| 1 | Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. |
| 2 | Sand Filling in Foundation Trenches as per Drawing & Technical Specification |
| 3 | Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. |
| 4 | RCC Grade M30 using batching plant transit mixer & Concrete pump |
| 5 | Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications. |
| 6 | Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications. |
| 7 | Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of embankment complete as per drawing and Technical specifications |
| 8 | Providing and laying boulders apron on river bed for protection against scour with stone boulders weighing not less than 40 kg each complete as per drawing and Technical specification. |
| 9 | Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical Specifications |
| 10 | Providing and Laying of drainage spouts complete as per drawing and technical Clause 2705 of MoRTH Specifications. |
| 11 | Painting with synthetic enamel paint bridge No. and span arrangements. Painting two coats after filling the surface with synthetic enamel paint bridge No. and span arrangements as per as directed by Engineer. |
| 12 | Providing and laying Cement concrete wearing coat RCC Grade M35 grade including reinforcement complete as per drawing and Technical Specifications |
| 13 | Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with a all lifts and leads, transporting to site. Spreading, grading to required slpoe and compacting to meet required of table 300.1 and 300.2 as per Technic |
| 14 | Providing, laying and spreading material on a prepared sub grade, adding cement @ 2% (CTS) by weight to the spread material manually, mixing in place with rotavator and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base. |
| 15 | Providing, laying and spreading material on a prepared sub base, adding cement @ 4% (CTB) by weight to the spread material manually, mixing in place with rotavator and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of base. |
| 16 | Providing and applying tack coat with Bitumen VG-10 using Bitumen Pressure Sprayer at the rate of 0.350 kg per sqm on the prepared granular surfaces treated with primer or previously painted surface & cleaned with Hydraulic broom as per MORD Technical Spe |
| 17 | Providing, laying and rolling of open-graded premix carpet of 20 mm thick (compacted) composed of 13.2 mm to 5.6 mm aggregates of approved quarry using bitumen (VG-10) to required line, grade and level to serve as wearing course on a previously prepared b |
| 18 | Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type C as per MORD Technical Specification Clause 510 and direction of Engineer-in-charge . Please Enable Macros to View BoQ information |