| 1 | Earth work in excavation of foundation in ordinary soil including dressing and levelling the bed and depositing the excavated soil clear of work site with all leads, lifts, delifts including removing bushes,stumps and any other foreign materials from the working area as well as from the foundation trenches with cost of all labour, T&P, taxes, hire and running charges of all machineries, labour welfare cess etc. complete in all respects as per specification and direction of the Engineer-In-Charge. |
| 2 | Filling foundation and plinth with sand in layers not exceeding 22.50cm in thickness, well watered and rammed including cost, conveyance, royalty and all other taxes of all materials with all leads,lifts and delifts, cost of all labour , T&P, taxes, labour welfare cess, E.M.F, D.M.F & addtional charges etc complete in all respects and as per specification and the direction of the Engineer-In-Charge. |
| 3 | Cement Concrete in (1:3:6) proportion using crusher broken hard granite coarse aggregate of 40 mm size of good quality collected from approved quarry free from weathered skin and all deleterious materials using screened and washed coarse sand, mixing by mechanical mixer, placing in proper position, compacting by mechanical vibrator including cost, conveyance, royalty of all materials with all leads,DMF, EMF, additional charges lifts and delifts, centering and shuttering, curing, hire and running charges of all machineries, with cost of all labour,T&P, taxes, fixing of embedments if any and labour welfare cess etc complete as per specification and direction of Engineer-in-charge. |
| 4 | Cement concrete M20 grade in approved surface using 20 mm size and down graded black hard granite crusher broken chips and sharp sand of approved grading from approved quarry for CC work conforming to specification, mixing by concrete mixture including hoisting and laying concrete in position,compacting with vibrator with all leads, lifts, delifts for mix concrete, royalty of all materials,DMF, EMF, additional charges , cess including dewatering, supplying T&P, curing for specified days by suitable means with supervision charges including mobilization and demobilization with cost of construction and dismantling of gangway and scaffolding, chute with all materials, approach road, diversion road, site illumination, hire and running charges of machineries required for the work as per approved drawing and specification complete with all cost as directed by Engineer-in-Charge. |
| 5 | Supplying, straightening, cutting, bending, binding and tying the grills using uncoated HYSD bars of designed diametres and placing in position for fabrication and fixing the reinforcement grills including laps, ties, providing chairs and welding whenever necessary with all labour, T & P including cost,Royality,DMF, EMF, additional charges conveyance of steel and binding wires with all leads, lifts and delifts and labour welfare cess etc. complete and as per the direction of Engineer-in-Charge. |
| 6 | Rigid smooth centering and shuttering for Concrete works including false works and dismantling them after casting including cost, carriage of all materials labour, T&P, taxes required for the work with all leads lifts and delifts, labour welfare cess etc. complete in all respects as per specification and direction of the Engineer-In-Charge. |
| 7 | Earth work in suitable type of soil in borrow area, loading into transport vehicle manually and transportation of earth by mechanical means and unloading the same over the approved surface of embankment in proper profiles with all leads, lifts, delifts etc. including rough dressing and breaking the clods to maximum 5 cm to 7 cm size including removal of roots, bushes, other deleterious materials from transported earth with all cost, carriage, royalty ,DMF, EMF & additional charges, labour welfare cess & laying in layers not exceeding 22.50 cm in depth with hire & running charges of all machineries with all labour & T&P, taxes required for the work etc complete in all respects as per specification and the direction of the Engineer-In-Charge. (Measurement to be taken on finished Level Sections only and earth to be arranged by the contractor at his own cost and responsibility) |
| 8 | Collecting,supplying and stacking good quality moorum from approved quarry and stacking the same at work site or at approved stack yard for premeasurement in regular box heaps of 1.50m x 1.50 m x 0.50 m to be measured as one cum and conveying from premeasured stacks and spreading the moorum over the prepared surface for sub-base not exceeding 10mm in layers to required thickness including watering and compacting to required density with P.R.R. including cost, conveyance,royalty ,DMF, EMF, additional charges and all other taxes of all materials and cost of labour , T&P, taxes required for the work including hire & running charges of machineries and labour welfare cess etc.complete in all respects,with all leads , lifts and delifts as per specification and as directed by Engineer-In-Charge. Please Enable Macros to View BoQ information |