| 1 | Fitting one set (3No.) 11KV LA and giving connections excluding earthing |
| 2 | Fitting one Additional 2.4m/3m Channel cross arm (100x50x6mm), in existing 11KV DP including. conveyance of materials. |
| 3 | Transporting poles by hired vehicle to a distance up to 5km and carrying up to 4 numbers poles excluding loading & unloading charges. |
| 4 | Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at a minimum distance of 1.5m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil & backfilling |
| 5 | Providing one Coil earth using No.8 GI-earth wire (50mm dia, 115 turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling. |
| 6 | Labour charges for loading HT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 7 | Fitting one Additional 75x40mm, 1.8m channel cross arm in existing single pole including. conveyance of materials |
| 8 | Providing Cable Tie |
| 9 | Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 10 | Fitting and erecting one HT A type Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing) |
| 11 | Fitting and providing one HT stay for 11KV pole, including digging and back filling pit in ordinary soil. |
| 12 | Fitting One no MVT on existing cross arm including 2 nos end termination (for One Phase) of any rating for 11 KV AB Cable. |
| 13 | Fitting one set AB switch on existing DP, giving connection and drawing suffcient length of GI earthing leads to the ground for earthing, excluding provision of earthing. |
| 14 | Drilling hole of various sizes on existing Channel/Cross arm |
| 15 | Fitting and erecting one HT Double Pole Structure using A type Pole in position including fitting 2 No. channel cross arm, digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing leads through all cross arms to the ground for earthing (excluding provision of earthing). |
| 16 | Dismantling of 1.1 KV Aerial bunched cable of size 3 x 70 + 1 x 16 (Street Light) + 1 x 50 Sq.mm. (Insulated Messenger) |
| 17 | Dismantling ( without damage) one LT PSC/RCC pole after disconnecting stays, strut, etc. attached thereon and stacking the same |
| 18 | Stringing of 1.1 KV Aerial bunched cable of size 3 x 70 + 1 + 16 + 1 x 50 sqmm with bare/insulated Messenger through existing poles |
| 19 | Providing concrete muffing of size 0.45x0.45x10.5m(0.5m above GL and 1m below GL). Excavation 0.45x0.45x1m, concrete (1:3:6, 20mm) 0.45x0.45x1.5m, Plastering (1:3) 12mm 0.45x0.45mx5sides. |
| 20 | Erection of Anchor clamp / dead end clamp for LT ABC of any size |
| 21 | Erection of suspension clamp for LT ABC of any size |
| 22 | Installing One No. Insulation piercing connector of size Main : 16 to 95, Tap:1.5 to 16 Sq.mm |
| 23 | Stringing of 11 kV Aerial Bunched cable of size 3 x 120 +1 x 95 sqmm with bare/insulated messenger through existing poles |
| 24 | Erection of Anchor clamp/dead end clamp for 11 KV ABC of any size |
| 25 | Dismantling (without damage) one 11 KV PSC/RCC pole after disconnecting stays , strut etc. attached thereon and stacking the same. |
| 26 | Installing of Insulation piercing connector for main to service line main : 16-95 sqmm, Tap 16-95 sqmm |
| 27 | Fitting and erecting one HT PSC Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standard), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing) |
| 28 | Fitting and providing one strut using HT PSC pole including digging and back filling pit in ordinary soil. |
| 29 | Fitting and providing one HT stay for 11 KV pole using HT PSC pole including digging and back filling pits in ordinary soil, drawing sufficient length of GI earth leads to the ground for earthing (excluding provision of earthing) |
| 30 | Disconnecting and lowering down the single phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 31 | Erection of suspension clamp for 11 KV ABC of any size |
| 32 | Disconnecting and lowering down the three phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 33 | Dismantling one ordinary street light/CFL/LED fitting from existing pole and refitting the same on newly erected pole including disconnecting and reconnecting wires. |
| 34 | Dismantling one damaged LT PSc/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 35 | Pole numbering using printed Aluminium sheets of 22 SWG having size 20 x12 cm or Painting the surface of line supports where numbers are to be inscribed, Pole numbers shall be painted in circular / rectangular background, using approved quality anti algal yellow paint in two coat after scraping and cleaning the surface at a height of 2.5 metre above ground level. the number and letter should be in black synthetic enamel paint. The size of the number should be at least 2cm in height x 1.5cm in width. including cost of paint. |
| 36 | Doing one cable end termination on HT ABC of sizes upto 3x150+1x120 sqmm and connecting to existing MVT or other terminals, using the cable end termination kit supplied departmentally including charges for cable jointer etc. complete as per the direction of the departmental officers. Please Enable Macros to View BoQ information |