| 1 | Fitting and providing one HT Stay for11kV pole, including digging and backfilling pit in ordinary soil |
| 2 | Fitting one No. Section fuse on LT linewith dropping cables, crimping sockets,connecting with bolt & nut etc |
| 3 | Erecting one LT PSC Pole in position including digging & back filling pit in ordinary soil |
| 4 | Dismantling one Transformer (upto and including 160kVA) from existing structure and loading to any vehicle directly, including disconnecting HT/LT earth connections |
| 5 | Transferring LT single phase 2/3 wireOH line to newly erected HT/LT poleincluding dismantling existing cross armand insulators, refitting the same on thenew pole, binding etc. complete |
| 6 | Transferring LT three phase 4/5 wire OHline to newly erected HT/LT poleincluding dismantling existing cross armand insulators, refitting the same on thenew pole, binding etc. complete. |
| 7 | Fitting and erecting one HT Double PoleStructure using A type pole in positionincluding fitting 2 No. channel crossarm, digging and back filling pit inordinary soil, drawing sufficient lengthof GI earthing leads through all crossarms to the ground for earthing(excluding provision of earthing). |
| 8 | Dismantling one damaged 11kVPSC/RCC pole after disconnecting stays,strut etc. attached thereon and stackingthe same. |
| 9 | Providing concrete muffing of size0.45x0. 45x1.5m (0.5m above GL and1m below GL). Excavation 0.45x0.45x1m, concrete (1:3:6, 20mm)0.45x0.45x1.5m, Plastering (1:3) 12mm0.45x0.45mx5sides |
| 10 | Providing WP support with PSC poleincluding digging & back filling pit inordinary soil. excluding transportation ofpoles. |
| 11 | Drilling hole of various sizes on existingChannel/Cross Arm |
| 12 | Fitting one set AB switch on existingDP, giving connection and drawingsufficient length of GI earthing leads tothe ground for earthing, excludingprovision of earthing |
| 13 | Fitting one Additional 2.4m/3m Channelcross arm (100x50x6mm), in existing11kV DP including conveyance ofmaterials. |
| 14 | Providing one Earth using GI earth pipeof size 38.1mm dia, 2.5m lengthincluding digging separate pit(0.45x0.45x2.5m) at standard distance(1.5m) away from the pole/structure inordinary soil & backfilling the pit with15cm alternate layer of charcoal, salt andsand up to 90cm from the bottom.including the cost of 20kg salt, 25kgcharcoal, excluding supply of earth p |
| 15 | Fitting and erecting one HT Double PoleStructure using PSC pole in positionincluding fitting 2 channel cross arms,digging and back filling pit in ordinarysoil, drawing sufficient length of GIearthing leads through all cross arms tothe ground for earthing (excludingprovision of earthing). |
| 16 | Erecting one 100kVA Transformer toexisting DP and giving connections,including loading from TMR/SRS/otherstacking place & unloading at site butexcluding cost for transportingtransformer. |
| 17 | Dismantling (without damage) one LTPSC/RCC pole after disconnecting stays,strut etc. attached thereon and stackingthe same |
| 18 | Dismantling (without damage) one kmLT single phase 2 wire OH lineconductor by dismantling cross arms,insulators and stacking the conductors inrolls properly |
| 19 | Dismantling transformer station withtransformer erected in DP structure by dismantling HT Double Pole Structure using PSC pole after disconnecting staywires, 10 channel cross arms,AB switch,DO fuse, LA, GI earthing leads, DTRmeter with box with meteringequipments, CTs, Distribution Box,statutory display boards etc. butexcluding the rate of dismantlingtransformer, earthing, stay sets &fencing |
| 20 | Dismantling (without damage) one HTPSC/RCC Strut pole including removalof clamps and stacking |
| 21 | Dismantling (without damage) one Vcross arm/Channel cross arm fromexisting Pole and bringing back tosection store. |
| 22 | Dismantling (without damage) oneChannel cross arm from existing DPstructure and bringing back to sectionstore. |
| 23 | Additional rate for providing one discset, PG clamp etc. complete, on any typeof HT pole for making cut point |
| 24 | Fitting 5 channel cross arms, AB switch,DO fuse, LA(Ord), HT & LTconnections upto OH lines, etc. onexisting DP structure, Fixing distributionbox/provision for one set (3No.) of LTfuses, , drawing sufficient length of GIearthing leads to the ground for earthing,excluding provision of earthing &mounting of Transformer on poles |
| 25 | Fitting one Additional V cross arm inexisting single pole includingconveyance of materials |
| 26 | Fitting one additional Fuse unit andgiving connection from Transformer tofuse and Distribution box to LT OH line |
| 27 | Fitting and erecting one HT PSC Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing) |
| 28 | Erecting one 25kVA Transformer toexisting DP and giving connections,including loading from TMR/SRS/otherstacking place & unloading at site butexcluding cost for transportingtransformer. |
