| 1 | Annual Rate Contract for maintenance/emergent nature / restoration works including improvement/Erection of HT/LT network & Creations falling under the jurisdiction of Electric Division JPDCL Kishtwar for the year 2026-27 |
| 2 | Erection of ST 9 Mtr Pole |
| 3 | Erection of ST 8 Mtr Pole |
| 4 | Erection of ST 11 Mtr Pole |
| 5 | Erection of ST 13 Mtr Pole |
| 6 | Dismantling of ST Pole 8 Mtr Long |
| 7 | Dismantling of ST Pole 9 Mtr Long |
| 8 | Dismantling of ST Pole 11 Mtr Long |
| 9 | Dismantling of ST Pole 13 Mtr Long |
| 10 | Unloading of ST 8 Mtr Pole |
| 11 | Unloading of ST 9 Mtr Pole |
| 12 | Unloading of ST 11 Mtr Pole |
| 13 | Unloading of ST 13 Mtr Pole |
| 14 | Loading of ST 8 Mtr Pole |
| 15 | Loading of ST 9 Mtr Pole |
| 16 | Loading of ST 11 Mtr Pole |
| 17 | Loading of ST 13 Mtr Pole |
| 18 | Average carriage of ST 8 Mtr Pole upto 100 Mtr |
| 19 | Average carriage of ST 8 Mtr Pole upto 100 - 200 Mtr |
| 20 | Average carriage of ST 9 Mtr Pole upto 100 Mtr |
| 21 | Average carriage of ST 9 Mtr Pole upto 100 - 200 Mtr |
| 22 | Average carriage of ST 11 Mtr Pole upto 100 Mtr |
| 23 | Average carriage of ST 11 Mtr Pole upto 100 - 200 Mtr |
| 24 | Average carriage of ST 13 Mtr Pole upto 100 Mtr |
| 25 | Average carriage of ST 13 Mtr Pole upto 100 - 200 Mtr |
| 26 | Straightening of tilted poles long |
| 27 | Installation of Link Set |
| 28 | Installation of DO Set |
| 29 | Installation of HG Set |
| 30 | Installation of GO Set |
| 31 | Installation of LA Set |
| 32 | Average carriage of 25 KVA upto 100 Mtr |
| 33 | Average carriage of 63 KVA upto 100 Mtr |
| 34 | Average carriage of 100 KVA upto 100 Mtr |
| 35 | Average carriage of 25 KVA 100 - 200 Mtr |
| 36 | Average carriage of 63 KVA 100 - 200 Mtr |
| 37 | Average carriage of 100 KVA 100 - 200 Mtr |
| 38 | Average carriage of 250 KVA upto 100 Mtr |
| 39 | Average carriage of 300 KVA upto 100 Mtr |
| 40 | Average carriage of 400 KVA upto 100 Mtr |
| 41 | Average carriage of 500 KVA upto 100 Mtr |
| 42 | Average carriage of 630 KVA upto 100 Mtr |
| 43 | Average carriage of 250 KVA 100 - 200 Mtr |
| 44 | Average carriage of 300 KVA 100 - 200 Mtr |
| 45 | Average carriage of 400 KVA 100 - 200 Mtr |
| 46 | Average carriage of 500 KVA 100 - 200 Mtr |
| 47 | Average carriage of 630 KVA 100 - 200 Mtr |
| 48 | Loading of 25 KVA Transformer |
| 49 | Loading of 63 KVA Transformer |
| 50 | Loading of 100 KVA Transformer |
| 51 | Loading of 250 KVA Transformer |
| 52 | Loading of 300 KVA Transformer |
| 53 | Loading of 400 KVA Transformer |
| 54 | Loading of 500 KVA Transformer |
| 55 | Loading of 630 KVA Transformer |
| 56 | Unloading of 25 KVA Transformer |
| 57 | Unloading of 63 KVA Transformer |
| 58 | Unloading of 100 KVA Transformer |
| 59 | Unloading of 250 KVA Transformer |
| 60 | Unloading of 300 KVA Transformer |
| 61 | Unloading of 400 KVA Transformer |
| 62 | Unloading of 500 KVA Transformer |
| 63 | Unloading of 630 KVA Transformer |
| 64 | Mounting of 25 KVA Transformer |
| 65 | Mounting of 63 KVA Transformer |
| 66 | Mounting of 100 KVA Transformer |
| 67 | Mounting of 250 KVA Transformer |
| 68 | Mounting of 300 KVA Transformer |
