| 1 | Clearing Jungle including uprooting of trunk vegetations grass, bush, wood trees and saplings of girth upto 30 cm. measured at a height of 1 metre above ground level & removal of rubbish upto a distance of 50 metres out side the periphery of area cleared as per S.I. No. 2.31 |
| 2 | Earth work in excavtion by mechanical means (hydraulic excavator) including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within a lead of 50m, lift upto 1.5m |
| 3 | Disposal of moorum/building rubbish/ malba/ similar unserviceable, dismantled or waste material by mechanical transport including loading, transporting, unloading to approved municipal dumping ground for lead upto 10 km for all lifts, complete as per directions of Engineer-in-charge.Note item to be applicable in urban areas having directions for restricted hours for movement/ plying of load-carrying motor vehicle of 3.5 cum or more. DAR 1.1.18 |
| 4 | Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m |
| 5 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. as per SOR No.Chapter-4 (2.27) |
| 6 | P/L cement concrete 1:3:6 having 6 part of Stone Ballast (20 mm nominal size):3 part of coarse sand :1 part of cement and curing complete i/c suplly of all materials,labour & T&P etc. required for proper completion of work.As per direction of E/I.As per SOR chapter no.-5 (4.1.5) |
| 7 | Reinforced cement concrete in open foundation complete as per drawing and technical specification. As per MoRT&H S.I. No.-12.8 & Clause 1500,1700 & 2100 (M-25) |
| 8 | Supplying, fitting & placing HYSD bar reinforcement in foundation complete as per drawing & technical specifications. As per MoRT&H S.I. No.-12.4 & Clause 1600 |
| 9 | Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-in- Charge: 2.1.1 All kinds of soil. Above 0.30 M (PWD 2.1.1) |
| 10 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:6:12 (1 Cement : 6 coarse sand (zone-III) : 12 brick aggregate 40 mm nominal size) |
| 11 | R.C.C. work with cement approved coarse sand and 20 mm. guage approved stone grit im the proportion of 1:1.5:3(1 cement : 1.5 coarse sand : 3 stone aggregates) in Footing i.e. having spans upto 6 m. excluding supply of reinforcement and its fixing and binding the same with 24 BWG binding wire and including necessary centering and shuttering etc.and also including supply of all materials, labour and tools and plants etc, required for proper completion of the works. strength of the concrete shall not beless than (M-20) |
| 12 | As in item 3 above but in R.C.C. columns in 1:1.5:3 having strength not less than [1 cement :1.5 coarse sand :3 stone aggregate] M-20 |
| 13 | As in item 3 above but in R.C.C. slab in 1:1.5:3 having strength not less than [1 cement :1.5 coarse sand :3 stone aggregate] M-20 |
| 14 | First class brick work in 1:6(one cement and six coarse sand sand of 2.25 fineness modulus) mortar in foundation & plinth including supply of all materials, labour and T & P etc reqiored for proper completion of the work. M-150 |
| 15 | Same as in item No. 12 above but in super-structure above plinth level up to floor two level (up to two storeys) including necessary cutting and moulding of brick work as required and also including honeycombed brick work in thickness of wall more than 12cms. [1:6 (one cement and six coarse sand sand of 2.25 fineness modulus)] |
| 16 | Providing and laying damp-proof course 40 mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 12.5 mm nominal size) |
| 17 | 12 mm cement plaster of mix : 1:4 (1 cement: 4 coarse sand) |
| 18 | Providing and applying plaster of paris putty of 2 mm thickness over plastered surface to prepare the surface even and smooth complete CPWD 13.26 |
| 19 | Finishing walls with textured exterior paint of required shade : New work (Two or more coats applied @ 3.28 ltr/10 sqm) over and including priming coat of exterior primer applied @ 2.20kg/ 10 sqm CPWD 13.45.1 |
| 20 | Applying priming coad over new steel and other metal surface upto 10 cm in width or firth of small articles not exceeding 0.10 Sq. area after and including preparion the surface by thorughly cleaning oil, grease, dirt and other foreign matter and scoured with wire brushes, fine stee wood Scrapper, sand papering and knotting including cost of all materials, labour, T & P cte. required for proper completion of work S.I. No.- 641+642 |
