| 1 | Dismantling of motor and pump with the help of chain pulley from bed to clear the foundation surface for repair of bed No 10 complete in all respect at W/w Sec.32, Chandigarh. |
| 2 | Fabrication of extension of channel frame as per existing supporting frame and welding with the existing frame & providing holes for the bolt by use of gas cutter complete as per site requirement complete in all respectbed No 10 at W/W-32, Chd |
| 3 | Drilling holes all along the periphery at pre-determined location and providing M 20 x 170/108-500-5-D/500/1 SS has-e-rods and RE 500 compound complete in all respect bed No 10 W/W-32, Chd |
| 4 | Providing and fixing of extra MS flat 2.5mm thick of size 1mmx0.1mm under the existing beds for the strengthening the foundation i/c cost of dismantling, cement and concrete complete. |
| 5 | Refixing of motor and pump after repier of bed complete in all respects |
| 6 | Dynamic Balancing of rotating assembly complete in all respects |
| 7 | Repairing of DV 50 vacuum pump with rewinding of motor including cost of copper wire, F class insulation paper, epoxy wedge Dr beck varnish, red becktrol, connection glass lead and repair of bearing 6308 2 No. repair of pump bush, neck ring, breazing o impellor fins, repari of bearing 6307-2 No, packing sheet, gland dori, nut bolt, repair of bed etc. complete at water works sector-26 & 32, Chandigarh. |
| 8 | Providing and fixing of 120mm2 copper conductor cable in slipring motor from starter to motor and regulator to slipring holder and flexible PVC pipe, crimping of copper thimble and glass taping, PVC taping nut bolt with washer etc complete in all respect in old pump house at water works sec 26 & 32 Chd make Havells/BCH/L&T |
| 9 | Providing and fixing of carbon brush holder for various slipring motors at water works sec 26 and 32 , Chd |
| 10 | Providing and fixing of carbon brush in various slipring motor at water works sec 26 and 32 ,Chd |
| 11 | Providing and fixing of contact block 3 pole model LC-IFDP 225 3 AC3-225 amp in water type regulator installed at bed No 5 Kirloskar side at water works sec 26, Chd make C&S, BCH, L&T |
| 12 | Providing and fixing of coupling with tyre i/c cost of machining boring, dismantling of old damaged coupling at 430 HP in kirloaskar side at water works sec 26, Chandigarh |
| 13 | Replacement by P/F of flexible coupling pin type i/c cost of rubber bush and pins etc suitable for centrifugal pump coupled with slipring motor installed at water works sec 26, Chd |
| 14 | Repairing, testing of ABB soft starter PSTB 370-600-70 by replacement of ABB make PSPCB, HV PCB, PSPCB LV/T and 6 Nos thyristors & replacement of aluminium Bus Bars, replacement of sleeves, Glass lead 90mm-3 Nos etc. i/c of nut bolts washers etc complete in module of PSTB 370 which in turn helps in controlling its voltage for smooth start control circuit and overhauling of soft starter & resistance box i/n wiring of the soft starter for 240 HP motor installed at bed No 4 Jyoti side at W/w Sec 26, Chd. |
| 15 | Dismantling of 24\\" i/d Sluice Valve i/c cost of Gun Metal dpincle, Guide Nut, Packing sheet, Nut Bolt etc i/c cost of crane Hydra complete in all respect at W/W- 26, Chd |
| 16 | Repair of centrifugal pump coupled of 268 HP slipring motor, replacement of motor slipring of Bed No-2 Kirloskar side at W/w Sec 26, Chd. |
| 17 | Providing and fixing of pump shaft SS 410 i/c cost of turning, threading, key way cutting and fixing of impellor with hydraulic press complete |
| 18 | P/F of gun metal neck ring i/c cost of machining etc |
| 19 | P/F of gun metal sleeves as per existing size with machining etc |
| 20 | P/F of ball bearing 6311 complete in all respect o make SKF/FAG/TATA |
| 21 | Providing and fixing of check-nut complete in all respects. |
| 22 | Dynamic balancing of rotating assembly complete in all respects |
| 23 | Carriage of pump from site to work shop at back to site |
| 24 | Re-fixing of single stage centrifugal pump i/c of packing sheet, gland dori, grease and nut-bolt complete in all respect at |
| 25 | Providing and fixing of slipring of 268 HP motor inuclding cost of inner bore turning and key way cutting, locking system, nut bolt complete in all respect at water works sec 32, Chd |
| 26 | Repair of single stage centrifugal pump coupled with 375 HP Slipring motor installed at bed No 2 & 3 Jyoti side at water works sec 26, CHD |
| 27 | P/f of pump shaft made of SS 410 i/c of turning, threading, key way & fixing of impellor with the help of hydraulic press complete in all respect. |
| 28 | P/F of gun metal neck ring i/c cost of machining etc |
| 29 | P/F of gun metal sleeve as per existing size with machining etc |
| 30 | P/F of alignment bush |
| 31 | P/F of bearing 6314 complete in all respect of make SKF./FAG/TATA |
| 32 | P/F of check nut complete in all respects |
| 33 | Dynamic Balancing of rotating assembly complete in all respects |
| 34 | Carriage of pump from site to work shop and back to site |
| 35 | Fixing of pump after alignment of pump and motor complete |
| 36 | Cost of gland dori, packing sheet, Nut bolt with washer complete |
| 37 | Repairing of split casing horizontal centrifugal pump coupled with 125 HP motor of bed No 3 in NPH at water works sec 26, Chandigarh. |
| 38 | Dismantling of pump with the help of chain pulley coupled with existing motor complete in all respect |
| 39 | Providing and fixing of gun metal shaft sleeve as per existing size i/c machining, turning, lathe work etc complete in all respects |
| 40 | Providing and fixing of neck ring made of bronze complete in all respects |
| 41 | P/f \of ball bearing 6308 complete in all respect SKF/FAG/TATA |
| 42 | Providing and fixing of check nut Complete in all respects. |
| 43 | P/f of gun metal alignment bush complete in all respects. |
| 44 | Dismantling of impellor with the help of hydraulic press and providing and fixing of cutter key etc. complete |
| 45 | Dynamic balancing of impellor end shaft |
| 46 | Replacement of packing sheet, gland dori, grease and nut bolt etc |
| 47 | Carriage of pump from site to work shop & work shop of site |
| 48 | Repair of single stage centrifugal pump coupled with 475 HP slipring motor installed at bed no.1 Kirloskar side at water Works Sector-26, Chd. |
| 49 | Dismantling of pump with the help of chain pulley coupled with existing motor complete in all respects. |
| 50 | Providing and fixing of gun metal sleeves as per existing size with machining etc complete in all respects. |
| 51 | Providing and fixing of alignment bush complete in all respects. |
| 52 | P/f of neck ring including cost of machining etc. complete in all respects. |
| 53 | Providing and fixing of check nut complete in all respects. |
| 54 | Providing and fixing of ball bearing 6314 complete in all respects. |
| 55 | Remetalling of SS shaft for bearing seat driving, and non driving side including cost of machining, truning etc complete in all respects. |
| 56 | Carriage of pump from site to work shop & work shop to site. |
| 57 | Dynamic balancing of rotating assembly complete in all respects |
| 58 | Re-fixing of single stage centrifugal pump including cost of packing sheet, gland dori, grease, nut bolt etc. complete in all respects. |
| 59 | Credit against old material Please Enable Macros to View BoQ information |