| 1 | Excavation of pole pit for pole upto 8.00m length by using JCB/Manual |
| 2 | Erection of RCC, REC, PSC poles upto 8.00m length by using Crane / Manual |
| 3 | Excavation of pole pit for pole above 8.00m length by using JCB/Manual |
| 4 | Erection of RCC, REC, PSC poles above 8.00m length by using Crane / Manual |
| 5 | Excavation of Stay pit of 4.5 ' to 5 ' depth using JCB / Manual |
| 6 | Erection of stay set complete with fixing up stay wire Eye, Bow, Guy Shackle, Binding etc.. |
| 7 | Fixing of Tapping X-Arm/Guarding X-Arm/V cross arm |
| 8 | Fixing of HT/LT TI Fittings |
| 9 | Fixing of LT 3 phase cross arm |
| 10 | Fixing of 11 KV Strain Disc with Metal Parts |
| 11 | Fixing of 11 KV Pin Insulator/Polymer Pin Insulator |
| 12 | Paving and stringing of conductors of sizes upto 7/2.59 mm ACSR or other equivalent conductor |
| 13 | Paving and stringing of conductors of sizes above 7/2.59 mm ACSR or other equivalent conductor |
| 14 | Paving and stringing of conductors of sizes 7/4.09 mm ACSR or other equivalent conductor |
| 15 | Fixing of LT Shackle |
| 16 | Fixing of LT Pin Insulator |
| 17 | Fixing of Alu Knob |
| 18 | Erection of 11 KV Single Pole Structure including erection of DT complete with centre support including fixing of MCD box |
| 19 | Loading and Unloading of Distribution Transformer (i) Upto 100 KVA |
| 20 | Loading and Unloading of line materials |
| 21 | Transporting of Distribution Transformer/line materials from stores to office /site upto 10 KM distance by engaging 1 Ton Capacity Minidor (Lorry) |
| 22 | Transportation of all type of poles by bullock cart or other vehicle (for all sizes of poles including loading and unloading) (i) For a lead upto 5 KM |
| 23 | Transporting of conductors of all sizes from road side to pit locations upto one KM of Conductor |
| 24 | Dismantling of RCC,REC,PSC & metal pole of all sizes including the closing of the pit |
| 25 | Dismantling of line materials, cross arm, clamps, TI Fittings etc.., |
| 26 | Dismantling of conductor upto 7/3.35 mm including closing of the pit |
| 27 | Dismantling of conductor above 7/3.35 mm including closing of the pit |
| 28 | Concreting with 1:4:8 mix using 40 mm Jelly including curing(Material + labour) (i) Mass concreting of poles |
| 29 | Earthing of Pole |
| 30 | Erection of DP structure with stay as per TNEB standard including of top channel, cross bracing, concreting, painting, colour washing etc.., (i) With 11 KV AB Switch using all types of poles of size 9 m and above length |
| 31 | Resagging of one run of all size of conductor (i) 7/2.50 mm AAAC 7/2.59 mm ACSR |
| 32 | Resagging of one run of all size of conductor (ii) 7/3.15 mm AAAC 7/3.35 mm ACSR |
| 33 | Resagging of one run of all size of conductor (iii) 7/4.09 mm ACSR |
| 34 | Dismantling of Double Pole Structure with complete set |
| 35 | G.S.T. @18% should be Entered by the Bidder Please Enable Macros to View BoQ information |