| 1 | Carriage of the following material from Store Centre, Rampur to work site including loading & unloading. |
| 2 | PCC Pole 11 Mtr Long |
| 3 | PCC Pole 9 Mtr Long |
| 4 | PCC Pole 8.5 Mtr Long |
| 5 | 11 KV VCB O/G CTR 200/100/5A (1250 amp) |
| 6 | 11 KV V Type X Arm |
| 7 | ACSR Dog (In Mtr) |
| 8 | ACSR Weasal Conductor |
| 9 | ACSR Rabbit Conductor (In Mtr) |
| 10 | Pin insulator with fitting |
| 11 | Polymeric 11 KV Disc Insulator |
| 12 | Polymeric 11 KV Pin Insulator |
| 13 | Disc fitting T & C with 45 KN |
| 14 | Disc insulator T & C 45 KN |
| 15 | Earthing of Pole |
| 16 | Distibution box |
| 17 | Stay Set Complete |
| 18 | 11 KV Fuse Set |
| 19 | G.I. Wire 6 Swg |
| 20 | GI Wire for Contenary Cable |
| 21 | G.I wire 8 Swg |
| 22 | AB Cable (3x120+1x795+1x16) sq mm |
| 23 | AL. LT Armourd XLPE CABLE 3.5X50 Sq |
| 24 | 11 KV 3X70 Sqmm XPLE Cable |
| 25 | 11 KV 3x185 Sqmm XLPE Cable |
| 26 | Jointign Kit Indoor(3x185) |
| 27 | 11 KV Jointing Kit O/D 3X70 |
| 28 | Jointign Kit Out door(3x300) |
| 29 | Jointign Kit Out door(3x185) |
| 30 | GI Scarp(Recived Back Site to Store) |
| 31 | AL Scrap(in Kg)(Recived Back Site to Store) |
| 32 | Meltabal Steel Scrap (kg)(Recived Back Site to Store) |
| 33 | ACSR DOG Conductor(Recived Back Site to Store) |
| 34 | AB Contuctor Clamp(Recived Back Site to Store) |
| 35 | ACSR Weasal (Recived Back Site to Store) |
| 36 | Old damage 11 KV XLPE Cable(Recived Back Site to Store) |
| 37 | a) Single/Double support structure as required (rate given by for single pole )Excavation of foundation Pit in size of 75x45cm having depth of 1/6th of the full length of the support(pole), providing and laying of stone pad (300x300x75 mm) in the Bottom of the pit. Erection of support(pole) complete with fixing of 11 KV V-type cross-Arms and other accessories by providing clamps made of MS flat of size 65x65xc6 mm with Nuts & Bolts, as per RESPO Norms. |
| 38 | 11 Mtr long PCC Pole |
| 39 | 9 Mtr long PCC Pole |
| 40 | 8.5 Mtr long PCC Pole |
| 41 | Grouting of support in CC 1:4:8(cement, sand & 40 mm. brick ballast) Grouting will be done in the block of size 45x45cmx1/6th of full length of the support upto ground level, 30 cm plinth above the ground level with CC 1:3:6 (cement, course sand and stone grit) with muffing. The work includes back filling and proper ramming etc.Single/Double support structure(rate given by for single pole ) |
| 42 | 11 Mtr long PCC Pole |
| 43 | 9 Mtr long PCC Pole |
| 44 | 8.5 Mtr long PCC Pole |
| 45 | Earthing of support with MS Earth Rod of (20x2500)mm long including excavation of pit and driving MS Rod 3.0 M apart from support and 0.5 M below the ground level and connecting below the earth electrodes with the help of GI wire No. 8SWG and earthing lugs. |
| 46 | Grouting of Stay Rods(20x1800)mm including all work of excavation, cement concrete in size of (0.60x0.60x0.30)M in the ratio of 1:4:8(cement, sand, 40mm brick ballast) including back filling of soil and proper ramming etc. |
| 47 | Fixing, tightening and nozelling of stay wire with stay rod with the pole of required tension by providing stay clamps. |
| 48 | fixing of 11 KV Pin Insulator with Pin as per RESPO Norms and as per direction of Supervising Engineer. |
| 49 | fixing of 11 KV Disc Insulator with Fitting as per RESPO Norms and as per direction of Supervising Engineer. |
| 50 | fixing of 11 KV 11 KV VCB O/G CTR 200/100/5A (1250 amp) as per RESPO Norms and as per direction of Supervising Engineer. |
| 51 | fixing of Distribution Box as per RESPO Norms and as per direction of Supervising Engineer. |
| 52 | fixing of 11 KV Fuse Set as per RESPO Norms and as per direction of Supervising Engineer. |
| 53 | laying ,stringing and binding of 11 KV 3x120 Sqmm XLPE Cable with the help of cable jointing kit as per RESPO Norms and as per direction of Supervising Engineer. |
| 54 | laying ,stringing and binding of LT Armourd XLPE Cable 3.5X50 Sqmm with the help of cable jointing kit as per RESPO Norms and as per direction of Supervising Engineer. |
| 55 | laying ,stringing and binding of 11 KV 3x70Sqmm XLPE Cable with the help of cable jointing kit as per RESPO Norms and as per direction of Supervising Engineer. |
| 56 | laying ,stringing and binding of 11 KV 3x185 Sqmm XLPE Cable with the help of cable jointing kit as per RESPO Norms and as per direction of Supervising Engineer. |