| 21 | Earth work in cutting or in embankment in regular soil excavation to be the form of regular pits not exceeding 1/2 meter (20\\") in depth and earth work in embankment to be in 20cm (8\\") layers, including ramming and dressing the surface too required levels and slopes and also including 1.5cm (5\\") lift and 30m (100\\") lead. The earth form cutting to be used in making embankment or to be deposited as spoil banks with in 30m (100\\") distance as directed by the Engineer i/c with in a lead of 50m. (PWD-251) |
| 22 | Earth work in filling around the plantation area Carted Earth of 10.0km as per S.I. No. 253+231(A) |
| 23 | Concrete with 40mm gauge approved stone ballast, sand of 1.25 fineness modulus in 8:4:1 in foundation including supply of all materials labour and tools and plants etc.required for proper completion of work |
| 24 | R.C.C. work with cement, approved course sand and 2cm gauge approved stone grit (Dala) ballast in the proportion 1:1.5:3 in R.C.C. Slab, excluding supply of steel and its bending but including fixing and binding the same with 24 B. W.G.G.I binding wire and including necessary centering and shuttering etc and also including s/o all materials required for proper completion of work. |
| 25 | Mild steel or Iron work in plain work such as reinforced cement concrete (when not included in over all rate) wrought to required shape as necessary including bending for proper completion of work, supply of steel, all labour etc. required and including westage bend, hook and authorised over lapping shall be measured. |
| 26 | Chequered terrazo tiles 22mm thick with graded marble chips of size up to 6mm in floors, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete on 20mm thick bed of cement mortar 1:4 (1cement :4course sand) Dark shade pigment used for work. |
| 27 | Hiring of Diesel pump/hiring charge of 5 KV Generator set (7.50 H.P. ) including suction and delivery pump opertor and khalasi and POL complete with all respect for Dewatering |
| 28 | Installation & ComissioningSolar Module, 110wp module with LED Lights, 18 watt Batterys 50AH (Lithium Ferro Phosphate) Poles 7 meter high i/c suplly of all materials,labour & T&P etc. required for proper completion of work.As per direction of E/I. |
| 29 | Supply and fixing of precast RCC fencing post 9 feet long |
| 30 | Supply of Galvanized iron Barbed Fencing Wire, 6mm |
| 31 | Fixing of Galvanized iron Barbed Fencing Wire, 6mm in 7 rows and in cross |
| 32 | Fabrication and fixing of MS Grill made with 40X40X6mm MS Angle, 12X12mm square bar and 30mm X6mm MS Flat around the Pond and front boundary for safety purpose including Supply of all material, labour and T&P etc. |
| 33 | Supply and fixing of MS Gate with handle bush and locking system in front boundary for safety purpose including Supply of all material, labour and T&P etc. |
| 34 | Painting or varnishing on new iron work in small areas with two coat priming & twocoat paint or varnish |
| 35 | Supplying and Installing of Cemented Bench including Supply of all material, labour and T&P etc. |
| 36 | Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3 Construction of U Type Drain |
| 37 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 Construction of U Type Drain |
| 38 | Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204 Construction of U Type Drain |
| 39 | Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 Construction of U Type Drain |
| 40 | Providing and Laying of 80 mm thick pre moulded inter locking paying M-30 Grade including 3 cm thick coarse sand bed over prepared surface including all labour T&P etc. required for proper completion of work. |
| 41 | Construction of Granular sub base by providing well graded material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and complacting with smooth wheel roller to achieved the desired density. complete as per clause 401. |
| 42 | Development of horticulture work and plantation work as per details provisions as per direction of E/I Please Enable Macros to View BoQ information |