| 1 | Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000m as per technical specification clause 301.5 |
| 2 | Excavation in foundation in ordinary soil, loame, clay or sand inculuding lift upto 1.5 m & lead upto 30m including filling watering & ramming of excavated earth into the trenches or into the space between the building & the sides of foundation trenches or in to the plinth removal & disposal of surplus earth as directed by the engineer in charge upto a distance of 30mfrom the foundation trenches. SI. No. 251. |
| 3 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. |
| 4 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness hand packing rolling with smooth wheel roller 80-100 Kn in stages to proper grade and camber applying and brooming stone screening / binding material to fill up the interstics of coarse aggregate, watering and compacting to the required dencity . Grading - II ( with 45-63 mm size stone ballast) As per technical specification clause 405. |
| 5 | Concrete with the 4 cm guage Brick Ballast,Fine Local sand of 1.25 F.M and cement in proportion of 12:6:1 in foundation and under floor including supply of all material and T&P etc. required for proper completion of the work as P.W.D S.I. No 273 |
| 6 | First class Brick work in 1:4 cement and coarse Sand morter in foundation & Plinth inculding supply of all materials Labour T & P etc.required for proper completion of work. As per S.I. No. 305. |
| 7 | Cement Concrete with 20 mm. gauge approved stone grit ; approved Coarse Sand and Cement in the proportion of 4:2:1 inculding supply of all Material, Labour and T & P etc. required for proper completion the work. As per S.I. No. 279(i) |
| 8 | R.C.C. Work with cement approved coarse sand and 2cm. Gauge approved stone ballast in the proportion of 1:1½:3 in lintels of doors and windows excluding supply of reinforcement and its binding but including its fixing and necessary centering and shuttering etc. and also inculding supply of all Material, Labour and T & P etc. required for proper completion of the work. As per S.I. No. 283A. |
| 9 | Mild steel or iron work in plain work such as reinforced concrete or reinforced brick work (when not included in an over all rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of all steel and wastage and over lapping & hooks. S.I.No. 504 |
| 10 | Providing and laying of factory made 80 mm thick Interlocking cement concrete tiles (30mpa) including 25mm thick compacted bed of fine sand compacting and proper embedding/ laying of Interlocking tiles leveling and dressing of surface to required level and slope, filling joints with fine sand including the cost of material, labour T&P etc.required for proper completion of work as directed by Engineer-in-Charge |
| 11 | Supply & Fixing of Informatory Sign Board Rates Sanction SE/RED Please Enable Macros to View BoQ information |