| 1 | PART-A (Labour Portion): |
| 2 | Production of packaged drinking water on 8 hours per shift basis of R.O. based fully automatic drinking water bottling plant with an hourly Production capacity 1200 bottles of 2000 ml capacity at Haringhata Bottling Plant in the district of Nadia by providing sufficient skilled machine operator for pet Blowing machine (1 No.), Rincing filling capping machine (1 No.), labeling machine & batch code machine (1 No.), shirnk wrapping machine (1 No.), water treatment plant (1 No.), High pressure Compressor, Low pressure Compressor, Chiller and Cooling tower (1 No.). Assistant operator cum helper for despatch of finished product to ware house (1 No.), Security guard (1 No.) per shift including providing necessary personnel for guarding arrangement round the clock. The Agency will provide sufficient man power for smooth operation security of the bottling plant as directed by E.I.C. This does not include any spares and raw materials for operation and maintenance of the bottling plant. |
| 3 | Provision of Electrician visit to oversee the overall power circuit and electrical accessories and machineries. |
| 4 | Part-B (Supervision Portion): |
| 5 | Skilled supervisor for supervision of entire installation for trouble free operation including manning, control, output data generation etc. |
| 6 | Sweeping of garbage from bins of different area inside the plant, collecting from roads, intermediate path way, back side of the plant , cleaning of surrounding surface drains, cleaning of roofs including collection of dust and also mopping of inside area of the whole plant, rooms to ensure highest level of hygenic condition inside the plant, cleaning of all grease strains thoroughly including supply of all necessary T & P items like brooms, approved disinfectant, floor cleaner, room freshner etc. as per direction of EIC. |
| 7 | Part-C |
| 8 | (Daily/Weekly/Monthly Maintenance): Making arrangement for adequate care for day to day and weekly preventive maintenance to keep the plant healthy. All the machines and apparatus need to be cleaned and washed every time before and after use. The machines and apparatus, electrical panel board switches, switch gear etc. to be monitored and checked for its proper functioning by supplying different lubrication oil and grease for daily replenishment & topping of grease (AP 2) and lubrication oil 30 grade ( RFC & labelling machine ), FRL- 32, CRC, WD-40 for pet blowing machine, Recip oil for HP compressor and other compressor oil including changing of fuse wires, tubes, bulbs etc. Weekly Maintenance to be done preferably on weekly holiday by deploying skilled man power in WTP area (4 times in month). PET Blowing, RFC, Labelling, Batch coding & Shrink Wrapping Machine( 4 times in a month) and HP compressor with Dryer, LP compressor with Dryer, Chiller, Cooling Tower, CW pump, all pneumatic conveying main etc ( 4 times in a month) and pouch filling machines (4 times in amonth).Raw materials to be kept properly in good condition and |
| 9 | Deployment of skilled technician of work force to undertake routine daily /weekly / monthly periodical machine wise maintenance work strictly adhering to the maintenance guidilines of the manufacturer including other routine (daily / weekly /monthly) maintenance work viz CIP, lubrication, greasing, tightening of nuts, checking conding of belts & air filter, alignment as required and regular upkeepment in different parts of plant including fitting of Deparmental supplied spares as and when required to ensure overall good health of the plant of whole as per direction of E.I.C. Static Portion:-WTP areas (Dual Media, UF, RO, Ozanator etc.Motive Portion:-PET blowing machine, RFC, Labeling machine, shrink wrapping machineHP compressor with dryer, LP compressor |
| 10 | with dryer, chiller tower, CW pump etc. including leakage test of entore pneumatic, conveying main including calibration of gauges.Miscellaneous Charges:-Supply, delivery & keep ready stock different lubrication oil and grease for daily replenishment / topping of grease (AP 2) and lubrication oil 30 grade RFC & labelling machine, recip oil for HP compressor and other compressor oil including changing of fuse wires, tubes, bulbs etc. |
| 11 | Making arrangement for monthly preventive maintenance by manufacturer / parent company of a) PET Blowing Machine b) RFC Machine c) Labelling Machine d) Batch Coding Machine e) High pressure Compressor with Dryer f) Low pressure Compressor with Dryer g) Chiller h) Cooling Tower i) Shrink Wrapping machine j) Water Treatment Plant by deploying Service Enginner of the parent manufacturing company as per preventive maintenance schedule with all incidental charges for setting and resetting of different critical process related field instrumena alongwith replacement of spares of these plants . A seperate register for attaing monthly preventive maintenace by the parent manufacturing company is to be kept at site duly authenticated by the concerned Engineer-In -charge and should be submitted during preparation of bill. Deployment of Service Engineer of the parent company with all conveynance for setting, re-setting and calibration of the equipment upto the level of standardi)Rinsing Filling cleaning machine (involving of 2 days)ii)Labeling machine (involving of 2 days)iii)PET blowing machine (involving of 2 days)iv)High Pressure compressor (involving of 2 days)v)Low Pressure compressor (involving of 2 days)vi)Chiller (involving of 1 day) |
| 12 | vii)Cooling tower (involving of 1 day)viii)Shrink Wrap Machine (involving of 1 day)ix)Water Treatment plant (involving of 2 days)x)Batch code machine (involving of 1 day) |
| 13 | GST 18% |
| 14 | Cess @1% Please Enable Macros to View BoQ information |