| 1 | Cutting & clearance of jungle, bushes, shurbs, Ankra / Ipomoea, Julicflora typna etc. on canal and bunds in dry / moist / slushy condition including disposal as per instruction of the Engineer in charge. Cost of wood has been deducated from rates and thus will be property of contractor after cutting. (b) For ordanary |
| 2 | Excavation including loading, unloading, disposal and dressing of excavated earth within initial lead of 50m and lift up to 1.5 m in dry or moist including dressing of excavated area dewatering wherever required complete in all respect (b)Hard / Dense soil . |
| 3 | Providing and Laying in position of Cement concrete Nominal mix (1:3:6) including leads of all construction materials, curing, compaction and finishing with rendering in cement sand mortar l:3 ( I cement : 3 coarse sand) and making good the joints excluding the cost of centering, shattering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto 20 mm |
| 4 | Providing and Laying in position of Cement concrete Nominal mix (1:2:4) including leads of all construction materials, curing, compaction and finishing with rendering in cement sand mortar l:3 ( I cement : 3 coarse sand) and making good the joints excluding the cost of centering, shattering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto 20 mm |
| 5 | Providing and Laying in position of Cement concrete Nominal mix (1:1.5:3) including leads of all construction materials, curing, compaction and finishing with rendering in cement sand mortar l:3 ( I cement : 3 coarse sand) and making good the joints excluding the cost of centering, shattering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto 20 mm |
| 6 | Centring and shuttering for slab, beam, lintels, columns, trough with or without caps and base including propering and remove. |
| 7 | Side shuttering including proping etc. complete (to achieve finish f2 (a) for block joints of foundation, stilling basins, buckets, aprons etc. (non-suspended horizontally lain mass concrete) for Dowels. |
| 8 | Supplying of M.S. reinforcement including labour charges for bending, binding and placing in position all reinforcement as per drawing including cost of binding wire and all leads and lifts using toe or ribbed bar (IS:1786-1985). |
| 9 | Extra labour charges for obstruction in laying and placing the reinforced cement concrete due to reinforcement in foundation rafts, beams, columns bases stilling basins, buckets, aprons etc. (non-suspended horizontally laid mass concrete). |
| 10 | Providing, laying & fixing in position RCC spun or hume pipe with collars (ISI 458-2003) in required size packed in gasket for hume or spun yarn & neatly finished with rich grout of cement mortar (1:3) perfectly air tight including testing of joints class NP-3.1000MM |
| 11 | Earth work in rough (borrow area) excavation for embankments in hard soil, morrum or highly weathered strata dry or moist, including laying in 20 cm layers (before compaction) and breaking of clods, sorting of grass, pebbles etc. and dressing when compacted by vibro compactor, vibro sheep foot roller, sheep foot roller/pneumatic tyred rolier to obtain dry density of at least 98% of Standard Proctor's density with initial lift of I.5m (Excluding charges for compaction and watering) including loading and un-loading wherever required complete in alI respect. |
| 12 | Hydraulic excavator/ loader like JCB/ Poclain, Hitachi etc. with all accessories (for actual site working, idle period) having bucket capacity (b) above 0.40 & upto 0.75 cum Hire charges without diesel but with operational staff M.oil, spares & lubricants (in Rs) |
| 13 | Hydraulic excavator/ loader like JCB/ Poclain, Hitachi etc. with all accessories (for actual site working, idle period) having bucket capacity (b) above 0.40 & upto 0.75 cum Provision for diesel per Km/or per hr. (in liters) Please Enable Macros to View BoQ information |