| 1 | Construction of embankment with approved material obtained from borrow pits with all lifts upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-1 and 300.2 with lead up to 1000m as per technical specification clause 301.5 |
| 2 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density as per MORD specification 401 |
| 3 | Providing, laying, spreading and compacting stone aggregates of specific sizes of 22.4-53 mm to water bound macadam Grading 3 specification in pot holes & damaged edges of road. including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 KN in stages to proper grade and camber, applying and brooming, stone screening to fill (Type B) up the interstices of coarse aggregate, watering and compacting to the required density as per Technical Specification Clause 405. |
| 4 | Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel bars, near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days, |
| 5 | Providing and fixing of sign board at site for information with mat lab T&P etc. |
| 6 | Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. |
| 7 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 I. P.C.C grade M (i) Nominal mix 1:4:8 |
| 8 | Stone masonry in cement mortar for substructure complete as per drawing & technical specification Clauses 702, 704, 1202 and 1204 Random rubble masonry In 1:4 cement mortar |
| 9 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203P.C.C grade M 20 |
| 10 | Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification Clauses 613.4 & 1204 |
| 11 | Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. |
| 12 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 I. P.C.C grade M (i) Nominal mix 1:4:8 |
| 13 | Stone masonry in cement mortar for substructure complete as per drawing & technical specification Clauses 702, 704, 1202 and 1204 |
| 14 | Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 1106. (1000 mm Dia Hume Pipe) |
| 15 | Pointing with cement mortar (1:3) on brickwork as per drawing and technical specification Clauses 613.3 and 1204 Please Enable Macros to View BoQ information |