| 1 | E/W in foundation in all kind of soil with all lead and lift and including back filling, watering, ramming of excavated earth into the trenches and removal and disposal of surplus earth as directed by Engineer-in-charge within a distance of 30M from the foundation trenches. |
| 2 | Laying of C.C in (1:3:6) with stone ballast (20mm to 40mm) size and coarse sand FM not less than 2 including all cost of materials labour and T&P complete.as per direction by Engineer in charge. |
| 3 | Centering and shuttering for R.C.C. work including cost of all materials, labour and T&P etc for proper completion of work as per direction by Engineer-in-Charge |
| 4 | Bending, binding ,cutting,placing in position steel reinforcement including materials with cost of binding wire and tack welding for proper completion of work. As per direction of Engineer in Charge. |
| 5 | Reinforced cement concrete (1:1.5:3) in all RCC work with Coarse sand having F.M. Not less than 2, Crushed Stone Aggregate of size (10 mm to 20 mm) Mechanically mixed and properly compacted by Vibrator including cost of all materials labours T&P etc. as per direction of Engineer in charge. |
| 6 | M 150 class brick work in 1:4 CM with coarse sand FM not less than 2 including cost of all material, labour and T&P etc. Complete. as per direction by Engineer in charge. |
| 7 | Filling 100mm thick coarse sand in filter material including cost of all material, labour and T&P etc. Complete. as per direction by Engineer in charge. |
| 8 | Providing and lying 150 micron thick L.D.P.E film including cost of all material ,labour etc.. |
| 9 | Filling sealing compound betwwen constraction & contraction joint in groove including cost of all material ,labour etc. |
| 10 | Earth work in making Road Diversion for V.R.B. Construction including all lead , lift, labour and T&P etc.as per direction of engineer in charge |
| 11 | Running of 05 H.P generator set pump for dewatering including arangements of pump suction and delivery pipes and other accessories at site including cost of all material labour and T & P etc for complete work as directed by engineer in charge as per ID specification. |
| 12 | Dismentaling of old brick work including stacking of material within a distance of 60M as per direction of Engineer in charge. |
| 13 | Dismentaling of RCC work including stacking of material within a distance of 60M as per direction of Engineer in charge. |
| 14 | Dismentaling of PCC work including stacking of material within a distance of 60M as per direction of Engineer in charge. |
| 15 | Providing and fixing of P.V.C.Pipe 110 mm dia 1.0 m c/c ,average length 0.60 m each for drainage spout and weep hole pipe. |
| 16 | Finishing walls with water proofing cement paint of approved quality make such as super snowcem in two coat over one coat of white cement primer including brushing the surface curing and cost of all materials. |
| 17 | Providing & Fixing wheel gaured including all cost of material labour T&P etc. |
| 18 | Dry brick on edge soling with 1st class brick including preparation of sub-grade to prescribed camber, filling joint with Local sand including cost of material, labour and T&P etc for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification. |
| 19 | Laying C.C. M-20 (1:1.5:3) in Sleeper with cement Dalla stone grit 10 mm to 20 mm size &Coarse sand including cost of all material & labour T&P etc. |
| 20 | Laying C.C. M-20 (1:1.5:3) in Lining with cement Dalla stone grit 10 mm to 20 mm size &Coarse sand including cost of all material & labour T&P etc. Please Enable Macros to View BoQ information |