or plastered surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc. |
| 121 | Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. Including using of approved putty etc. on the surface, if necessary :On timber or plastered surface :With super gloss (hi-gloss) -Two coats (with any shade except white) |
| 122 | Painting with ready mixed Black Japan of approved make and brand including moothening surfacetwo coats |
| 123 | Polishing only of old marble or terrazo work with oxalic acid powder sing 33 gms/ sq.m. by manual labour / machine where necessary. |
| 124 | Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor)Extra for staging beyond 4 m in any floor (Mode of measurement: area in plan x mean height of staging upto soffit of shuttering above initial 4 m) |
| 125 | Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge |
| 126 | Sub-Total |
| 127 | GST @ 18% |
| 128 | Cess @ 1% Please Enable Macros to View BoQ information |