| 1 | Jungle clearance in borrow area, building premises, flanks and slopes on the roads, canals and embankment by removing the grass and the jungle bushes from the top including weeding out shrubs including roots and levelling etc. complete as per direction of E/I. (6.1.3.1 PART B ,PART A-2.02) |
| 2 | E/W in excavation in canal by the hydraulic excavator as per designed section in all kinds of soil, soil mixed with kankar, pebbles and boulders upto 300 mm size and disposal of spoil upto 10 m with all lifts all complete as per specification and direction of E/I..( 7.1.43.1 PART B) |
| 3 | E/W in excavation in canal by the hydraulic excavator as per designed section in all kinds of soil, soil mixed with kankar, pebbles and boulders upto 300 mm size and disposal of spoil upto 500 m with all lifts by tipper including construction and maintenance of haul road all complete as per specification and direction of E/I . (7.1.43.2 PART B) |
| 4 | E/W in excavation of foundation trenches of toe wall, spillway, head regulator, outlet, intake well etc. as per designed section in all kinds of soil including moorum soil, soil mixed with kankar, pebbles and boulders upto 300 mm size and disposal of the same (beyond 50m away from the edge of the trenches) with initial lead of 150m and initial lift of 1.5M. as per specification and direction of E/I.(PART -B 5.1.14.1) |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering all work up to plinth level 1:2:4(1cement :2coarse sand (zone-iii):4graded aggregate 20mm nominal size). PART-B 5.3.6 B.C.D- 5.3.1.2) |
| 6 | Providing rough dressed random rubble stone masonry in cement mortar (1:4) in foundation with aproved quality of coarse sand of requisite F.M. (2.5 to 3.0) washed and screened with raking out joints, curing, soaffolding and its removal wherever required including royalty and all taxes etc. complete job as per specification and direction of E.I. (5.4.8 PART-B , PART-A 4.28) |
| 7 | Providing shuttering including strutting, proping etc.and its removal after use in foundation work as per specifications and direction of E/I (5.3.17 PART -B) |
| 8 | Providing rough dressed random rubble stone masonry in cement mortar (1:4) in superstructure with aproved quality of coarse sand of requisite F.M. (2.5 to 3.0) washed and screened with raking out joints, curing, scaffolding and its removal wherever required including royalty and all taxes etc. complete job as per specification and direction of E.I. (5.4.11 PART -B, PART-A 4.31) |
| 9 | Dewatering by 10 HP diesel pump.( P.M -29, PART B) |
| 10 | Providing 25mm thick cement plaster (1:4) with approved quality of sand of requisite F.M. (2.5 to 3.0) washed and screened including curing, scaffolding, wherever required and its removal, royalty and all taxes etc. complete job as per specification and direction of E/I. (5.5.5 PART -B,PART -A 3.12) |
| 11 | Earth work in filling foundation trenches or back filling of masonry structures with suitable earth in layers not exceeding 150mm thick well watered, rammed and fully compacted and finally dressed with earth obtained from excavation of foundation trenches and kept at a lead of 30m and initial lift of 1.5m complete as per specification and direction of E/I. (6.1.16 PART B) |
| 12 | Supplying 300mm dia NP2 hume pipe with collors in line, level and grade as per IS 458-1971 all complete. (M 300(V) P.N -84,WRD) |
| 13 | Labour for laying, fitting and fixing 300mm dia NP2 hume pipe with collors in line, level and grade, as well as providing approved jointing materials and joints properly filled to make them water proof, all complete, as per specification and direction of E/I.(7.6.1 .3 PART B) |
| 14 | Carriage of materials by diesel truck including loading at source, unloading at work site and stacking properly, labour etc. all complete as per direction of E/I.Cement - 10 km (p) + 1 km (k) |
| 15 | Sand -30 km (p) + 1 km (k) |
| 16 | Stone Chips - 40 km (p) + 1 km (k) |
| 17 | Boulder - 40 km (p) + 1 km (k) |
| 18 | Hume Pipe (300mm dia) - 50 km (p) + 1 km (k) |
| 19 | Goods & Services Tax (G.S.T.) - 12% |
| 20 | Labour Cess - 1% Please Enable Macros to View BoQ information |