| 1 | Excavation in foundation in ordinary soil (Loam, clay or sand) Including lift upto 1.50 M and lead upto 30 M and including filing watering and rammind of excacated earth into the treaches or into the space between the building and the sides of foundation trenchs or into the plinth and removal and disposal of surplus earth as directed by the engineer in charge upto a distance of 30 M from the foundation trenches SOR UP PWD S1-251A) |
| 2 | Concrete with 4 cm gauge brick ballast fine sand and cement in proportion are 1:6:12 in foundation and under floors, including supply of all materials, labour. T&P etc. required for proper completion the work |
| 3 | M-150 Brick work in 1:4 one cement and four course sand, mortar in foundation in plinth including supply of all material labour, T &P etc. required for proper completion of the work. |
| 4 | 2.50 cm. thick DPC with 1:1.5:3 with 10mm Stone grite inclding labour T&P etc all complete |
| 5 | M-150 Brick work in 1:4 one cement and four course sand, mortar in foundation in plinth including supply of all material labour, T &P etc. required for proper completion of the work. |
| 6 | 12 mm thick plaster with cement and approved c sand mortar in 1:4 over brick work minium thickness not to be less than 1 Cm including supply of all material labour Tool & Plants etc. required for proper completion of the work. |
| 7 | Earth work in filling upto 8 km distance frome site including loading unloading cartage etc complete (anallises Rate) |
| 8 | Cemant concrete with 4cm Gauge stone Ballast Fine sand of 1.25 FM and cemant in Proportion of 4:2:1 in Founfation including supply of all matrial labour and tools and plant for proper complition of work (S.I.No. 279) |
| 9 | Chequerred precast cement concrete tiles 22m thick in footpath & courtyard in all complete work |
| 10 | R.C.C. Work with cement, approved coarse sand & 2 cm gauge approved stone grit in proportions of 1:1.5:3 in slab/ nall with all comp of work |
| 11 | M.S. (tor steel or plain) in Plain work such as R.C.C. or R.B. work including bending for proper shape and including supply of steel & its wastage, bend, hooks, and authorised overlapping shall be measured and including cost of binding wire. |
| 12 | M.S iron work as per reinforcement in all complete work |
| 13 | Painting or varnishing work in small area or new with Two coat of approved suprior quality |
| 14 | Supply and fixing of 6 mm thick china white glazed tiles including or in skirting or dado laid with 1:3 cement and c,Sand mortar finished with white cement slurry jointing and polishing complete including supply of all material complete of the work.( Size of tiles up to 200x300mm) |
| 15 | Suuply and fixing galvanized corrugated iron roofing 24 BWG in position in all complete work |
| 16 | Providing of wall putty with all material labour T&P etc all complete |
| 17 | Two coat painting with all material labour T&P etc all complete |
| 18 | Providing and fixing wash basin with C.I brackets 15mm CP brass pillar taps 32mm CP brass waste of standard pattern in all complete work |
| 19 | Providing and fixing white vitreous china extended wall mounting water closet of size in all complete work |
| 20 | Providing and fixing of Indian Type W.C. Pan in all complete |
| 21 | Supply and fixing of C.P brass 15mm dia angle valve in all complete work |
| 22 | Supply and fixing of bib cock 15mm dia in all complete work |
| 23 | Supply and fixing of C.P brass long bib cock 15mm dia angle value in all complete work |
| 24 | Supply and fixing of C.P step cock 15mm dia angle value in all complete work |
| 25 | Supply and fixing of C.P brass 15mm dia angle value in all complete work |
| 26 | as per item no.730 above but for 10.0cm PVC down pipe kissan/suprime make in all complete work |
| 27 | Water supply work in all complete work |
| 28 | Providing and placing on terrace at all floor levels polyethylene water storage tank 12701 marked in all complete work |
| 29 | Fixing of PVC water tank in all complete |
| 30 | Designing, fabrication, testing, installation and fixing in position curtain wall with aluminium compasite panel cladding in all complete work |
| 31 | Add 5% electrification |
| 32 | Add 18%GST Please Enable Macros to View BoQ information |