| 1 | Safe Carriage of PCC Pole | Safe Carriage of PCC Pole 8.5 / 9 mtr long Store Center or from any other place to the respective site of work through the Kachha Pacca road including the work of its loading & unloading at the respective ends also including the work of dragging etc. and also including the cost of labour, T&P carrier etc. required for proper completion of work. |
| 2 | Safe Carraige of ST Pole | ST Poles 11/13 mtr |
| 3 | Cartage of line material | Cartage of line material viz Weasal Conductor, Dog Concudtor, Stay Set, Earthing Rod, LT AB Cable (Different Size) GI earth wire, Cross Arm, Angle, Channel, Insulator, Clamps & other line material from Store Centre or from any other place to the respective site of work through the Kachha Pacca road including the work of its loading & unloading at the respective ends also including the work of dragging etc. and also including the cost of labour, T&P carrier etc. required for proper completion of work. (up to 100 Km). |
| 4 | Replacment of damaged PCC Pole | Replacement of damaged PCC Pole 8.5/ 9 mtr. Long by opening of all existing accessories and conductor from damaged pole properly and removal of damaged pole and erect the new pole at same place including fixing of all existing accessories and conductor on the new pole etc. as per direction of supervising engineer. Its including the cost of all labour, T&P etc. (including carriage of damaged pole to store) required for proper completion of work. |
| 5 | Replacment of damaged ST Pole | ST Poles 11/13 mtr |
| 6 | Grouting Nuzzling and Muffling of PCC Pole | Grouting, Nuzzling and Muffling of PCC Pole 8.5/9 mtr. Long as per RESSPO Manual including of the cost of labour, T&P and carrier etc. required for proper completion of work. The support shall be grouted with cement, sand and brick ballast in ratio including the cost of arrangement of cement, sand, brick ballast etc. |
| 7 | Grouting Nuzzling and Muffling of ST Pole | Erection of ST Poles 11/13 mtr |
| 8 | Erection of double PCC Pole | Erection of double supprot PCC Pole 8.5/9 mtr Long |
| 9 | Erection grouting and nuzzling of Stay Set | Erection, grouting and nuzzling of stay set including the work of nozzling etc. as per RESPO manual and also including the cost of arrangement of all grouting material, labour, T&P etc. required for proper completion of work as per RESSPO Manual. |
| 10 | Fixing and connecting of earthing rods | Fixing and connecting of earthing rods as per RESSPO Manual including the cost of labour T&P etc required for proper completion of work. |
| 11 | Re sagging of ACSR Dog and Weasel Conductor | Re-sagging of loose 33KV/11 KV / L.T. lines as per direction of supervising engineer. Its includes the cost of labour, T&P etc. required for proper completion of work. |
| 12 | Re sagging of LT AB Cable | LT A. B. Cable (different size) |
| 13 | Laying spreading Lifting of Cable | Laying, spreading, Lifting & Final sagging of Aerial Bunched 3x50+1x35+1x16 sq.mm.Cable of following size including fixing of All accessories as per RESSPO manual & as per direction by Supervising Engineer. |
| 14 | Laying spreading Lifting of cable | 3x95+1x70+1x16 sq.mm. |
| 15 | Laying spreading Lifting of Cable | 3x120+1x90+1x16 sq.mm. |
| 16 | Cutting and Chopping of tree branches | Cutting & Chopping of tree branches for proper clearance of HT/LT Line |
| 17 | Supply and Fixing of nut bolt off size | Providing & Fixing of nut bolt off size on vendors cost. |
| 18 | Supply and Fixing of Holding clamp | Providing & Fixing of holding clamp for ST/PCC pole one vendors cost. |
| 19 | Erection of Cross arm etc | Fixing of cross arm, insulator etc. |
| 20 | Weldig of STP rust Pole | Welding of STP Rust Pole with fixing & removal of all accessiores. |
| 21 | Replacment of LT cable | Replacement of LT Cable provided by department in Distrubution Transformers. |
| 22 | Recieved Back Material | Rust/Damage Iron Material carriage from site to store center |
| 23 | Recieved Back Material | Cartage of dismantlled line material / scrap viz ST Pole Weasal Conductor, GI earth wire, Cross Arm, Angle, Channel, Insulator, Clamps & other line material from site to Store Centre as per direction of supervising engineer through the Kachha Pacca road including the work of its loading & unloading at the respective ends also including the work of dragging etc. and also including the cost of labour, T&P carrier etc. required for proper completion of work. (Dist. 0 to 100 Kms.). |