| 1 | Part-A (Supply of Material)Barbed wire GI | Part-A (Supply of Material)Barbed wire GI |
| 2 | Alu. Winding wire | Alu. Winding wire |
| 3 | 33 KV V Type Cross arm clamp | 33 KV V Type Cross arm clamp |
| 4 | 11 KV V Type Cross arm clamp | 11 KV V Type Cross arm clamp |
| 5 | Stone Pad | Stone Pad |
| 6 | Top Channel | Top Channel |
| 7 | T-off Channel | T-off Channel |
| 8 | Dropper Channel | Dropper Channel |
| 9 | Holding Clamp | Holding Clamp |
| 10 | PG Clamp dog to dog | PG Clamp dog to dog |
| 11 | Nut & Bolt warshal all sizes | Nut & Bolt warshal all sizes |
| 12 | Number Plate | Number Plate |
| 13 | Danger Plate | Danger Plate |
| 14 | Brassing Set | Brassing Set |
| 15 | 11 KV E-Bracket | 11 KV E-Bracket |
| 16 | 11 KV F-Bracket | 11 KV F-Bracket |
| 17 | 33 KV F-Bracket | 33 KV F-Bracket |
| 18 | Neutral cum earth wire | Neutral cum earth wire |
| 19 | Suspension Clamp | Suspension Clamp |
| 20 | Distribution Box clamp | Distribution Box clamp |
| 21 | PG Clamp | PG Clamp |
| 22 | Dead End Clamp | Dead End Clamp |
| 23 | I Hook | I Hook |
| 24 | J Hook | J Hook |
| 25 | Alu. Paint | Alu. Paint |
| 26 | Red Oxide Paint | Red Oxide Paint |
| 27 | HDPE Pipe | HDPE Pipe |
| 28 | Part-B (Erection work)Carriage of PCC Pole 8.5 Mtr. Long from store center agra to work site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-70Kms.) | Part-B (Erection work)Carriage of PCC Pole 8.5 Mtr. Long from store center agra to work site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-70Kms.) |
| 29 | Carriage of PCC Pole 9 Mtr Long from store center agra to work site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70Kms.) | Carriage of PCC Pole 9 Mtr Long from store center agra to work site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70Kms.) |
| 30 | Carriage of ST Pole 13 Mtr Long from store center agra to work site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70Kms.) | Carriage of ST Pole 13 Mtr Long from store center agra to work site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70Kms.) |
| 31 | Carriage of ST Pole 11 Mtr Long from store center agra to work site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70Kms.) | Carriage of ST Pole 11 Mtr Long from store center agra to work site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70Kms.) |
| 32 | Cartiage of Line Material from Store Center Agra to work site through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-70Kms.) Line material viz. Distribution Box (18), 33 KV Stay Set Complete (04), 11 KV Stay Set Complete (110), Earthing Complete (181), V Type Cross Arm for 33 KV (08), V Type Cross Arm for 11 KV (1014), Polymer Pin Insulator for 11 KV (2342), 11 KV Pin with Nut (2270), Polymer Pin Insulator for 33 KV (24), Disc fitting for 11 KV (435), Disc Insulator for 11 KV (435), 33 KV Jointing Kit O/D 3x300 sqmm (8), 11 KV Cable Jointing Kit O/D 3x185 sqmm (36), 11 KV VCB O/D 200/100/5A (02), Dog Conductor (6000 Mtr.), Recoon Conductor (24000 Mtr.), Weasel Conductor (66000 Mtr.), etc and other line Material as required in Estimate/Package) | Cartiage of Line Material from Store Center Agra to work site through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work..(Distance 00-70Kms.) Line material viz. Distribution Box (18), 33 KV Stay Set Complete (04), 11 KV Stay Set Complete (110), Earthing Complete (181), V Type Cross Arm for 33 KV (08), V Type Cross Arm for 11 KV (1014), Polymer Pin Insulator for 11 KV (2342), 11 KV Pin with Nut (2270), Polymer Pin Insulator for 33 KV (24), Disc fitting for 11 KV (435), Disc Insulator for 11 KV (435), 33 KV Jointing Kit O/D 3x300 sqmm (8), 11 KV Cable Jointing Kit O/D 3x185 sqmm (36), 11 KV VCB O/D 200/100/5A (02), Dog Conductor (6000 Mtr.), Recoon Conductor (24000 Mtr.), Weasel Conductor (66000 Mtr.), etc and other line Material as required in Estimate/Package) |
| 33 | Cartiage of LT ABC Cable 3x95 sqmm (500 Mtr.), 33 KV XLPE Cable 3x300 sqmm (520 Mtr.), 11 KV XLPE Cable 3x185 sqmm (2640 Mtr.) from store center agra to work site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-50Kms.) | Cartiage of LT ABC Cable 3x95 sqmm (500 Mtr.), 33 KV XLPE Cable 3x300 sqmm (520 Mtr.), 11 KV XLPE Cable 3x185 sqmm (2640 Mtr.) from store center agra to work site through Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-50Kms.) |
