| 1 | Dismantling and removing cement concrete including stacking the useful materials for reuse and removing the debris within 50m. lead etc. complete and as per direction of the Engineer-in-Charge. |
| 2 | Earth work in excavation of foundation in hard soil within 50M. initial lead and 1.50M. initial lift including dressing and leveling the bed and rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.30M. in depth etc. complete and as per direction of the Engineer-in-Charge. |
| 3 | Filling foundation & plinth with sand including watering and ramming incl. cost, conveyance, royalty, taxes of sand to site, all labour, T&P complete and as per specification & direction of the Engineer-in-Charge. |
| 4 | Providing and laying cement concrete of grade M10 with 40mm size CBHG metal of approved quality including cost,conveyance,royalty of materials with all labour charges, T&P,Cess,VAT etc complete in all respect as per the direction of the Engineer-in-Charge. |
| 5 | C.C. / R.C.C. works of M-15 grade with 20mm. and down grade black hard granite Crusher broken stone chips including hoisting and laying over prepared surface with ramming and including cost, conveyance and royalty of all materials and curing upto required period etc. complete and as per direction of the Engineer-in-Charge. |
| 6 | Providing and laying cement concrete of grade M-20 with 20mm down graded Crusher broken hard granite coarse aggregate with supply of all materials, labour and machineries including hoisting and laying etc. complete and as per direction of the Engineer-in-Charge. |
| 7 | Rigid smooth centering and shuttering for CC/RCC works in canal structures including false works and dismantling the same after specified date of casting including cost, conveyance and royalty of all materials and disposal of debries and clear of worksites etc. complete and as per direction of the Engineer-in-Charge. |
| 8 | Filling F & P with excavated materials with watering and ramming completed in all respect including all charges and labour welfare cess etc. completed and as per direction of the Engineer-in-Charge. |
| 9 | Earth work in excavation in ordinary soil within 50M. initial lead and 1.50M. initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.30M. in depth etc. complete and as per direction of the Engineer-in-Charge. |
| 10 | Earthwork for strenthening and sectioning the Canal embankment with any approved type of soil having good cohesion free from rocks, pebbles, roots, grass, sticks and other debries with one extra lead over the initial lead of 50M. and 1.50M. initial lift including rough dressing and breaking of clods to maximum 5Cm. to 7Cm. in size and laying in layers not exceeding 0.30M. in depth etc. complete and as per direction of the Engineer-in-Charge. |
| 11 | Supplying,fitting and placing uncoated HYSD bar for R.C.C. works including cutting, bending and binding and tying the grills and placing in position including cost of binding wire 18 to 20 gauge.etc complete as per direction of the Engineer-in-Charge . |
| 12 | Removing all type of Hume pipes& stacking within a lead of 1000 metres including earthwork & dismantling of masonry works including T & P,sorting the dismantled material, disposal of unserviceble material & stacking the serviceble material with all lifts & lead of 1000 metres. |
| 13 | Laying and fixing in position R.C.C. spun pipes with collars jointed with cement mortar 1:3 complete excluding cost of spun pipes and collars. Complete. Please Enable Macros to View BoQ information |