| 1 | dk;ZA |
| 2 | Safe carriage of the following material from store centre to work site including loading and unloading at both ends as per RESPO norms (in juridiction of circle) Distance 0 to 60 km:-11 Mtr. PCC/ST Poles. |
| 3 | 09 Mtr. PCC Poles. |
| 4 | 8.5 Mtr. Long PCC Poles. |
| 5 | ACSR Weasel Conductor. |
| 6 | ACSR Dog Conductor. |
| 7 | LT AB Cable (3×95+1×70+1×16) sq.mm |
| 8 | LT AB Cable (3×120+1×95+1×16) sq.mm |
| 9 | T/F 11/0.4 kV, 63 kVA |
| 10 | T/F 11/0.4 kV, 100 kVA |
| 11 | T/F 11/0.4 kV, 250 kVA |
| 12 | 11 KV XLPE Cable AL. 3x70 sq.mm |
| 13 | 11 KV XLPE Cable AL. 3x185 sq.mm |
| 14 | LT XLPE Cable AL. 1x120 sq.mm |
| 15 | LT XLPE Cable AL. 1x400 sq.mm |
| 16 | 33/11 K.V Line material such as Cross-Arms, Polymeric Pin Insulators with pin, Guarding Angles, Guarding Wire, Disc Insulators with fittings, stay set, G.I wire, Earthing rod, Fuse set, M.s angle, M.s channel, jointing sleave for various type conductor etc. |
| 17 | 1-ϕ & 3 ϕ distribution box |
| 18 | Various Type Cable Jointing Kits (Indoor &outdoor ), straight through for 11/33 KV. |
| 19 | 11 KV TPMO |
| 20 | Dismantling/removing of the line by contractor and Safe carriage of the material from work Site to store including loading and unloading at both ends as per RESPO norms :-ACSR conductor from all phases on line, making bundle and stacking at a safe place, |
| 21 | M.S Scrape and other line item |
| 22 | Old and used TF 10/25/63/100 KVA |
| 23 | Construction of 33 KV/ 11 KV / LT Over head / Underground Line as per RESPO norms :-Sagging ACSR Weasel Conductor. |
| 24 | Sagging ACSR Dog Conductor. |
| 25 | Sagging LT AB Cable (3×95+1×70+1×16) sq.mm |
| 26 | Sagging LT AB Cable (3×120+1×95+1×16) sq.mm |
| 27 | Sagging Various type 11/33 KV XLPE Cable over head |
| 28 | Digging of cable trench in size of 0.45Mtr. x1.05 Mtr. and Laying cable in trench and Providing 150 mm. sand cushion beneath and 150 mm. above the cable. The cable shall be duly protected by 1st Class Bricks, two on either side and third on top of the cable, laid in the series one after the other and:-G.I. Pipe 6” dia for inserting 33/11 KV XLPE cable for safety of cable on Single/Double Pole by providing and fixing of MS Clamp, Nuts and Bolts. |
| 29 | Laying of HDPE pipe |
| 30 | Guarding of 33/11 KV Line with G.I. wire. |
| 31 | Fixing of 11 KV Fuse Set . |
| 32 | Mounting and fixing of 25/63/100 KVA transformer on double pole and making proper connections HT/ LT side. |
| 33 | Making 2x2x1.5 mtr size Plinth for 250 KVA/400KVA transformer with 1 class brick and with all material and civil work as per respo norms. |
| 34 | Installation of 250 KVA/400 KVA transformer on plinth including making proper connections HT/ LT side. |
| 35 | Making MS strip (50x6 mm) Fencing (6 feet height including civil work) for humanand equipment safty with interlocking tile inside transformer fencing. |
| 36 | Water level earthing of 250 KVA/400 KVA transformer for its safty with all accessories. (Earthing material should be provided by contractor) |
| 37 | Henly Type Tailless unit protection cubical panel 500A, 650V for 160/250 KVA Transformer. (Tail less unit should be provided by contractor) |
| 38 | Fixing of LT Fuse Set/Box with fuse wire and fixing of MS Clamp, Nuts and Bolts and making proper connections with all accessories. |
| 39 | Mounting and fixing 11 K.V Stay Set |
| 40 | Mounting and fixing 33 K.V Stay Set |
| 41 | Mounting and fixing 11 K.V Pin/Disk insulator with fitting. |
| 42 | Mounting and fixing 33 K.V Pin/Disk insulator with fitting. |
| 43 | Fixing of Danger board and number plate with clamp . |
| 44 | Wraping of Barbed wire on Pole. |
| 45 | Fixing of 1-ϕ & 3 ϕ distribution box with making proper connection |
| 46 | Earthing of PCC/ST Pole/ Transformer by M.S Earthing rod |
