| 1 | repairing of 25 HP VT pump set & 10 HP submersible pump set and other allied works at RAW WATER P/P for old Rural W/S scheme netarhat under D.W. & .S. Mech. Division Gumla. |
| 2 | Cost of dismantling the vt motor pump set and taking out bowl assembly from the intake well by supplying all labour, tools and tackles etc at site. |
| 3 | Cost towards dismantling, checking and repairing and rewinding of 25 H.P VT WPIL Limited squirrel cage induction motor with all labour, tools & tackles, rewinding material such as supper enameled copper wire of proper gauge and weight, heating, varnishing and refitting etc at site. (Weight 22 kg approx)including loading unloading and transportation charge. |
| 4 | Cost for complete opening dismantling and refitting after repairing of 25 HP VT ball assembly with S/F top and bottom G.M. Bush – 2 Nos. as per sample, intermediate bush 6 Nos. as per sample, pump shaft of S.S. making as per sample size – 01 No, wearing ring – 5 Nos. G.M. impeller as per sample – 5 Nos. including remetalling turning & polishing and making same size of ball assembly housing etc. all complete with all labour and materials as required on site. |
| 5 | Making and fitting shaft coupling of sleeve muff |
| 6 | Supplying and fitting intermediate rising main shaft bearing |
| 7 | Cost for S/F of head shaft of S.S. non-magnetic materials as per sample. |
| 8 | Cost for S/F of C.I. spider bearing with cut less rubber bush for suitable of 6” dia column pipe. |
| 9 | Cost for repairing with new making and fitting of stuffing box bush with gland packing tightner of in discharge head 20 HP VT p/sets with all labour and materials. |
| 10 | Cost for S/F of line shaft of S.S. non-magnetic materials as per sample. |
| 11 | Cost towards supply and fiting of 25 H.P.(VT)pumpset FASD starter.(make isi reputed brand) |
| 12 | Supplying and laying 20 mm2 PVC insulated and PVC sheathed 3 core copper cable from panel to starter and motor. |
| 13 | Cost towards taken out & then dismantle the 10HP submersible motor pump set for its complete new rewinding after cleaning the stator of 10HP submersible 3phase, 50c/s, 2900rpm working voltage 380/400 volt with all insulating material such as PVC insulated copper wiring kit with all insulating material and assembling the set with cable joining & testing on full load with all labour tool & tackles all complete at site including transportation charge. |
| 14 | Cost for opening of 10HP submersible pump for changing its damaged impellors & steel bus key, coupling & fitting the same & testing all complete. |
| 15 | Cost of supplying and laying 6 Sq mm 3 core PVC Sheathed flat submersible copper cable of 650 volt grad ISI marked Finolex universal/polycable make from starter to motor. |
| 16 | Cost towards repairing of 10 H.P.(SUBMERSIBLE) pump set FASD starter by replacing its contactor, relay & Timer and socketing Cu lugs etc . |
| 17 | Cost of consumable materials such as grease gland packing,packing paper,cotton waste,bulb,rubber insertion,nut bolt. Etc required for jointing all suction and delivery side etc at site. |
| 18 | S/F 45 w led street light including its accessories labour,tools & technicians etc. at site all complete |
| 19 | repairing of 75 KVA Servo controlled powerline Voltage stabilizer at Raw water p/p for Old Rural Water supply scheme Netarhat under D.W.& S. Mechanical Division Gumla. |
| 20 | Disconnecting all electric line and joints and dismantle the 100 KVA Servo Controlled power line voltage stabilizer for checking defects and removing them with all labour tools and tackles etc at site |
| 21 | Supplying and fitting 10Kg operating motor |
| 22 | Supplying and fitting 96 mm2 voltmeter(0-500V) |
| 23 | Supplying and fitting 96 mm2 Ammeter(0-100A) |
| 24 | Supplying and fitting Big neon light |
| 25 | Supplying and fitting control card |
| 26 | Supplying and fitting variac autotransformer 80Amp |
| 27 | Supplying and fitting control transformer |
| 28 | Supplying and fitting change over switch 200 A of L&T/ Havell’s make/ISI mark |
| 29 | Cost towards thorough overhauling and reassembling at site |
| 30 | Making earthing and neutral wires from transformer to OCB and stabilizer etc all complete Please Enable Macros to View BoQ information |