| 1 | cross drain |
| 2 | 2.5.1.A:Dismantling of Structures <br> Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202. <br> (I) By Manual Means <br> (A) Lime Concrete |
| 3 | 3.5.2:Excavation in Soil with Dozer with lead upto 100 m <br> Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 m, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections. |
| 4 | 11.4.1.1:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 <br> I. P.C.C grade M 10 <br> (i) Nominal mix 1:3:6 |
| 5 | 11.4.2.1:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 <br>II. P.C.C grade M 15 <br> (i) Nominal mix (1:2.5:5) |
| 6 | 11.4.4:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203<br> IV. R.C.C grade M 20 |
| 7 | 11.8:Supplying, fitting and placingTMT bar reinforcement in foundation complete as per drawings and technical specifications Clauses 1000 and 1202 |
| 8 | 12.8:Supplying, fitting and placing with MS bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 |
| 9 | 12.5.4:Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204 <br> For height upto 5 m <br> IV. R.C.C. grade M 25 |
| 10 | OD508310/2025-2026:Tubular Steel Railing on Precast RCC posts, 1.2 m high above Ground Level Providing, fencing and erecting 50 mm dia painted steel pipe railing in 3 rows on precast M-20grade RCC vertical posts 175 mm x 175 mm x 1.2 m high (1.2 m above Gl) with 3 holes 50 mmdia for pipe, fixed 2 m centre-to- centre complete as per approved drawings Clause 1706( item10.15 modified )( Deduction earth work, foundation concrte and height to 1.2metre) |
| 11 | 3.4:Construction of Embankment with Material Obtained from Borrow Pits <br> Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 |
| 12 | 75.8.1:Providing Plain cement concrete for road work CC 1:2:4 (1 cement: 2 fine aggregate: 4course aggregate) laid to required slope and camber in panels (@ 3 m c/c) as requiredincluding compaction, finishing and tamping etc .complete. Max. size of courseaggregate not exceeding 25mm , mixed in concrete mixer etc complete as perspecification(i) Nominal mix (1:2:4) |
| 13 | 3.3:Construction of Embankment with Material Obtained from Roadway Cutting <br> Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 |
| 14 | OD515356/2025-2026:60.7.2 DR PACKING Under foundation - Dry stone packing under foundation with good qualityblasted rubble including conveyance of material and labour charges etc. complete as perdirection of departmental officers at site. |
| 15 | 4.11.2:Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place method normal. Construction of granular sub-base by providing local material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408. <br>(ii) Using Gravel mix soil. |
| 16 | 4.9:Wet Mix Macadam <br> Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. <br> By Mechanical Means with 1 km lead |
| 17 | 75.5.1.1pb:Prime Coat - Low porosity - With Packed Bitumen Rates <br> Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502 |
| 18 | 75.5.2.3pb:Tack Coat - With Packed Bitumen Rates <br> Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per Technical Specification Clause 503. |
| 19 | 75.5.2.1pb:Tack Coat - With Packed Bitumen Rates <br> Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.20 to 0.25 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503. |
| 20 | 75.5.11.1.A.2pb:Mix Seal Surfacing - Manual Means - Type A - Bitumen S-65 - Packed Bitumen Rates <br> Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.9 mm (Type-A) or 13.2 mm to 0.9 mm (Type-B) aggregates using penetration grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 8-10 kN static roller and finishing to required level and grades as per Technical Specification Clause 509 <br> By Manual Means <br> Type A <br> (II) Bitumen (S-65) |
| 21 | 75.5.5.A.1pb:Modified Penetration Macadam 50 mm thick using Bitumen S-65 - Packed Bitumen Rates <br> Construction of penetration macadam over prepared base by providing a layer of compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key aggregates and rolling with a three wheel 80-100 kN static roller to achieve the desired degree of compaction as per Technical Specification Clause 506. Please Enable Macros to View BoQ information |