| 1 | Preparation and consolidation of sub grade with power road roller of 8 to 12 sonne capacity after excavating earth to an average of 22.5 cm depth, dressing to camber and consolidating with road roller including making good the undulations etc and re-rolling the sub grade and disposal of surplus earthwith lead upto 50metres. |
| 2 | Providing and Laying good earth mixed with lime 12% and ramming compacting manually completed job. |
| 3 | Banking excavated carth in layers not exceeding 20 cm in depth, breaking clods, watering, rolling cach layer with ½ tonne roller, or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up, in embankments for roads, flood banks, marginal banks, and guide banks etc., lead upto 50 m and lift upto 1.5 m (excl, ramming with PRR and watering) All kinds of soil. |
| 4 | Providing and Laying HDPE sheet Pond Linner 300-500 micron incl. carriage and fixing of joints and overlaps etc complete job. |
| 5 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement-All work up to plinth level 1:15:3 (1 cement: 1.5 coarse sand (zone-III) derived from natural sources: 3 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 6 | Providing/fixing of Reinforcement for RCC work including straightening cutting, bending, placing, in position and binding all complete. Hot rolled deformed bars.Incluidng all carriage complete. |
| 7 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1.3.6 (1 Cement 3 coarse sand (zone-III) derived from natural sources 6 graded stone aggregate 20 mm nominal size derived from natural sources) (inlet & Out let channel). |
| 8 | Providing and fixing of Steel Gate of Size 0.45mx0.6 m including opening and closing option. |
| 9 | Providing and laying of PVC pipe 150mm including trench cutting carriage of material all complete job as per site requirement. |
| 10 | Providing Supplying and fixing and commissionig of Sluice valve of dia 300 mm incluidng carriage of material and all job. |
| 11 | Hand Packed stone into wire crate incl. c/o stone, crate and carriage of stone by MT 6km H/Load 50 Mtr (for protection to hill side slope & Embankment). |
| 12 | Dewatering/Diversion of water caused by spring seepage/river tidal etc complete Job. |
| 13 | Carriage of material from source to site by mechanical means. |
| 14 | Cement/steel at an avg lead of 18 km Qty from table |
| 15 | Sand/Stone aggregate at an avg lead of 9 km Qty from table Please Enable Macros to View BoQ information |