| 34 | Erection and grouting of PCC 8.5 Mtr. long Single Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories as required clamps, Cross Arm, Insulator etc. including Stone Pad as per RESPO norms Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. | Erection and grouting of PCC 8.5 Mtr. long Single Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories as required clamps, Cross Arm, Insulator etc. including Stone Pad as per RESPO norms Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. |
| 35 | Erection and grouting of PCC 8.5 Mtr. long Double Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories as required clamps, Cross Arm, Insulator etc. including Stone Pad as per RESPO norms Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. | Erection and grouting of PCC 8.5 Mtr. long Double Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories as required clamps, Cross Arm, Insulator etc. including Stone Pad as per RESPO norms Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. |
| 36 | Erection and grouting of PCC Pole 9 Mtr. long Single Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories as required clamps, Cross Arm, Insulator etc. including Stone Pad as per RESPO norms.Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. | Erection and grouting of PCC Pole 9 Mtr. long Single Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories as required clamps, Cross Arm, Insulator etc. including Stone Pad as per RESPO norms.Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. |
| 37 | Erection and grouting of ST Pole 13 Mtr. long Single Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories as required clamps, Cross Arm, Insulator etc. including Stone Pad as per RESPO norms.Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. | Erection and grouting of ST Pole 13 Mtr. long Single Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories as required clamps, Cross Arm, Insulator etc. including Stone Pad as per RESPO norms.Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. |
| 38 | Erection and grouting of ST Pole 11 Mtr. long Single Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories as required clamps, Cross Arm, Insulator etc. including Stone Pad as per RESPO norms.Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. | Erection and grouting of ST Pole 11 Mtr. long Single Pole in 1:2:4 ratio (cement, sand and bricks balast) including fixing of all accessories as required clamps, Cross Arm, Insulator etc. including Stone Pad as per RESPO norms.Labour, T &P and carrier, grouting material etc. required for proper completion of work shall be done by the contractor at his own cost. |
| 39 | Laying sagging stringing and binding and jumpering of ACSR DOG Conductor at 33/11 KV line as per RESPO norms It includes the cost of labour, T & P carrier etc required for proper completion of work. | Laying sagging stringing and binding and jumpering of ACSR DOG Conductor at 33/11 KV line as per RESPO norms It includes the cost of labour, T & P carrier etc required for proper completion of work. |
| 40 | Laying sagging stringing and binding and jumpering of ACSR Recoon Conductor at 33/11 KV line as per RESPO norms It includes the cost of labour, T & P carrier etc required for proper completion of work. | Laying sagging stringing and binding and jumpering of ACSR Recoon Conductor at 33/11 KV line as per RESPO norms It includes the cost of labour, T & P carrier etc required for proper completion of work. |
| 41 | Laying sagging stringing and binding and jumpering of ACSR weasel Conductor at 33/11 KV line as per RESPO norms It includes the cost of labour, T & P carrier etc required for proper completion of work. | Laying sagging stringing and binding and jumpering of ACSR weasel Conductor at 33/11 KV line as per RESPO norms It includes the cost of labour, T & P carrier etc required for proper completion of work. |
