| 1 | Dismentalling of bricks on the edge/old interlocking pavement/ cc road including stacking of serviceable materials and disposal of unserviceable materials with the lead of 50 mtr as per direction of engineer in charge |
| 2 | Earth in Embankment in ordinary soil i/c lead 30mt. & lift 2 1.50 mt. with cartage 5.0 km distance to done from site. |
| 3 | Brick masonry work in 1:3 cement mortar complete excluding pointing and plastering as per drawing and technical speficiations clauses 600, 1202 & 1203 |
| 4 | Plastering with cement mortar (1:4) 15 mm thick on 5 brickwork in substructure/superstracutre as per technical specification clauses 613.4 & 1204 |
| 5 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with 2% cement (OPC) rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. |
| 6 | Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M 30 (Grade), coarse and fine aggregates conforming to IS: 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the coricrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel bars, near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days, |
| 7 | Providing and laying cement concrete in ratio of 1:2:4 (1 Cement: 2 coarse sand (zone-III): 4 graded stone aggregate 20 mm nominal size) including supply of all materials, labour and T&P etc required for proper completion of work. |
| 8 | Providing and laying cement concrete in ratio of 1:2:4 (1 Cement: 2 coarse sand (zone-III): 4 graded stone aggregate 20 mm nominal size) including supply of all materials, labour and T&P etc required for proper completion of work. |
| 9 | Supply & Fixing of granite board. As per M.R |
| 10 | Deduction ofold interlocking paver block vrick |
| 11 | Supplying fitting and placing HYSD bar reinforcement in ubstructure/superstructure complete as per drawing and Cechnical Specifications clauses 1002, 1010 and 1202 Please Enable Macros to View BoQ information |