| 47 | For 33/11 KV/LT Line, Excavation of foundation pit in size of 75x45 cm. having depth of 1/6th of the full length of the support (pole), providing and laying of stone pad (300x300x75mm.) in the bottom of the pit. (For PCC Pole) Erection of single pole support complete with fixing of 11 KV V-Type cross-arms, holding clamps, f-bracket and nuts & bolts and all other accessories , . Single support 8.5 Mtr. long PCC Poles :- |
| 48 | 9 Mtr. long PCC Poles :- |
| 49 | 11 Mtr. long PCC Poles :- |
| 50 | For 33/11 KV/LT Line, Excavation of foundation pit in size of 75x45 cm. having depth of 1/6th of the full length of the support (pole), providing and laying of stone pad (300x300x75mm.) in the bottom of the pit. (For PCC Pole) Erection of single pole support complete with fixing of 11 KV V-Type cross-arms, holding clamps, f-bracket and nuts & bolts and all other accessories , . Double support Double/section Pole structure with 8.5 Mtr. long PCC Poles :- |
| 51 | 9 Mtr. long PCC Poles :- |
| 52 | 11 Mtr. long PCC Poles :- |
| 53 | Installation of M.S Angle/ Channel/ Bracing on Existing Double pole Structure |
| 54 | For 33/11 KV/LT Line, Excavation of foundation pit in size of 75x45 cm. having depth of 1/6th of the full length of the support (pole), providing and laying of stone pad (300x300x75mm.) in the bottom of the pit. (For PCC Pole) Erection of single pole support complete with fixing of 11 KV V-Type cross-arms, holding clamps, f-bracket and nuts & bolts and all other accessories , . Tri support 11 Mtr. long PCC Poles :- |
| 55 | For 33/11 KV/LT Line, Excavation of foundation pit in size of 75x45 cm. having depth of 1/6th of the full length of the support (pole), providing and laying of stone pad (300x300x75mm.) in the bottom of the pit. (For PCC Pole) Erection of single pole support complete with fixing of 11 KV V-Type cross-arms, holding clamps, f-bracket and nuts & bolts and all other accessories , . four pole 9 Mtr. long PCC Poles :- :- |
| 56 | Grounting of Pcc/ST POLE |
| 57 | Grouting of stay rods (20x1800mm.) including all works of excavation, cement concrete in size of (0.60x0.60x0.30)M in the ratio of 1:4:6 (cement, sand and 40 mm. brick ballast) including back filling of soil and proper ramming etc. |
| 58 | Filling of various type 33/11 kv cable jointing kit. |
| 59 | Installtion of 11 kv TPMO |
| 60 | Matarials to be provided by contractor of 11 KV Underground/ Over head Line as per RESPO norms :-Stone Pad 300x300x75 mm |
| 61 | Cross Arm holding Clamps with bolts & nuts |
| 62 | Holding clamps for top channel TPMO & fuse set etc. with bolts & nuts |
| 63 | Al. PG clamps Dog to Dog |
| 64 | PG Clamp For LT |
| 65 | Suspension Clamp |
| 66 | Dead-End Clamp |
| 67 | Eye-Hook |
| 68 | J-Hook |
| 69 | Copper L-Piece 50x225x10 mm |
| 70 | Copper L-Piece 62x225x12 mm |
| 71 | F-bracket for 11 kV line |
| 72 | F-bracket for 33 kV line |
| 73 | Barbed wire GI |
| 74 | LT PVC Cable 3.5x70/35 sq mm |
| 75 | LT PVC Cable 3.5x150/70 sq mm |
| 76 | Al. long leg Barrel, off-size |
| 77 | Danger Board with clamps |
| 78 | Number Plate with clamps |
| 79 | Henly Type Tailless unit protection cubical panel 500A, 650V for 250 KVA and 400 KVA Transformer. |
| 80 | LT Fuse set with all accecesories |
| 81 | Piercing connector |
| 82 | Double pole clamp |
| 83 | Guarding clamp |
| 84 | M.S Guarding X-Arm |
| 85 | Eye-Bolt |
| 86 | Nut and bolts |
| 87 | M.S Channel Top |
| 88 | M.S Channel Dropper |
| 89 | M.S Angle For TF Base |
| 90 | M.S Bracing Angle |
| 91 | M.S channel T-Off |
| 92 | Grounting Of Pole (Grounting Material) |
| 93 | Connecting Lead 1x16 sq mm |
| 94 | Alluminium binding wire |
| 95 | G.I. Pipe 6” dia |
| 96 | HDPE PIPE 120mm Please Enable Macros to View BoQ information |