| 1 | Maintenanace work |
| 2 | 2.5.2.A:Dismantling of Structures<br> Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.<br>(II) By Mechanical Means <br> (A) Cement Concrete |
| 3 | 2.7.E:Dismantling Stone Masonry as per Technical Specification Clause 202.<br> Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202.<br>(E) Dismantling Stone Pitching / Dry Stone Spalls |
| 4 | 3.5.2:Excavation in Soil with Dozer with lead upto 100 m <br> Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 m, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections. |
| 5 | OD519819/2025-2026:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 <br> I. P.C.C grade M 10 <br> (i) Nominal mix 1:3:6 |
| 6 | 11.4.2.1:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 <br>II. P.C.C grade M 15 <br> (i) Nominal mix (1:2.5:5) |
| 7 | 11.4.4:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203<br> IV. R.C.C grade M 20 |
| 8 | 11.8:Supplying, fitting and placingTMT bar reinforcement in foundation complete as per drawings and technical specifications Clauses 1000 and 1202 |
| 9 | 2.14.2.A:Dismantling of Flexible Pavements<br> Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 100 m, stacking serviceable and unserviceable materials separately as per Technical Specification Clause 202 <br> (II) By Mechanical Means<br> (A) Bituminous Courses |
| 10 | 3.2:Preparation of Foundation for Embankment <br> Scarifying Existing Bituminous Surface to a Depth of 150 mm by Mechanical Means <br> Scarifying the existing bituminous road surface to a depth of 150 mm and disposal of scarified material with a lift upto 3 m and lead upto 1000 m as per Technical Specification Clause 301.4. |
| 11 | 3.14:Construction of Subgrade and Earthen Shoulders<br> Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. |
| 12 | 4.1.A.2:Granular Sub-base with Well Graded Material (Table 400.1)<br>(A) By Mix in Place Method <br> Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. (ii) For Grading II Material |
| 13 | 4.9:Wet Mix Macadam <br> Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. <br> By Mechanical Means with 1 km lead |
| 14 | 75.5.1.1pb:Prime Coat - Low porosity - With Packed Bitumen Rates <br> Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502 |
| 15 | 75.5.2.3pb:Tack Coat - With Packed Bitumen Rates <br> Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per Technical Specification Clause 503. |
| 16 | 75.5.11.1.A.2pb:Mix Seal Surfacing - Manual Means - Type A - Bitumen S-65 - Packed Bitumen Rates <br> Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.9 mm (Type-A) or 13.2 mm to 0.9 mm (Type-B) aggregates using penetration grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 8-10 kN static roller and finishing to required level and grades as per Technical Specification Clause 509 <br> By Manual Means <br> Type A <br> (II) Bitumen (S-65) |
| 17 | 75.8.1.1:Providing plain/reinforced concrete(1 cement:2 fine aggregate: 4 course aggregate) forsubstructure as per drawings and technical specifications Clause 802, 803, 1202 & 1203as required including compaction, finishing and tamping etc .complete. Max. size ofcourse aggregate not exceeding 25mm , mixed in concrete mixer etc complete as perspecification(i) Nominal mix (1:2:4) Please Enable Macros to View BoQ information |