| 1 | Dismentaling of brick work including stacking of material within a distance of 60M as per direction of Engineer in charge. |
| 2 | Dismentaling Cement Concrete including stacking of material within a distance of 60M as per direction of Engineer in charge. |
| 3 | E/W in foundation in all kind of soil with all lead and lift and including back filling, watering, ramming of excavated earth into the trenches and removal and disposal of surplus earth as directed by Engineer-in-charge within a distance of 30M from the foundation trenches. |
| 4 | Earth work for making embankment of service road in all type of soil with all lead and lift including proper disposal of excess earth as per direction of Engineer-in-charge. |
| 5 | Laying of C.C in (1:3:6) with stone ballast (20mm to 40mm) size and coarse sand FM not less than 2 including all cost of materials labour and T&P complete. as per direction of Engineer in charge. |
| 6 | Laying C.C. (1 : 1.5 : 3) with coarse sand F.M. Not less than 2, Crushed Stone Aggregate of size (10 mm to 20 mm)including all cost of material, labour and T&P etc. as per direction of Engineer in charge. |
| 7 | Reinforced cement concrete (1:1.5:3) in all RCC work with Coarse sand having F.M. Not less than 2, Crushed Stone Aggregate of size (10 mm to 20 mm) Mechanically mixed and properly compacted by Vibrator including cost of all materials labours T&P etc. as per direction of Engineer in charge. |
| 8 | Centering and shuttering for R.C.C. work including cost of all materials, labour and T&P etc for proper completion of work as per direction by Engineer-in-Charge |
| 9 | Brick work in 1:4 CM with course sand F.M. Not less than 2, including all cost of materials,T&P and labours and proper completion of work. As per direction of Engineer in Charge. |
| 10 | Providing and laying Sand (F.M. Not less than 2) filling for Inverted filter including materials T&P labours for proper completion of work. As per direction of Engineer in Charge. |
| 11 | Providing and laying Aggregate filling for Graded filter size 4.75 mm to 10.00 mm including materials T&P labours for proper completion of work. As per direction of Engineer in Charge. |
| 12 | providin and laying coarse Aggregate filling for Graded filter size 10.00 mm to 20.00 mm including materials T&P labours for proper completion of work. As per direction of Engineer in Charge. |
| 13 | 1st class brick work in 1:3 cement mortar with coarse sand (F.M. Not less than 2) including all cost of materials,T&P and labours for proper completion of work. As per direction of Engineer in Charge. |
| 14 | Cement pointing struck in 1:2 cm including all cost of materials,T&P and labours for proper completion of work. As per direction of Engineer in Charge. |
| 15 | Laying of mirzapur stone boulder size not less than 300mm and weight less than 40 kg including cost of all material labour T&P etc required for proper completion of work. |
| 16 | Dry Brick on edge soling including preparation of subgrade to prescribed camber, filling joints with local sand/earth |
| 17 | Bending, binding ,cutting,placing in position steel reinforcement including materials with cost of binding wire and tack welding for proper completion of work. As per direction of Engineer in Charge. |
| 18 | Fixing wheel guard stone including cost of all material ,labour, t&p etc. required for proper completion of work |
| 19 | Finishing wall with acrylic smooth exterior paint of required shade new work (two or more coats applied @ 1.67 litre/10 sqm over and including priming coat of exterior primer applied @0.90 litre /10 sqm) |
| 20 | Fabrication of head regulator steel Gate/Iron work including oling,Greasing , painting with cost of all material ,labour and T&P etc. Required for proper completion of work. |
| 21 | Running of 05 H.P generator set pump for dewatering including arangements of pump suction and delivery pipes and other accessories at site including cost of all material labour and T & P etc for complete work as directed by engineer in charge as per ID specification. |
| 22 | S/F PVC pipe of 75 mm dia including cost of pipe, other material, labour, T&Petc. Required for complete work as directed by Engineer in charge and as per drawing and I.D. Please Enable Macros to View BoQ information |