| 69 | Mounting of 400 KVA Transformer |
| 70 | Mounting of 500 KVA Transformer |
| 71 | Mounting of 630 KVA Transformer |
| 72 | Erection of Guys in HT Line |
| 73 | Erection of Guys in LT Line |
| 74 | Earthing of Substation complete (Poles,Transformer,CT/PT,LA) |
| 75 | Dismantling of Link Set |
| 76 | Dismantling of DO Set |
| 77 | Dismantling of GO Set |
| 78 | Dismantling of HG Set |
| 79 | Dismantling of LA Set |
| 80 | Erection of Jumper Set HT Side |
| 81 | Erection of Jumper Set LT Side |
| 82 | Dismantling of Jumper Set HT Side |
| 83 | Dismantling of Jumper Set LT Side |
| 84 | Dismounting of 25 KVA Transformer |
| 85 | Dismounting of 63 KVA Transformer |
| 86 | Dismounting of 100 KVA Transformer |
| 87 | Dismounting of 250 KVA Transformer |
| 88 | Dismounting of 300 KVA Transformer |
| 89 | Dismounting of 400 KVA Transformer |
| 90 | Dismounting of 500 KVA Transformer |
| 91 | Dismounting of 630 KVA Transformer |
| 92 | Laying & Stringing of ACSR Squirel Conductor |
| 93 | Laying & Stringing of ACSR Weasel Conductor |
| 94 | Laying & Stringing of ACSR Rabbit Conductor |
| 95 | Laying & Stringing of ACSR Dog Conductor |
| 96 | Dismantling of ACSR Squirrel Conductor |
| 97 | Dismantling of ACSR Weasel Conductor |
| 98 | Dismantling of ACSR Rabbit Conductor |
| 99 | Dismantling of ACSR Dog Conductor |
| 100 | Tightening of loose conductor Squirrel/Weasel |
| 101 | Tightening of loose conductor Rabbit/Dog |
| 102 | Route clearance for making path for Corridor of 5 mtr./KM |
| 103 | Cement Bottoming of PCC/ST Poles of all sizes (Material for Cement Bottoming is to be provided by contractor) 0.5Cum |
| 104 | Fixing of LT Circuit Component of Substation (LT cables,Thimbles,Busbar,Shackle insulators) with Fuse Set / MCCB with Box |
| 105 | Dismantling of LT Circuit Component of Substation (LT cables,Thimbles,Busbar,Shackle insulators) with Fuse Set / MCCB with Box |
| 106 | Branch Cutting |
| 107 | Unloading T & P items i.e Line materials Substations/HT/LT lines |
| 108 | Loading T & P items i.e Line materials Substations/HT/LT lines |
| 109 | Average carriage of T & P items i.e Line materials Substations/HT/LT lines upto 100 Mtr |
| 110 | Average carriage of T & P items i.e Line materials Substations/HT/LT lines 100 - 200 Mtr |
| 111 | Survey/Route Alignment |
| 112 | Drilling of Holes /Each |
| 113 | Fixing/Installation of 11 KV Disc Insulators with fittings |
| 114 | Dismantling of 11 KV Disc Insulators with fittings |
| 115 | Fixing of U-Clamps and Shackle Insulators |
| 116 | Dismantling/Refixing of U-Clamps and Shackle Insulators |
| 117 | Fixing of 11 KV Pin Insulators with Pins |
| 118 | Dismantling of 11 KV Pin Insulators with Pins |
| 119 | Fixing of Top Clamps for Pin Insulators |
| 120 | Dismantling/ Fixing of Top Clamps for Pin Insulators |
| 121 | Fixing of Braces |
| 122 | Dismantling of Braces |
| 123 | Fixing of Danger Plates |
| 124 | Dismantling of Danger Plates |
| 125 | Fixing of Anti Climbing Devices Plates |
| 126 | Painting of Steel Tubular Poles Including Cross arms clamps etc. (Upto 9 Mtr.) (including cost of Paint) |
| 127 | Painting of Steel Tubular Poles Including Cross arms clamps etc. (Above 9 Mtr.) (including cost of Paint) |
