| 1 | Dismantling of cement concrete pavements by mechanical means using pneumatic tools breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials upto a lead of 1000 m, stacking serviceable and unserviceable materials separately |
| 2 | Granular Sub-base with Well Graded Material (Table 400-1)By Mix in Place Method Construction of granular sub-base by providing well graded material, spreading in uniform layers with Tractor Mount Grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per MoRTH Specification Clause 401.For Grading I Material |
| 3 | Granular Sub-base with Well Graded Material (Table 400-1)By Mix in Place Method Construction of granular sub-base by providing well graded material, spreading in uniform layers with Tractor Mount Grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per MoRTH Specification Clause 401.For Grading III Material |
| 4 | Water Bound Macadam with Crushable ScreeningsWBM Grading 2Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per MoRTH Specification Clause 404. Using Crusher Broken aggregate : By Mechanical Means |
| 5 | Construction of un-reinforced, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 602.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 31.5 mm, mixed in a concrete mixer of not less than 0.5 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed Side Formwork (steel channel, laying and fixing of 150 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days, using water finishing to lines and grade as per drawing and MoRTH Specification Clause 602 including vaccum dewatering process with all required equipments (Dowel Bars will be paid seprately) |
| 6 | Excavation for Structures Earthwork in excavation for structures as per drawing and MoRTH specifications Clause 304.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. In Ordinary Soil : Upto 3 m depth |
| 7 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and MoRTH specifications Clause 1702, 1703, 2102 & 2104 (Banas/Bikaner quarry sand permitted only) P.C.C grade M 10 : Nominal mix 1:3:6 |
| 8 | Stone masonry work in cement mortar in foundation complete as per drawing and MoRTH specifications Clauses 1402, 1405, 2102 & 2104. (Banas/Bikaner quarry sand permitted only) Random Rubble masonary : In cement mortar 1:4 |
| 9 | Plastering with cement mortar (1:4), 20 mm thick on Stone work. (Banas/Bikaner quarry sand permitted only) |
| 10 | Providing PCC M-20 architectural coping on the top of wing wall, return wall etc. complete as per drawing and MoRTH specification Clauses 1313, 1411 and 2206.6 50 mm thick |
| 11 | Providing weepholes in brick masonry/stone masonry, plain / reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and MoRTH specification Clauses 1409, 2204.4, 2206.4 & 2706 Please Enable Macros to View BoQ information |