| 42 | Laying of 33 KV XLPE cable 3x300 sqmm in trench with making loop (at a distance of approx. 4 mtr.) as per RESPO Norms and direction by superivising Engineer. | Laying of 33 KV XLPE cable 3x300 sqmm in trench with making loop (at a distance of approx. 4 mtr.) as per RESPO Norms and direction by superivising Engineer. |
| 43 | Laying of LT ABC cable 3x95 sqmm overhead with making loop (at a distance of approx. 4 mtr.) as per RESPO Norms and direction by superivising Engineer. | Laying of LT ABC cable 3x95 sqmm overhead with making loop (at a distance of approx. 4 mtr.) as per RESPO Norms and direction by superivising Engineer. |
| 44 | Laying of 11 KV XLPE cable 3x185 sqmm overhead with making loop (at a distance of approx. 4 mtr.) as per RESPO Norms and direction by superivising Engineer. | Laying of 11 KV XLPE cable 3x185 sqmm overhead with making loop (at a distance of approx. 4 mtr.) as per RESPO Norms and direction by superivising Engineer. |
| 45 | Laying of 11 KV XLPE cable 3x185 sqmm (single Circuit) Through H.D.P.E.pipe by drill machine/H.D.D. Machine including the cost of arrangment of labour, T&P & Drill machine/H.D.D. machine at a depth of 1.0 mtr. Below the ground level. | Laying of 11 KV XLPE cable 3x185 sqmm (single Circuit) Through H.D.P.E.pipe by drill machine/H.D.D. Machine including the cost of arrangment of labour, T&P & Drill machine/H.D.D. machine at a depth of 1.0 mtr. Below the ground level. |
| 46 | Filling of 33 KV Cable Jointing Kit 3x300 sqmm O/D and making connection as per respo norms & direction by supervising engineer. | Filling of 33 KV Cable Jointing Kit 3x300 sqmm O/D and making connection as per respo norms & direction by supervising engineer. |
| 47 | Filling of 11 KV Cable Jointing Kit 3x185 sqmm O/D and making connection as per respo norms & direction by supervising engineer. | Filling of 11 KV Cable Jointing Kit 3x185 sqmm O/D and making connection as per respo norms & direction by supervising engineer. |
| 48 | Erection and grouting of 33 KV stay set as ratio 1:2:4 (cement, sand and bricks balast) as per RESPO norms including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. Grouting material i.e. cement, sand, brick ballast/stone ballast etc. shall be arranged by the contractor at his own cost. | Erection and grouting of 33 KV stay set as ratio 1:2:4 (cement, sand and bricks balast) as per RESPO norms including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. Grouting material i.e. cement, sand, brick ballast/stone ballast etc. shall be arranged by the contractor at his own cost. |
| 49 | Erection and grouting of 11 KV stay set as ratio 1:2:4 (cement, sand and bricks balast) as per RESPO norms including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. Grouting material i.e. cement, sand, brick ballast/stone ballast etc. shall be arranged by the contractor at his own cost. | Erection and grouting of 11 KV stay set as ratio 1:2:4 (cement, sand and bricks balast) as per RESPO norms including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. Grouting material i.e. cement, sand, brick ballast/stone ballast etc. shall be arranged by the contractor at his own cost. |
| 50 | Erection of Earthing Complete as per RESPO norms including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. | Erection of Earthing Complete as per RESPO norms including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. |
| 51 | Concreting of Support PCC/ST Pole. including the cost of arrangement of labour & required material T&P etc for proper completion of work. | Concreting of Support PCC/ST Pole. including the cost of arrangement of labour & required material T&P etc for proper completion of work. |
| 52 | Concreting of Support of Stay including the cost of arrangement of labour & required material T&P etc for proper completion of work. | Concreting of Support of Stay including the cost of arrangement of labour & required material T&P etc for proper completion of work. |
| 53 | Fixing of Dropper channel with clamp as per resop norms and direction by supervising engineer. | Fixing of Dropper channel with clamp as per resop norms and direction by supervising engineer. |
| 54 | Fixing of Top channel for 11 KV as per resop norms and direction by supervising engineer. | Fixing of Top channel for 11 KV as per resop norms and direction by supervising engineer. |
