| 1 | Dismantling and removing old cement concrete including stacking the useful materials for reuse and removing the debris |
| 2 | Earth work in Slushy soil including dressing and leveling the bed and depositing the soil with intial lead and lift etc complete. |
| 3 | Supplying and filling the foundation and plinth with clean coarse river sand of approved quality from approved quarry, laying in layers not exceeding 150mm thick, watering and ramming including cost, conveyance royalty and taxes of all |
| 4 | Providing cement concrete for unreinforced cement concrete works of proportion (1:4:8) with 40mm size crusher broken hard granite (CBHG) metal of approved quality and from approved quarry in foundation bed and floors including cost of labour, materials (inclusive of cost, conveyance, royalties, taxes, loading and unloading) & equipments for handing, |
| 5 | Providing & laying cement concrete of prop. (1:2:4) using 12mm size, screened, washed hard black crusher broken granite chips of approved quality & from approved quarry including laying in the layers not exceeding 150mm thick hoisting, lowering, laying, watering and curing etc. complete to the required levels including cost, conveyance, royalty and |
| 6 | CC work of prop M20 having minimum compressive strength (in work test) 200kg./cm2 in 15cm cubes at 28days after mixing 516using 12mm to 20mm size (1/2\\" to %\\") crusher broken hard and test conducted in accordance with I.S. 456 and I.S. black granite chips of 20mm size (not to exreed 25%) of approved quality & from approved quarry including hosting. lowering, laying and compacting concrete with vibrator, watering and curing for 28days, cost of rigid and smooth centering & shuttering and finishing to exposed surface smooth direction of the Engineer in charge including cost, conveyance, providing, grooves or beads wherever necessary as per royalties & taxes of all materials and cost of all labour, T&P etc. as required for the work completion in all respects as per direction of Engineer in charge but excluding cost of M.S rod /Tor steel and binding wires and labour. |
| 7 | Straightening, cutting, bending and binding, welding and jointing (if necessary) coiled/ bent up MS Rods /Tor Steel/deformed rods etc. including hoisting, placing in position, tying the grills binding with 18 to 20 gauge binding wire required for R.C.C work including cost, conveyance, taxes of all materials, cost of all labour, T&P etc. as required for the work complete (weight of binding wire will not be considered) as |
| 8 | Rigid smooth centering and shuttering for R.C.C work including false work and dismantling after casting including cost of all labour, materials, T&P required etc. as per the direction of |
| 9 | Remove excavated & dismantled materials from the site by mechanical means with loading and unloading the same within 5 kms lead as per direction of enginner in charg Please Enable Macros to View BoQ information |