| 1 | Cariage of following material from centre stores, Asfabad to site of work through the Kachcha and Pakka road including the work of its loading and unloading at the respective ends in the area of EDD, Sirsaganj including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work . [Distence 00.00 Km. to 20.00 Km.] | Cariage of following material from centre stores, Asfabad to site of work through the Kachcha and Pakka road including the work of its loading and unloading at the respective ends in the area of EDD, Sirsaganj including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work . [Distence 00.00 Km. to 20.00 Km.] |
| 2 | 8.5 mtr. Long PCC Poles | 8.5 mtr. Long PCC Poles |
| 3 | 11 KV X - arms, Pin Insulators, clamps Conductor and 11 KV & 33KV Jointing Kits, terminating Kits other required line material, if any. | 11 KV X - arms, Pin Insulators, clamps Conductor and 11 KV & 33KV Jointing Kits, terminating Kits other required line material, if any. |
| 4 | Replacement of damaged 8.5 mtr. Long PCC pole by digging of pit and dismantling of all accessories from the existing / damaged pole and erection of single new pole including fitting all accessories including the cost of labourer, T&P etc. required for proper completion of work. | Replacement of damaged 8.5 mtr. Long PCC pole by digging of pit and dismantling of all accessories from the existing / damaged pole and erection of single new pole including fitting all accessories including the cost of labourer, T&P etc. required for proper completion of work. |
| 5 | Replacement of damaged Double pole of 8.5 mtr. Long PCC pole ( first opening of all accessories & then removing damaged poles), re - erecting D/P including fixing of Disc Insulators with fitting and other 11 KV accessories as per RESPO manual and as per direction of supervising engineer, including the cost of arrangement of labour, T&P, carrier etc, required for proper completion of work.The double pole shall be grouted in ratio 1:4:8 ( Cement, sand, brick ballast/ stone pad as per actual requirement at site. | Replacement of damaged Double pole of 8.5 mtr. Long PCC pole ( first opening of all accessories & then removing damaged poles), re - erecting D/P including fixing of Disc Insulators with fitting and other 11 KV accessories as per RESPO manual and as per direction of supervising engineer, including the cost of arrangement of labour, T&P, carrier etc, required for proper completion of work.The double pole shall be grouted in ratio 1:4:8 ( Cement, sand, brick ballast/ stone pad as per actual requirement at site. |
| 6 | Straightening of tilted following poles in the existing lines as per direction of supervising engineer including the cost of arrangement of labour, T&P carrier etc. required for proper completion of work. | Straightening of tilted following poles in the existing lines as per direction of supervising engineer including the cost of arrangement of labour, T&P carrier etc. required for proper completion of work. |
| 7 | 8.5 mtr. Long PCC Poles | 8.5 mtr. Long PCC Poles |
| 8 | 9/11 mtr ST Poles | 9/11 mtr ST Poles |
| 9 | Replacement of following damaged accessories in 11 KV/ LT line | Replacement of following damaged accessories in 11 KV/ LT line |
| 10 | 11 KV X arm with clamp | 11 KV X arm with clamp |
| 11 | 11 KV Pin Insulators with pin | 11 KV Pin Insulators with pin |
| 12 | U clamp with nut and bolt | U clamp with nut and bolt |
| 13 | Stay Clamp with nut and bolt | Stay Clamp with nut and bolt |
| 14 | LT Pin clamp | LT Pin clamp |
| 15 | Rebinding & Tightining of loose stay set at defferent places of defferent feeders as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc, required for proper completion of work. | Rebinding & Tightining of loose stay set at defferent places of defferent feeders as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc, required for proper completion of work. |
| 16 | Reconnecting of earthing rod as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc, required for proper completion of work. | Reconnecting of earthing rod as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc, required for proper completion of work. |
| 17 | RE - sagging and stringing of existing following conductor in 11 HT/LT line as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work | RE - sagging and stringing of existing following conductor in 11 HT/LT line as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work |
| 18 | ACSR Weasel conductor | ACSR Weasel conductor |
| 19 | ACSR Dog conductor | ACSR Dog conductor |
| 20 | AB conductor | AB conductor |
| 21 | RE - sagging and stringing of existing following conductor in 33 line as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work | RE - sagging and stringing of existing following conductor in 33 line as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work |
| 22 | ACSR Dog conductor | ACSR Dog conductor |
| 23 | Guarding of 11 KV line by laying, stringing sagging and binding of 02 Nos. parallel GI wire 6 SWG after providing, fabrication and fixing of guarding angle and fabrication and fixing of X - guards ( Tiles) of GI wire at distance of 3 mtr. Including the cost of arrangement of labour, T&P etc. required for proper completion of work. | Guarding of 11 KV line by laying, stringing sagging and binding of 02 Nos. parallel GI wire 6 SWG after providing, fabrication and fixing of guarding angle and fabrication and fixing of X - guards ( Tiles) of GI wire at distance of 3 mtr. Including the cost of arrangement of labour, T&P etc. required for proper completion of work. |
| 24 | Re- sagging of Guarding of 11 KV line as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc, required for proper completion of work. | Re- sagging of Guarding of 11 KV line as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc, required for proper completion of work. |
| 25 | choping of tree branches at defferent places of defferent feeders as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc, required for proper completion of work. | choping of tree branches at defferent places of defferent feeders as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc, required for proper completion of work. |
| 26 | Straightening of tilted cross arms as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc, required for proper completion of work. | Straightening of tilted cross arms as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc, required for proper completion of work. |
| 27 | Digging & Laying of 33 KV and 11 KV XLPE Cables and Installation of 33 KV & 11 KV terminating Kits, Jointing Kits | Digging & Laying of 33 KV and 11 KV XLPE Cables and Installation of 33 KV & 11 KV terminating Kits, Jointing Kits |