| 1 | Dismentling of Stone work in cement mortar including staacking of material as directed by engineer in charge within a distence of 60m as per ch No XV SL No-1 (Including all material, T&P, royalty, labour cess etc. but excluding G.S.T.) |
| 2 | Dismentling of cement concrete floor including base concrete and including stacking of dismantle material as directed by the engineer in charge within a distence of 60m as per chapter xv-16 (Including all material, T&P, royalty, labour cess etc. but excluding G.S.T.) |
| 3 | Photography with all Expenditure (Size 6\\"x4\\") (Including all material, T&P, royalty, labour cess etc. but excluding G.S.T.) |
| 4 | Supply & Fixing of shila patt (size 3'x2.50') granite stone (Including all material, T&P, royalty, labour cess etc. but excluding G.S.T.) |
| 5 | Earth work in correcting internal section by Porclain/JCB machiens for bed width 8m including internal sides slope cutting at required slope with all lead and lift in all types of soil with disposal on daulas and top and outer slope of banks as directed by site incharge including and partial dressing for bed width 8-16m.Ch.5 A item no.3(b.) (Including all material, T&P, royalty, labour cess etc. but excluding G.S.T.) |
| 6 | C.C in 1:3:6 cement,coarse sand,stone ballast (20-40 mm)including cost of material at site labour,T&P etc required for proper completion of work. (Including all material, T&P, royalty, labour cess etc. but excluding G.S.T.) |
| 7 | CC Work in 1:2:4 Cement, Coarse sand, & Dala Grit (10-20mm) (Including all material, T&P, royalty, labour cess etc. but excluding G.S.T.) |
| 8 | Cement Plastering on stone Masonary with 1:3 Cement & Coarse sand mortar upto 12mm thick. (Including all material, T&P, royalty, labour cess etc. but excluding G.S.T.) |
| 9 | Deep Struck/ raised pointing in 1:2 cement , coarse sand mortar over stone masonary. (Including all material, T&P, royalty, labour cess etc. but excluding G.S.T.) |
| 10 | Filling of diversion drain (Including all material, T&P, royalty, labour cess etc. but excluding G.S.T.) |
| 11 | Dewatering with Diesel Pump Set 5-8 HP (Including all material, T&P, royalty, labour cess etc. but excluding G.S.T.) Please Enable Macros to View BoQ information |