| 128 | Painting of Cross arms and Clamps of PCC/Wooden Poles. (including cost of Paint) |
| 129 | Providing of earthing (Spiral/Pipe/Rod Type) including fixing to the pole and cross arm etc. |
| 130 | Fixing of Spacers for LV Lines (for 5 Wire System) |
| 131 | Fixing of Spacers for LV Lines (for 4 Wire System) |
| 132 | Fixing of Spacers for LV Lines (for 3 Wire System) |
| 133 | Fixing of Pre fabricated bracket and cross arm bed for placement of transformer (for transformers upto includiung 250 KVA) |
| 134 | Fixing of MS Channels 8/7/6/5/4/3 feet long along with Braces |
| 135 | Dismantling of MS Channels 5/4/6/3/7/8 feet long along with Braces |
| 136 | Fixing of M S Angle Iron 9 feet long crossarm |
| 137 | Fixing of MS Angle Iron 5/4/3 feet long crossarm |
| 138 | Unloading of CT/PT Unit |
| 139 | Average carriage of CT/PT Unit upto 100 Mtr |
| 140 | Average carriage of CT/PT upto 100 - 200 Mtr |
| 141 | Erection of CT/PT Unit along with Trivector Meter |
| 142 | Erection of CTPT Unit |
| 143 | Testing and commissioning of CT/PT Unit |
| 144 | Fixing of Suspension/Anchoring Clamps |
| 145 | Laying of HT AB Cable 35 mmsq |
| 146 | Laying of HT AB Cable 50 mmsq |
| 147 | Laying of HT AB Cable 70 mmsq |
| 148 | Laying of HT AB Cable 95 mmsq |
| 149 | Laying of HT AB Cable 120 mmsq |
| 150 | Laying of HT AB Cable 185 mmsq |
| 151 | Laying of HT AB Cable 300 mmsq |
| 152 | Laying of HT AB Cable 400 mmsq |
| 153 | Laying of HT XLPE Cable 35 mmsq |
| 154 | Laying of HT XLPE Cable 50 mmsq |
| 155 | Laying of HT XLPE Cable 70 mmsq |
| 156 | Laying of HT XLPE Cable 95 mmsq |
| 157 | Laying of HT XLPE Cable 120 mmsq |
| 158 | Laying of HT XLPE Cable 185mmsq |
| 159 | Laying of HT XLPE Cable 300 mmsq |
| 160 | Laying of HT XLPE Cable 400 mmsq |
| 161 | Laying of LT AB Cable 35 mmsq |
| 162 | Laying of LT AB Cable 50 mmsq |
| 163 | Laying of LT AB Cable 70 mmsq |
| 164 | Laying of LT AB Cable 95 mmsq |
| 165 | Laying of LT AB Cable 120 mmsq |
| 166 | Laying of LT AB Cable 185 mmsq |
| 167 | Laying of LT AB Cable 300 mmsq |
| 168 | Laying of LT AB Cable 400 mmsq |
| 169 | Laying of LT XLPE Cable 35 mmsq |
| 170 | Laying of LT XLPE Cable 50 mmsq |
| 171 | Laying of LT XLPE Cable 70 mmsq |
| 172 | Laying of LT XLPE Cable 95 mmsq |
| 173 | Laying of LT XLPE Cable 120 mmsq |
| 174 | Laying of LT XLPE Cable 185 mmsq |
| 175 | Laying of LT XLPE Cable 300 mmsq |
| 176 | Laying of LT XLPE Cable 400 mmsq |
| 177 | Dismantling of HT AB Cable 35 mmsq |
| 178 | Dismantling of HT AB Cable 50 mmsq |
| 179 | Dismantling of HT AB Cable 70 mmsq |
| 180 | Dismantling of HT AB Cable 95 mmsq |
| 181 | Dismantling of HT AB Cable 120 mmsq |
| 182 | Dismantling of HT AB Cable 185mmsq |
| 183 | Dismantling of HT AB Cable 300 mmsq |
| 184 | Dismantling of HT AB Cable 400 mmsq |
| 185 | Dismantling of HT XLPE Cable 35 mmsq |
| 186 | Dismantling of HT XLPE Cable 50 mmsq |
| 187 | Dismantling of HT XLPE Cable 70 mmsq |
| 188 | Dismantling of HT XLPE Cable 95 mmsq |
| 189 | Dismantling of HT XLPE Cable 120 mmsq |
| 190 | Dismantling of HT XLPE Cable 185mmsq |
| 191 | Dismantling of HT XLPE Cable 300 mmsq |
