| 1 | Safe carriage of the following Centralised material from any Store Centre of PVVNL/Baghpat/Baraut to work site /JE store with loading & unloading at both ends respectively. |
| 2 | 8.5 Mtr PCC Pole |
| 3 | 11 Mtr PCC Pole |
| 4 | 9 Mtr. PCC POLE |
| 5 | 11 KV \\"V\\" type cross arm 65x65x6 mm |
| 6 | Polymeric 11KV Pin Insulator |
| 7 | 11kv XLPE Cable 3x185 sqmm |
| 8 | 11kv XLPE Cable Jointing kit 3x185 O/D |
| 9 | Earthing of Pole by M S Earthing Rod 20 x 2500 mm and 6 SWG earthing wire etc |
| 10 | Complete Stay Set 9GI Stay Rod 20x1800 mm |
| 11 | 11 kv Disc Fitting for T&C 45 KN |
| 12 | 11 kv Disc Insulator T&C 45 KN |
| 13 | ACSR Weasel Conductor |
| 14 | ACSR Rabit Conductor |
| 15 | 11/0.4 KV T/F 250KVA |
| 16 | 11 KV TPMO |
| 17 | 11 KV fuse Set |
| 18 | Distribution Box 3phase |
| 19 | ABC cable 3x120+1x90+1x35 sq mm |
| 20 | LT XLPE Cable Al 1x400 sq mm |
| 21 | 11/0.4 KV T/F 100 KVA |
| 22 | ABC cable 3x95+1x70+1x16 sq mm |
| 23 | LT xlpe Cable Al 3.5x70 sq mm |
| 24 | 11 kv VCB Outgoing 200/100/5A 350 MVA |
| 25 | 11 kv VCB Incoming 600/300/5A 350 MVA |
| 26 | 33 KV 3x300 XLPE Cable |
| 27 | H/S O/D 33 KV 3x300 sqmm J/kit |
| 28 | 33kv Cross Arm |
| 29 | 33 kv disk fitting |
| 30 | 33 kv polimer disk insulator |
| 31 | 33 Kv Pin Insulator With Pin |
| 32 | 33 kv VCB (750 MVA 1250 Amp.) |
| 33 | 33KV TPMO (Bus Isolator 800 A, 33KV) |
| 34 | 33 kv CT (200/100/1 Amp.+400/200 /1 Amp.) |
| 35 | 11 KV XLPE CABLE 3X300 |
| 36 | 11 KV CABLE BOX 3X300 I/D |
| 37 | 33 KV Control Pannel for Single T/F |
| 38 | Contol Cable 4x2.5 sqmm |
| 39 | Contol Cable 2x2.5 sqmm |
| 40 | 33 KV PT O/D |
| 41 | Proper Installation/Fabrication/laying/fixing/binding etc. of the above and Following Centralised Material With proper connection including All the Accessories and complete work in all respect (as per resspo norms and site requirement) (All work in the Contractor Scope with Carriage of material to different work site including loading & unloading at both ends respectively). |
| 42 | Excavation of foundation pit in size of 75x45 cm. having depth of 1/6th of the full length of the support (pole), providing and laying of stone pad (300x300x75mm.) in the bottom of the pit. Erection of support (pole) For HT/LT Line and complete work as per RESSPO Norms.PCC Pole 08.5 Mtr AND 9 MTR PCC POLE . |
| 43 | Excavation of foundation pit in size of 75x45 cm. having depth of 1/6th of the full length of the support (pole), providing and laying of stone pad (300x300x75mm.) in the bottom of the pit. Erection of support (pole) For HT/LT Line and complete work as per RESSPO Norms.PCC Pole 11 Mtr. |
| 44 | Double pole structure with ST/PCC Poles :- Excavation of foundation pit in size of 75x45 cm. having depth of 1/6th of the full length of the support (pole), providing and laying of stone pad (300x300x75mm.) in the bottom of the pit. Erection of double pole For HT/LT Line and complete work as per RESSPO Norms.PCC 8.5Mtr/PCC 11Mtr./PCC 9Mtr/STP 11Mtr/STP 13Mtr Pole Please Enable Macros to View BoQ information |
| 45 | Double pole structure with ST/PCC Poles :- Excavation of foundation pit in size of 75x45 cm. having depth of 1/6th of the full length of the support (pole), providing and laying of stone pad (300x300x75mm.) in the bottom of the pit. Erection of double pole For HT/LT Line and complete work as per RESSPO Norms.PCC 8.5Mtr/PCC 11Mtr./PCC 9Mtr/STP 11Mtr/STP 13Mtr Pole Please Enable Macros to View BoQ information |