| 29 | Fitting and providing one HT Fly stayfor 11kV pole using HT PSC poleincluding digging and back filling pits inordinary soil, drawing sufficient lengthof GI earth leads to the ground forearthing (excluding provision ofearthing). |
| 30 | Transporting poles by hired vehicle to adistance beyond 5km and carrying upto4 numbers of poles. (Running km) |
| 31 | Stringing of one km 11kV line withACSR Raccoon (3 conductors) afterfitting insulators and giving jumperconnections including cutting andremoving tree branches wherevernecessary excluding cut point works |
| 32 | Fitting and erecting one HT A typeSingle Pole in position, including fittingcross arm, digging and back filling pit inordinary soil (as per standards), drawingsufficient length of GI earthing leadsfrom F clamp through V cross arm to theground for earthing (excluding provisionof earthing). |
| 33 | Fitting one Additional 75x40mm, 1.8mChannel cross arm in existing single poleincluding conveyance of ma |
| 34 | Additional rate for excavation of one Pitfor LT Pole/LT Stay in Laterite |
| 35 | Additional rate for excavation of one Pitfor LT Pole/LT Stay in Hard Lat |
| 36 | Providing one Coil Earth using No.8 GIearthwire (50mm dia, 115 turns)including digging separate pit(0.45x0.45x1.5m) at standard distanceaway from the pole/structure in ordinarysoil & backfilling. |
| 37 | Disconnecting and lowering down thesingle phase WP service connection withguy wire from the OH line andreconnecting the same after completingthe line work |
| 38 | Disconnecting and lowering down thethree phase WP service connection withguy wire from the OH line andreconnecting the same after completingthe line work |
| 39 | Dismantling (without damage) one LTPSC/RCC Strut pole including removalof clamps and stacking |
| 40 | Dismantling one damaged LT PSC/RCCpole after disconnecting stays, strut etc.attached thereon and stacking the same |
| 41 | Providing Cable Tie |
| 42 | Labour charges for loading HT PSC polefrom the stacking place and unloadingthe same at work site (transportation byany vehicle). |
| 43 | Transporting poles by hired vehicle to adistance upto 5km and carrying upto 4numbers of poles excluding loading&unloading charges. |
| 44 | Dismantling (without damage) one ABswitch from existing structure andbringing back to section store. |
| 45 | Dismantling (without damage) one km11kV line (three conductors) includingdismantling cross arm, insulators, disc,disconnecting jumper connection, rollingthe conductor and stacking the materials |
| 46 | Dismantling one damaged HT PSC/RCCStrut pole including removal of clampsand stacking. |
| 47 | Dismantling (without damage) one 11kVA type pole after disconnecting stays,strut etc. attached thereon and stackingthe same. |
| 48 | Dismantling (without damage) one kmLT three phase 4 wire OH line conductorby dismantling cross arms, insulatorsand stacking the conductors in rollsproperly. |
| 49 | Fitting and providing one Strut using HTPSC pole including digging and backfilling pit in ordinary soil. |
| 50 | Dismantling one suspension clamp from11 KV ABC |
| 51 | Dismantling one Anchor clamp /deadend clamp from 11 KV ABC |
| 52 | Dismantling of 11 kV Aerial bunchedcable XLPE insulated of size 3 x 120+ 1x 95 sqmm with bare insulatedMessenger |
| 53 | Erection of suspension clamp for 11KVABC of any size |
| 54 | Erection of Anchor clamp / dead endclamp for 11kV ABC of any size |
| 55 | Stringing of 11 kV Aerial bunched cableof size 3 x 120 + 1 x 95 sqmm withbare/insulated Messenger throughexisting poles |
| 56 | Fiting One no MVT on existing crossarm including 2 nos end termination (forOne phase) of any rating for 11 kV AB cable |
| 57 | Labour charges for loading LT PSC polefrom the stacking place and unloadingthe same at work site (transportation byany vehicle). |
| 58 | Dismantling (without damage) one 11kVPSC/RCC pole after disconnecting stays,strut etc. attached thereon and stackingthe same |
| 59 | Stringing, shackling, fitting cross arms,insulators and binding, giving jumperconnection etc. using ACSR Rabbit forPhase and Neutral, for one km LT singlephase 2 wire line including cutting andremoving tree branches wherevernecessary and conveyance of allmaterials (except poles) from stacking place |
| 60 | Stringing, shackling, fitting cross arms,insulators and binding, giving jumperconnection etc. using ACSR Rabbit forPhase and ACSR Weasel for Neutral, forone km LT three phase 4 wire lineincluding cutting and removing treebranches wherever necessary andconveyance of all materials (exceptpoles) from stacking place. |
| 61 | Conveyance of one km 11kV linematerials from section store/stackingplace to the work site (excluding poles). |
| 62 | Providing Stay for LT poles includingdigging & back filling pit in ordinarysoil. |
| 63 | Providing Strut using LT PSC poleincluding digging and back filling pit inordinary soil. Please Enable Macros to View BoQ information |