| 57 | laying ,stringing and binding of ACSR Rabbit Conductor as per RESPO Norms and as per direction of Supervising Engineer. |
| 58 | laying ,stringing and binding of ACSR Dog Conductor as per RESPO Norms and as per direction of Supervising Engineer. |
| 59 | laying ,stringing and binding of ACSR Weasal Conductor as per RESPO Norms and as per direction of Supervising Engineer. |
| 60 | Providing and fixing Top Channel as per RESPO Norms and as per direction of Supervising Engineer. |
| 61 | Providing and fixing Dropper Channel as per RESPO Norms and as per direction of Supervising Engineer. |
| 62 | Providing and fixing of Cross Breacing Sets per RESPO Norms and as per direction of Supervising Engineer. |
| 63 | Providing and fixing and laying of HDPE pipe 80 PN 200 Dia with all respect (if underground required) as per RESPO Norms and as per direction of Supervising Engineer. |
| 64 | Providing and fixing and laying of HDPE pipe with all respect (if underground required) as per RESPO Norms and as per direction of Supervising Engineer. |
| 65 | Guarding of of Line by G.I. wire 6 swg and 8 swg wire as per RESPO Norms and as per direction of Supervising Engineer |
| 66 | fixing of G.I. wire for Contenary Cable as per RESPO Norms and as per direction of Supervising Engineer |
| 67 | Providing and fixing of MS Angle for side bracket as RESPO Norms and as per direction of Supervising Engineer |
| 68 | Providing and fixing of Clamp for X-Arm with Nut and bolt per RESPO Norms and as per direction of Supervising Engineer. |
| 69 | Providing and fixing E Bracket per RESPO Norms and as per direction of Supervising Engineer |
| 70 | Providing and fixing F Bracket per RESPO Norms and as per direction of Supervising Engineer |
| 71 | Providing and fixing Stone Pad per RESPO Norms and as per direction of Supervising Engineer |
| 72 | Providing and fixing Clamp with Nut bolt for DB RESPO Norms and as per direction of Supervising Engineer |
| 73 | Providing and fixing GI Pipe 6\\" Dia RESPO Norms and as per direction of Supervising Engineer |
| 74 | Laying of Cable by drilling and digging as RESPO Norms and as per direction of Supervising Engineer |
| 75 | Laying of Cable by digging, Brick and sand as RESPO Norms and as per direction of Supervising Engineer |
| 76 | laying of 3x70 Cable RESPO Norms and as per direction of Supervising Engineer |
| 77 | Providing and fixing of Guarding Angle RESPO Norms and as per direction of Supervising Engineer |
| 78 | Providing and fixing Holding Clamp RESPO Norms and as per direction of Supervising Engineer |
| 79 | Providing and fixing 11 KV O/D joint Kit as per RESPO Norms and as per direction of Supervising Engineer |
| 80 | Providing and fixing Clamp for X arm as per RESPO Norms and as per direction of Supervising Engineer |
| 81 | Providing and fixing Cable Route Marker as per RESPO Norms and as per direction of Supervising Engineer |
| 82 | Providing and fixing of AL Lug RESPO Norms and as per direction of Supervising Engineer |
| 83 | Providing and fixing J Hook RESPO Norms and as per direction of Supervising Engineer |
| 84 | Providing and fixing Pearcing Clamp as per RESPO Norms and as per direction of Supervising Engineer |
| 85 | Providing and fixing Dead and Clamp as per RESPO Norms and as per direction of Supervising Engineer |
| 86 | Providing and fixing MS Clamp as per RESPO Norms and as per direction of Supervising Engineer |
| 87 | Providing and fixing Suspension Clamp as per RESPO Norms and as per direction of Supervising Engineer |
| 88 | Dismentaling of old and used GI Scrap as RESPO Norms and as per direction of Supervising Engineer |
| 89 | Dismentaling of old and used AL Scrap as RESPO Norms and as per direction of Supervising Engineer |
| 90 | Dismentaling of old and used Meltabal Steel Scrapas RESPO Norms and as per direction of Supervising Engineer |
| 91 | Dismentaling of old and used ACSR Dog conductor as RESPO Norms and as per direction of Supervising Engineer |
| 92 | Dismentaling of old and used ACSR AB Contuctor Clamp conductor as RESPO Norms and as per direction of Supervising Engineer |
| 93 | Dismentaling of old and used ACSR weasel conductor as RESPO Norms and as per direction of Supervising Engineer |
| 94 | Dismentaling of old and used 11 KV XLPE Cable as RESPO Norms and as per direction of Supervising Engineer Please Enable Macros to View BoQ information |