| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. |
| 2 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) DSR 4.1.8 |
| 3 | Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge; for the following grades of concrete. Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the specified minimum cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement. Concrete of M-25 grade with minimum cement content of 330 kg /cum DSR 5.33.1 |
| 4 | Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge; for the following grades of concrete. Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the specified minimum cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement. DSR 5.33Concrete of M25 grade with minimum cement content of 330 kg /cum DSR 5.33.2.1 |
| 5 | Steel reinforcement for R.C.C. work including straightening, cutting,bending, placing in position and binding all complete upto plinth & above plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more. DSR 5.22.6 |
| 6 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in: Cement mortar 1:6 (1 cement : 6 coarse sand) DSR -6.1.2 |
| 7 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in: Cement mortar 1:4 (1 cement : 4 coarse sand) |
| 8 | 12 mm cement plaster of mix : 1:6 (1 cement: 6 coarse sand) |
| 9 | Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of required shade. New work (Two or more coats applied @ 1.43 ltr/ 10 sqm. over and including priming coat of exterior primer applied @ 2.20 kg/ 10 sqm). |
| 10 | PORVIDING I.S.A. 40mm40mm5mm Angle size |
| 11 | Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture |
| 12 | PORVIDING I.S.A. 40mm40mm5mm Angle size IN Pillars for fixing barbed wire |
| 13 | PrOVIDING barbed iron wire fencing including fixing it to post after streching it including labour and T&P etc required for proper completion of the work but excluding cost of posts & barbed wire. |
| 14 | PrOVIDING barbed iron wire fencing including fixing it to post after streching it including labour and T&P etc required for proper completion of the work but excluding cost of posts & barbed wire. (Labour Rate only)513 |
| 15 | Construction of Embankment with approved material obtained from road way cutting with a lift upto 1.5 m , transporting to site , spreading,gradding to required slope and compacting to meet requirment of tables 300.1 and,300.2 as per tech classification 301.5. Please Enable Macros to View BoQ information |