| 1 | Excavation in trenches not exceeding 1.5 Mtr wide and not exceeding 1.5 mtr depth for laying cable at and getting out in soft/ loose soil all as specified and directed. |
| 2 | Excavating in trenches, n exc 1.5 m wide and exceeding 1.5 m not exceeding 3 m in depth for foundation, etc. or for shafts, wells, cesspits, manholes, pier holes, etc. n exc 10 sq m on plan and n exc 1.5 m in depth and getting out in Hard / Dense soil complete all as specified. |
| 3 | Returning, filling in soil including spreading, levelling, watering and well ramming in layers, not exceeding 25 cm thick all as specified and directed |
| 4 | Removing surplus soil to a distance not exceeding 50 Mtr and deposited at a level not exceeding 1.5 mtr above from the starting point all as specified |
| 5 | Supply and spread Riddle sand in trenches for cable cushioning including watering and consolidation all as specified.Note: For the purpose of payment punned thickness only will be measured. |
| 6 | Supplying and laying reinforced precast concrete cable cover, Class LV, Type I, flat, size 250 mm x 150mm x 40mm complete all as specified and directed. |
| 7 | M&L for PCC 1:3:6 type C2 (40mm graded aggregates) as in foundation, filling and mass concrete complete all as specified. |
| 8 | M&L for cement concrete 1:3:6 type C-1 using 20mm graded stone aggregates as in coping / pedestal of poles including necessary formwork complete all as specified. |
| 9 | Supplying, laying, jointing, testing and commissioning 1100 volts grade, LT XLPE insulated, PVC sheathed as per IS-7098 (Part-I), 1988 galvanized steel strip or wire armoured, heavy duty, electric cables, with multistranded aluminium conductor laid in trenches/ passing through pipe/ duct/ road crossing or fixed on poles, walls with suitable size clamps made out of mild steel flat iron including jointing material such as crimping type lugs, brass cable glands, heavy duty double compression type etc., including taking down unserviceable cable complete all as specified and directed.Note: Earthwork Excavation, sand cushioning GI pipe and cable protection will be measured and paid separately. |
| 10 | All as per item No. 9.00 above 3.5 core 185 Sqmm |
| 11 | All as per item No. 9.00 above 3.5 core 150 Sqmm |
| 12 | All as per item No. 9.00 above 3.5 core 120 Sqmm |
| 13 | All as per item No. 9.00 above 3.5 core 95 Sqmm |
| 14 | All as per item No. 9.00 above 3.5 core 70 Sqmm |
| 15 | All as per item No. 9.00 above 3.5 core 50 Sqmm |
| 16 | All as per item No. 9.00 above 3.5 core 35 Sqmm |
| 17 | All as per item No. 9.00 above 3.5 core 25 Sqmm |
| 18 | All as per item No. 9.00 above 4 core 16 Sqmm |
| 19 | All as per item No. 9.00 above 4 core 10 Sqmm |
| 20 | Supply and laying in trenches of 40 mm dia DWC HDPE pipe, Heavy Duty, conforming to IS 16205 Part 24, made of HDPE, with corrugated outer wall and smooth inner bore, suitable for passing 1.1 kV, 4C x 10 sqmm to 3.5C x 35 sqmm XLPE cable, including cost of couplers, jointing accessories, end caps, and laying as per site requirement Complete all as specified and directed by Engr-in-Charge direction. Make: SFMC, Reliance, Supreme.Note: Higher Grade IS compatible for Electrical cable protection is acceptable as approved by GE. |
| 21 | All as per item No. 10.00 above 90 mm dia |
| 22 | All as per item No. 10.00 above 110 mm dia |
| 23 | Supply and fix, Street light control junction box 230 x 170 x 105mm up to 25 Sqmm 3.5/ 4 core cables made out of FRP sheet moulded and arrangement for incoming and outgoing 3 phase 4 wire system with R, Y, B & N studs and control for incoming and outgoing cables with MCB SP 10 Amp 230 volts with neutral link including pole mounting kit, completed all as specified and directed.Make: HENSEL, HAGER, LEGRAND, PHOENIX.Note: Volume of the junction box should not be below the given specification as directed by GE. Please Enable Macros to View BoQ information |
| 24 | Supply and fix, Street light control junction box 230 x 170 x 105mm up to 25 Sqmm 3.5/ 4 core cables made out of FRP sheet moulded and arrangement for incoming and outgoing 3 phase 4 wire system with R, Y, B & N studs and control for incoming and outgoing cables with MCB SP 10 Amp 230 volts with neutral link including pole mounting kit, completed all as specified and directed.Make: HENSEL, HAGER, LEGRAND, PHOENIX.Note: Volume of the junction box should not be below the given specification as directed by GE. Please Enable Macros to View BoQ information |