| 192 | Dismantling of HT XLPE Cable 400 mmsq |
| 193 | Dismantling of LT AB Cable 35 mmsq |
| 194 | Dismantling of LT AB Cable 50 mmsq |
| 195 | Dismantling of LT AB/ Cable 70 mmsq |
| 196 | Dismantling of LT AB Cable 95 mmsq |
| 197 | Dismantling of LT AB Cable 120 mmsq |
| 198 | Dismantling of LT AB Cable 185 mmsq |
| 199 | Dismantling of LT AB Cable 300 mmsq |
| 200 | Dismantling of LT AB Cable 400 mmsq |
| 201 | Dismantling of LT XLPE Cable 35 mmsq |
| 202 | Dismantling of LT XLPE Cable 50 mmsq |
| 203 | Dismantling of LT XLPE Cable 70 mmsq |
| 204 | Dismantling of LT XLPE Cable 95 mmsq |
| 205 | Dismantling of LT XLPE Cable 120 mmsq |
| 206 | Dismantling of LT XLPE Cable 185 mmsq |
| 207 | Dismantling of LT XLPE Cable 300 mmsq |
| 208 | Dismantling of LT XLPE Cable 400 mmsq |
| 209 | Tightening of loose HT Cable AB/XLPE |
| 210 | Tightening of loose LT Cable AB/XLPE |
| 211 | Fixing of Heat Shrinkable Outdoor Kit for AB/XLPE cables of HT Lines |
| 212 | Fixing of Straight Through Cable Jointing Kit for AB/XLPE cables of LT Lines |
| 213 | Dismantling of M S Angle Iron 9 / 7 / 6 feet long |
| 214 | Dismantling of MS Angle Iron 5/4/3 feet long |
| 215 | Construction of Cemented Platform (8x8x6 feet) for 630/400 KVA Substation along with Mesh Fencing of 6 feet height( If Material to be provided by department for this item) |
| 216 | Construction of Cemented Platform (8x8x6 feet) for 630/400 KVA Substation along with Mesh Fencing of 6 feet height( If Material to be provided by Contractor for this item) |
| 217 | Fixing of IPC 120/50mm |
| 218 | Service connection (Domestic/Commercial) |
| 219 | Laying of LT PVC Single Core Cable 95 mmsq |
| 220 | Laying of LT PVC Single Core Cable 120 mmsq |
| 221 | Laying of LT PVC Single Core Cable 185 mmsq |
| 222 | Laying of LT PVC Single Core Cable 300 mmsq |
| 223 | Laying of LT PVC Single Core Cable 400 mmsq |
| 224 | Laying of LT PVC Single Core Cable 630 mmsq |
| 225 | Fixing of Al. Thimbles of different Sizes 95 mmsq |
| 226 | Fixing of Al. Thimbles of different Sizes 185 mmsq |
| 227 | Fixing of Al. Thimbles of different Sizes 300 mmsq |
| 228 | Fixing of Al. Thimbles of different Sizes 400 mmsq |
| 229 | Fixing of Al. Thimbles of different Sizes 630 mmsq |
| 230 | Fixing of Aluminium Jointing Sleeves |
| 231 | Fixing of Suspension/Tension Clamp with eye hook |
| 232 | Fixing of Wedge connectors/PG Clamps |
| 233 | Fixing of GI Barbed wire for anti climbing |
| 234 | Sundry items like aluminium Lugs, jumpers, binding , Tape. |
| 235 | Fixing of LT Distribution Box for 63/100 KVA DTR with MCCB for incomer & SFU's for Outgoing Circuits |
| 236 | Fixing of LT Distribution Box for 200/250/300/400 KVA DTR with MCCB for incomer & SFU's for Outgoing Circuits |
| 237 | Laying of 3 and a half core PVC 95 mmsq LT XLPE Cable/ AB Cable |
| 238 | Fixing of LT Distribution Box for 500/630 KVA DTR with MCCB for incomer & SFU's for Outgoing Circuits |
| 239 | Fixing of Nuts & Bolts |
| 240 | Fabrication of steel |
| 241 | Mounting/Unmounting of Distribution Transformers per Hour basis through Mechanical means Please Enable Macros to View BoQ information |