| 1 | Item No. 1 : Providing and supplying in standard lengths Polyethelene Pipes, confirming to IS 4984 / 14151 / 12786 / 13488 with nesessary jointing material like mechanical connector i. e. thread / insert joint / quick release coupler joint / compression fitting joint or flanged joint excluding coupler/specials, including transportation and freight charges, inspection charges, loading / unloading charges, conveyance to the departmental stores & stacking the same in closed shade duly protecting from sun 110 mm dia PE-100 6 kg/Sq.cm 5 % amount for HDPE specials |
| 2 | item No.2: Providing double flange sluice valve confirming for IS -4846 including worm gear arrangements as per test pressure ,stainless steel spindle ,caps, including inspection charges transportation upto departmental store unloading stacking including GST levied by GOI & GOM in all rescept etc complete 100 mm dia |
| 3 | item No.3: Providing and supplying Air valves as per IS-10845 and MJP's standard specifications of approved make and quality of following diameter including all taxes (Central and Local ), railway freight , inspection charges, unloading from railway wagon , loading into truck, transportation upto departmental stores /site , unloading , stacking etc. complete.a) Air Valve Double Ball Flanged / Screwed Type - PN -150 mm dia Double Ball |
| 4 | Item No.4:Excavation for foundation / pipe trenches in earth,soils of all types ,sand,gravel & soft all types sand,gravel & soft murum , including removing the excavated material upto a distance of 50 meters and lifts as below ,stacking and spreading as directed , manual dewatering preparing the bed for foundation and excluding backfilling etc complete |
| 5 | item No.5:Excavation for foundation / pipe trenches in hard murum and boulders, W.B.M. road including removing the excavated material upto a distace of 50 M and lifts as below, stacking and spreading as directed by Engineer-in-charge, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete.(MJP-SSR-2023-24 P. No.37 I. No.3) |
| 6 | item No.6: Excavation for foundation / pipe trenches by blasting in soft rock and old cement and lime masonry foundation asphalt road including removing the excavated material upto a distance of 50 meters beyond the area and lifts as below, stacking and spreading as directed by Engineering -in -charge, normal dewatering ,preparing the bed for foundation and excluding backfilling,etc.complete.(MJP-SSR-2023-24 P. No.37 I. No.5) |
| 7 | item No.7:Filling in plinth and floors murum bedding in trenches with approved murum from excavated materials from foundation 15cm to 20cm layers including watering and compaction complete. Murum from excavated stuff |
| 8 | item No.8:Lowering,Laying and Jointing H.D.P.E. / M. D. P. E. pipes in proper position including all specials by compression fitting/electrofusion and butt fusion jointing procedure as per relevent IS Code complete with all materials for jointing procedure like Electrofusion machine, Electric heater/butt fusion welding machine with hydraulic jack, top loading clamp etc. and all labours as directed by engineer in charge as per IS-7634 Part II110 mm dia. 6 Kg/Cm2 (MJP-SSR-2023-24 P. No.125 I. No.2) |
| 9 | iteam No.9:Hydraulic testing of HDPE /MDPE line to specified pressure including cost of all materials and labour and water for testing for specified length including cutting, placing end cap making arrangement for filling safe water using reciprocating type pumps which should be able to provide specified test pressure gauges and other necessary equipments, labour, operation charges, etc. required for testing. The rate under this item shall also include cost of retesting, if necessary and reinstating to original position.110 mm dia. PE-100, 6Kg/Sq.cm (MJP-SSR-2023-24 P. No,126 I. No.3) |
| 10 | item No.10:Lowering , laying and jointing in position following C.I.D/F reflux valves, Butter fly valves and Sluice valves including cost of all labour jointing material, including nut bolts and giving satisfactory hydraulic testing etc. complete. ( Rate for all class of valves)100 mm dia Sluice Valve & Reflux Valve(MJP-SSR-2023-24 P. No.148 I. No.4) |
| 11 | item No.11:Providing and laying in situ 1:2:4 (M-150) grades of C.C. of trap/granite/ quartzit/gneiss metal for foundation and bedding including dewatering, form work, compacting and curing, finishing , etc. complete. With initial lift of 1.5 M below / above ground level.M-150/ 1:2:4(MJP-SSR-2023-24 P. No,47 I. No.1) |
| 12 | item No.12:Making cross connection / lekages to existing pipe line to new pipeline including excavation, breaking and removing existing pipes, lowering, laying and jointing ..etc complete 80 mm(MJP-SSR-2023-24 P. No.58 I. No.10) |
| 13 | item No.13:Providing and fixing in position air valve shaft including providing and fixing GI medium class or 6 mm thick M.S. pipe shaft 2.70 M long over branch flange of air valve tee , providing PCC block of M¬150 concrete , 150 mm thick around the air valve tee including encasing of vertical shaft in PCC M¬150 as shown in type design together with providing and making flanged joints wherever required and fixing of air valve over the shaft excluding cost of air valve and branch flanged air valve tee etc. complete as per type design and as directed by Engineer-in-charge for following diameters of pipe lines (Type design attached) Foundation on Murum and Harder strata Upto 150 mm dia.( MJP SSR 2023-24 Page No.155 I.No. 17 a ) |
| 14 | item No.14:Refiling the trenches with available excavated stuff with soft material first over pipeline and then hard material in 15 cm layers with all leads and lifts including consolidation surcharging etc complete |
| 15 | Add 18 % GST Please Enable Macros to View BoQ information |