| 1 | Earth work |
| 2 | Excavation for Structures A. Without dewatering.Earthwork in excavation for structures as per drawing andMoRD technical specifications Clause 305.1 includingsetting out, construction of shoring & bracing, removal ofstumps & other deleterious material and disposal upto alead of 50 m, dressing of sides & bottom and backfilling intrenches with excavated suitable material.Ordinary Soil |
| 3 | Filling in foundation trenches as per drawing & MoRDtechnical specification Clause 305.3.9, 1200.I Sand filling |
| 4 | Cement Concrete Work |
| 5 | Providing concrete for plain/reinforced concrete in openfoundations complete including formwork as per drawings& MoRD technical specifications Clauses 802, 803, 900,1202 and 1203. (including centering, shuttering, stagingetc. but excluding reinforcement).P.C.C grade M 10(i) Nominal mix 1:3:6 |
| 6 | Reinforced Cement Concrete Work |
| 7 | Supplying, fitting & placing Thermo-Mechanically treatedbar/ Cold twisted deformed steel bar reinforcement infoundation complete as per drawings & MoRD technicalspecifications Clauses 1000 & 1202. |
| 8 | Plain/reinforced cement concrete in substructure complete including formwork as per drawings & MoRD technical specification Clauses 802, 804, 805, 806, 807, 900, 1202 & 1204. (including centering, shuttering, staging etc. but excluding reinforcement)V. R.C.C grade M-20 (1:2:4) (Nominal mix)i) upto 5 m height |
| 9 | STEEL WORK |
| 10 | Providing structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete as required. |
| 11 | SUB-HEAD : BRICK WORK |
| 12 | Half brick masonry work with first class bricks in foundation and plinth including cost of all materials as required complete:-In cement mortar 1:4 ( 1 cement : 4 fine sand ). |
| 13 | First class brick work in foundation and plinth including cost of all materials as required complete:-In cement mortar 1:4 ( 1 cement : 4 fine sand ). |
| 14 | FINISHING WORK |
| 15 | 12 mm cement plaster of mixCement mortar 1:4 (1 cement : 4 fine sand) |
| 16 | Painting Steel work with Deluxe Multi Surface Paint to givean even shade. Two or more coat applied @ 0.90 ltr/ 10sqm over an under coat of primer applied @ 0.80 ltr/ 10sqm of approved brand and manufacture Please Enable Macros to View BoQ information |