| 1 | Additionalrateforprovidingonediscset,PGclampetc.complete,onany type of HT pole for making cut point. |
| 2 | FittingoneAdditional75x40mm,1.8mChannelcrossarminexisting single pole including conveyance of materials. |
| 3 | Renewing one V Cross arm on the 11kV Pole including dismantling and conveyance. |
| 4 | Additional rate for providing one F top bracket complete, on any type of HT pole. |
| 5 | Fitting and providing one HT Stay for 11kV pole, including digging and back filling pit in ordinary soil. |
| 6 | Providing additional HT stay insulator in existing stay. |
| 7 | Renewal of existing damaged/broken old 11kV Stay to the existing stay rod. |
| 8 | Straightening one slanted 11kV pole after unbinding the line and binding the line after work. |
| 9 | Dismantling (without damage) one km 11kV line (three conductors) including dismantling cross arm, insulators, disc, disconnecting jumper connection, rolling the conductor and stacking the materials. |
| 10 | DismantlingonedamagedLTTW/RSJ/Railpoleafterdisconnecting stays, strut etc. attached thereon and stacking the same. |
| 11 | Transferring LT single phase 2/3 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators, refitting the same on the new pole, binding etc. complete. |
| 12 | Additionalrateforrefitting/redoingoneShackleSet,includingreshacling one span, while renewing any type of LT pole. |
| 13 | Stringing of one km 3 PH 11kV line with XLPE Insulated ACSR Raccoon or equivalant (3 conductors) after fitting insulators, binding conductors to pin insulators using suitable tie and anchoring with wedge type anchoring clamps including cutting and removing tree branches wherever necessary excluding cut point works. |
| 14 | Insertion of one HTPSC pole in existing HT/LTlineincludingdigging& backfillingofpitinordinary soil,fittingcrossarm,insulator,bindingetc. |
| 15 | Additional rate for excavation of one Pit for Coil Earthing in Laterite |
| 16 | ProvidingoneCoilEarthusingNo.8GI-earthwire(50mmdia,115turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling. |
| 17 | FittingandprovidingoneStrutusingHTPSCpoleincludingdiggingand back filling pit in ordinary soil. |
| 18 | AdditionalrateforexcavationofonePitforHTPole/HTStayinHard Laterite. |
| 19 | Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 20 | Providingconcretemuffingofsize0.45x0.45x1.5m(0.5maboveGLand 1m below GL). Excavation 0.45x0.45x1m, concrete (1:3:6, 20mm) 0.45x0.45x1.5m, Plastering (1:3) 12mm 0.45x0.45mx5sides. |
| 21 | LabourchargesforloadingHTPSCpolefromthestackingplaceand unloading the same at work site (transportation by any vehicle). |
| 22 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. |
| 23 | Transportingpolesbyhiredvehicletoadistancebeyond5kmand carrying upto 4 numbers of poles. (Running km) |
| 24 | Dismantling (without damage) one 11kV pole after disconnecting stays, ) strut etc. attached thereon and stacking the same |
| 25 | Fitting and erecting one HT A type Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing). |
| 26 | Fitting one set AB switch on existing DP, giving connection and drawing sufficientlengthofGIearthingleadstothegroundforearthing,excluding provision of earthing. |
| 27 | FittingoneAdditional2.4m/3mChannelcrossarm(100x50x6mm),in existing 11kV DP including conveyance of materials. |
| 28 | Transferring LT three phase 4/5 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators, refitting the same on the new pole, binding etc. complete. |
| 29 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 30 | Quoted Amount of BOQ1 in figures |
| 31 | GST Rate in percentage Please Enable Macros to View BoQ information |