| 1 | Clearing Grass and removal of rubbish up to a distance of 50 meters outside the periphery of the area with all labour charges, T & P etc. required for the work including labour welfare cess etc. complete as per direction of the Engineer-in-charge |
| 2 | Excavation of foundation in ordinary soil with intial lead of 50m and initial lift of 1.5m including rough dressing levelling the bed and depositing the excavated earth away from worksite etc. complete as per specification and direction of the Engineer-in-charge |
| 3 | Filling foundation and plinth with sand from approved river including well waterred and rammed etc. complete with cost, conveyance, royality of sand including all labour, T & P EMF,DMF and additional charge labour welfare cess etc. complete as specification and direction of the Engineer-in-charge |
| 4 | Cement Concrete (1:3:6) with 40mm size crusher broken hard granite metal from approved quarry including cost, conveyance, royality of all materials required for the work with all leads, lifts, delifts, all labour T & P labour welfare cess etc. EMF,DMF and additional charge complete as per specification and direction of the Engineer-in-charge |
| 5 | Cement Concrete (1:2:4) with 12mm size crusher broken hard granite metal from approved quarry including cost, conveyance, royality of all materials required for the work with all leads, lifts, delifts, all labour T & P labour welfare cess etc. EMF,DMF and additional charge complete as per specification and direction of the Engineer-in-charge |
| 6 | Rigid smooth centering and shuttering for RCC works super structures, plinth band, footing bases of columns etc. including false works and dismentalling then after acasting including cost, conveyance of all materials required for the work with all labour, T & P labour welfare cess etc. complete as per specification and direction of the Engineer-in-charge |
| 7 | Laying and fixing in position RCC hume pipes (NP-3) 1200mm dia at worksite with collars jointed with cement mortar (1:3) complete excluding cost, conveyance and taxes of spun pipes and cost of collars but with all labour charges, T & P required for the work and labour welfare cess etc. complete as per direction of the Engineer-in-charge |
| 8 | Earth work in suitable type of soil in approved borrow area, loading into transport vehicle manually or mechanically and transportation of earth by mechanical means and unloading the same over the approved surface of the embankment in proper profiles with all leads of 1 km, lifts,delifts including rough dressing and breaking the clods in to 5 cm to 7 cm size including removal of all roots, bushes from transported earth with all cost, carriage, royality, labour welfare cess and laying in layers not exceeding 22.50cm in depth including watering and oridinary compaction by sheep foot roller with hire and running charges of all labour, T & P, cost of fuel, lubricant, cost of labour, carriage, royality EMF, DMF, additional charges, cess, taxes, etc. all complete as per specification and direction of the Engineer-in-Charge. (Measurement will be taken on finished level section only and earth to be arrange by the contractor at his own cost and responsibility) |
| 9 | Providing dry rubble rock toe to the ambankment with blasted and quarried hard granite stone boulder of size not leass than 0.0025 cum of approved quality with all leads, lifts and delifts including mechanical transporation stacking at worksite for pre-measurement coveying from stacks and dumping with packing interstices properly and surface packing to proper line and level with cost, conveyance, royality, EMF, DMF, and additional charges and all other taxes of all materials with all labour, T & P required for the work, labour welfare cess etc. complete as per specififcation and direction of the Engineer-in-charge Please Enable Macros to View BoQ information |