| 1 | Earth Work in correcting internal section of Soraon branch from km 0.000 to km 4.459 by hydrraulick excavator (poclain/JCB) with side slop cutting at required slop including all lead & lift in all type of soil with proper disposal , compaction & dressing of bank and daula as per direction of Engineer in charge. |
| 2 | Earth Work in Restoration of Daula of Soraon branch From km. 0.000 to 4.459 with manual compaction and dressing as per direction of engineer in charge. |
| 3 | Earth Work in excavation of foundation in all type of soil including all lead,lift T&P etc. complete. As per direction of Engineer in charge. |
| 4 | Laying Plain Cement Concrete in 1:3:6 with maximum size of 40 mm crushed stone ballast & Coarse sand having F.M. not less than 2.0 including all cost of labour,materials,T&P etc. compaction required for proper completion of work. As per direction of Engineer in charge. |
| 5 | 1st class B/W in 1:4 C.M. Coarse sand having F.M. not less than 2.0 including all cost of labour,materials,T&P etc. compaction required for proper completion of work. As per direction of Engineer in charge. |
| 6 | Supply & Laying LDPE Film below C.C Lining including all cost of material,labour T&P etc. complete. As per direction of Engineer in charge. |
| 7 | Laying Plain Cement Concrete in 1:2:4 with maximum size 20 mm crushed stone ballast & Coarse sand having F.M. not less than 2.0 including all cost of labour,materials,T&P etc. compaction required for proper completion of work. As per direction of Engineer in charge. |
| 8 | Cement pointing 1:2 (struck deep ) C.M. including all cost of labour,materials,T&P etc. for proper completion of work. As per direction of Engineer in charge. |
| 9 | Cement Plastering 1:4 C.M. including all cost of labour,materials,T&P etc. for proper completion of work. As per direction of Engineer in charge. |
| 10 | Ist class brick soling on edge both side i/c cost of Labour & T&P etc. complete. As per direction of Engineer in charge. |
| 11 | Painting two coat synthetic enamel paint including all material,labour T&P etc. complete. As per direction of Engineer in charge. |
| 12 | Earth Work in making canal section in all type of soil including all lead ,lift T&P etc. complete. As per direction of Engineer in charge. |
| 13 | Finishing side post and parapet with two coats of water proofing cement paint of approved make & quality of required shade on wall surface over one coat of white cement primer with preparation of surface i/c cost of material T&P etc. As per direction of Engineer in charge. |
| 14 | Supplying & fabrication and fixing of Mild steel/iron work in grill, gates, railing, door, window frames including cutting, drilling, welding, riveting and fixing hinges where necessary with fixing in position including cost of all material, labour, T&P etc. required for proper completion of work with one coat of red oxide primer. As per direction of Engineer in charge. |
| 15 | Providing and fixing 100 mm dia R.C.C. N.P.2 pipe including all cost of material,labour T&P etc. complete. As per direction of Engineer in charge. Please Enable Macros to View BoQ information |