| 55 | Fixing of E-Bracket for 11 KV as required on Poles as per RESPO norms and direction by supervising Engineer. | Fixing of E-Bracket for 11 KV as required on Poles as per RESPO norms and direction by supervising Engineer. |
| 56 | Fixing of F-Bracket for 11 KV as required on Poles as per RESPO norms and direction by supervising Engineer. | Fixing of F-Bracket for 11 KV as required on Poles as per RESPO norms and direction by supervising Engineer. |
| 57 | Fixing of F-Bracket for 33 KV as required on Poles as per RESPO norms and direction by supervising Engineer. | Fixing of F-Bracket for 33 KV as required on Poles as per RESPO norms and direction by supervising Engineer. |
| 58 | Installation of Distribution Box with clamps as per RESPO norms and direction by supervising Engineer. | Installation of Distribution Box with clamps as per RESPO norms and direction by supervising Engineer. |
| 59 | Fixing of P.G. Clamps as per RESPO norms | Fixing of P.G. Clamps as per RESPO norms |
| 60 | Fixing of V Type Cross Arm Clamp for 11 KV as per RESPO norms | Fixing of V Type Cross Arm Clamp for 11 KV as per RESPO norms |
| 61 | Fixing of V Type Cross Arm Clamp for 33 KV as per RESPO norms | Fixing of V Type Cross Arm Clamp for 33 KV as per RESPO norms |
| 62 | Fixing of Suspension clamp as per RESPO norms | Fixing of Suspension clamp as per RESPO norms |
| 63 | Fixing of I hook as per RESPO norms | Fixing of I hook as per RESPO norms |
| 64 | Fixing of J hook as per RESPO norms | Fixing of J hook as per RESPO norms |
| 65 | Fixing of Barbed wire in direction by supervising Engineer. | Fixing of Barbed wire in direction by supervising Engineer. |
| 66 | Fixing of Brassing Set as per RESPO norms | Fixing of Brassing Set as per RESPO norms |
| 67 | Fixing of T-off Channel as per RESPO norms | Fixing of T-off Channel as per RESPO norms |
| 68 | Fixing of Holding Clamp as per RESPO norms | Fixing of Holding Clamp as per RESPO norms |
| 69 | Fixing of PG Clamp dog to dog as per RESPO norms | Fixing of PG Clamp dog to dog as per RESPO norms |
| 70 | Fixing of Nut & Bolt washer all sizes as per RESPO norms | Fixing of Nut & Bolt washer all sizes as per RESPO norms |
| 71 | Fixing of Number Plate as per RESPO norms | Fixing of Number Plate as per RESPO norms |
| 72 | Fixing of Danger Plate as per RESPO norms | Fixing of Danger Plate as per RESPO norms |
| 73 | Earthing of VCB as per RESPO norms | Earthing of VCB as per RESPO norms |
| 74 | Installation of 11 KV O/D VCB 200/100/5 Amp in proper alignment and direction and jointing of earthing strips with help of gas welding and making cable connection including shifting dragging with all other associated works. | Installation of 11 KV O/D VCB 200/100/5 Amp in proper alignment and direction and jointing of earthing strips with help of gas welding and making cable connection including shifting dragging with all other associated works. |
| 75 | Fixing of Neutral cum earth wire as per RESPO norms | Fixing of Neutral cum earth wire as per RESPO norms |
| 76 | Fixing of Dead end Clamp as per RESPO norms | Fixing of Dead end Clamp as per RESPO norms |
| 77 | Surface Preparation for Painting on ST Poles including cleaning, sanding and single coat of Red Oxide Paint as per RESPO norms and direction by supervising engineer. | Surface Preparation for Painting on ST Poles including cleaning, sanding and single coat of Red Oxide Paint as per RESPO norms and direction by supervising engineer. |
| 78 | Surface Preparation for Painting on ST Poles including cleaning, sanding and double coat of Alu. Paint as per RESPO norms and direction by supervising engineer. | Surface Preparation for Painting on ST Poles including cleaning, sanding and double coat of Alu. Paint as per RESPO norms and direction by supervising engineer. |
| 79 | Removal of old & Used weasel conductor and receive back to store center agra from work site along with loading unloading both ends (approx 50 to 70 km.). | Removal of old & Used weasel conductor and receive back to store center agra from work site along with loading unloading both ends (approx 50 to 70 km.). |