| 1 | Supplying of \\"B\\" check maintenance materials for 70 KVA Kirloskar make DG set Engine Model :- HA694T ESN: 06.2445/1300046 . The spares including Spinon Lube oil Filter, Fuel Filter Element Primary , Fuel filter Element Secondary , Kirloskar care Premium Genuine oil , Fuel pipe feed pump-fuel filter, Fuel pipe fuel filter to fip, Fuel pipe inlet: M14xM14 BANJO both side, copper washer, comb leak off pipe, fuel hose, Hose clamp-const press spr Band, Exhaust fan 450mm with connector, starter ring 121T 3.175 MOD, controller unit, bolt nut M10 with dowel washer, with distilled water & cotton waste Complete with all accessories as per the direction of Engineer in Charge . |
| 2 | a) Spinon Lube oil Filter 06.436.01.0.00 |
| 3 | b) Fuel Filter Element Primary 3H.132.01.0.00 |
| 4 | c) Fuel Filter Element secondary 3H.132.02.0.00 |
| 5 | d) Kirloskar care Premium Genuine oil 82.060.10.0.20 ( 20 litres) |
| 6 | e) Fuel Pipe ( Feed pump -fuel filter 06.333.01.0.00 |
| 7 | f) Fuel pipe fuel filter to Fip 06.333.02.0.00 |
| 8 | g) Fuel pipe inlet :M14 x M14 BANJO Both side 900L 4H.896.09.0.00 |
| 9 | h) Copper washer ( 14 x 20) 50.508.12.000 |
| 10 | i) Comb Leak off pipe: HA694 06.006.01.0.00 |
| 11 | j) Fuel Hose 5.1D x 11.5 x 12.7 O 02.525.06.0.00 |
| 12 | k) Hose clamp -Const Press Spr Band 02.500.08.0.00 |
| 13 | l) Exhaust fan 450mm with connector DB.079.26.0.00 |
| 14 | m) Starter ring 121T 3.17MOD |
| 15 | n) Controller unit |
| 16 | o) Bolt & Nut M10 with Dowel washer |
| 17 | p) Cotton Waste |
| 18 | Q) Distilled water ( 2 litrs) |
| 19 | Service charges for dismantled the alternator from the Engine and removed the flywheel from the Engine. Removed the flywheel ring from the flywheel and refitment the new flywheel ring in the flywheel. Fitted the flywheel in the Engine and coupled the dismantled Alternator in the Engine. Checked the alignment, checked the fuel line hoses,battery terminal cables and all the elctrical wiring systems. Started and tested the DG set with load and idle condition found the performance satisfactory |
| 20 | Service charges for New Controller Fitment and connected the all circuit wirings and programming the control unit and checked the all electrical & electronic wiring systems connected the controller unit and checked and started the DG set. |
| 21 | Service charges for (preventive maintenance ) changing of above all new spares, checking of all fuel line systems, hose clips, Battery terminal cables and all electrical wiring systems. Started and tested of the DG set with laod condition performance satisfactory. |
| 22 | Designing, supply and commissioning of Automatic Mains failure panel for 70 KVA capacity Genset of suitable size with following technical specifications.1) Electricity board supply loading / unloading in Off/Manual/Auto mode.2) Selectable auto/manual start/stop of the generator.3) Selectable Auto/Manual loading/unloading of the generator.4) Interlocking loops with solid state logic circuit to avoid shorting of EB supply side and generate supply side.5) Short circuit protection system for both EB side and generator side.6) Overload Protection system for generator.7) Single phase prevention system.8) Phase sequence sensing system.9) Time sensing system for all operation.10) Digital monitoring system for voltage, amps, and frequency11) Short Circuit protection for DC circuit12) By Pass Arrangements. |
| 23 | Supplying and drawing FRLSH PVC insulated Industrial multicore flexible copper cable in the existing surface/recessed steel/ DWC pipe/PVC conduit/PVC casing capping etc as required. |
| 24 | a) 4 core x 2.5 Sqmm Please Enable Macros to View BoQ information |