| 1 | Excavation in trenches, not exc 1.5 mtr wide and not exc 1.5 mtr in depth for laying of LT UG cable/poles etc in soft/loose soil and getting out complete all as specified. |
| 2 | Returning, filling in soil, including spreading, leveling watering and well ramming in layers not exceeding 25cm all as specified and directed. |
| 3 | Removing excavated material not exceeding 50m and depositing where directed at a level not exceeding 1.5 m above the starting point for any type of excavation. |
| 4 | Supply and laying DWC (Double Wall corrugated) HDPE pipe ISI marked of outer dia of following sizes polythylene including coupler and bend with smooth internal and profiled external surfae for non pressure under groundcable complete all as specified |
| 5 | (a) 50mm |
| 6 | (b) 40 mm |
| 7 | M&L for cable cover of size 80mm half round complete all as specified and directed.Note : two half round (one on top and one on bottom of cable ) shall be measured as one RM length |
| 8 | M & L for Cutting of road/hard standing and making good with PCC (1:2:4) using 20mm graded stone aggregate complete all as specified. |
| 9 | Supply in replacement & Lay in trenches in road cross / floor/pole etc, tube galvanised iron, 40 mm bore Light grade for protection of cable all as directed. |
| 10 | M&L for PCC 1:4:8, type D2, using 40mm graded stone aggragate for pole foundations, filling and mass concrete all as specified and directed. |
| 11 | M & L for PCC 1:3:6, type B1, using 20mm graded stone aggregate concrete mass filling, copping for poles etc including necessary form work all as directed. |
| 12 | Supply and fix in replacement cable insulated galvanised steel strip or wire armoured, electric power cables (heavy duty) 1100 volts grade with aluminium conductor for cross sectional area of 6 Sqmm 2 core including connections with lugs all as directed. |
| 13 | Supply, lay / fixing in replacement, commissioning of Cable XLPE insulated Galvanized steel strip or wire armoured, electric power cables (heavy duty) 1100 Volts grade with aluminium conductor of size 10 sqmm 2 core and testing all as directed. |
| 14 | Supply and lay/ fixing in replacement Cable XLPE insulated Galvanized steel strip or wire armoured, electric power cables (heavy duty) 1100 Volts grade with aluminium conductor of size 10 sqmm 4 core complete all as directed. |
| 15 | Supply and lay/ fixing in replacement Cable XLPE insulated Galvanized steel strip or wire armoured, electric power cables (heavy duty) 1100 Volts grade with stranded aluminium conductor of size 16 sqmm 4 core complete all as directed. |
| 16 | Supply and lay/ fixing in replacement Cable XLPE insulated Galvanized steel strip or wire armoured, electric power cables (heavy duty) 1100 Volts grade with stranded aluminium conductor of size 25 sqmm 4 core complete all as directed. |
| 17 | Taking out existing old corroded pole and Supply & erect in position steel tubular pole complete with MS base plate finial tapper plug cap bolt, nut, screws etc all as specified for swaged pole of type 410 SP 31 , 09 mtrs long including painting with two coats of aluminium paint over a coat of red oxide paint all as directed. NOTE: Excavation, earth work and PCC shall be measured and paid sperately. |
| 18 | Disconnecting and taking down defective street light fittings of any type/ brand from post top lantern pole or street light pole up to11 mtr height / from gate pillars and repairing and refixing the same in original position after replacing all unserviceable parts and making servicable including replacement of internal wiring all as directed. Note : (1) spares such as nults and bolts shall be included and driver if any shall be measured in item No 18&19(2) Necessary ladder or vehicle arrangement shall be provided by contractor and rate for the same deemed to be included. Please Enable Macros to View BoQ information |
| 19 | Disconnecting and taking down defective street light fittings of any type/ brand from post top lantern pole or street light pole up to11 mtr height / from gate pillars and repairing and refixing the same in original position after replacing all unserviceable parts and making servicable including replacement of internal wiring all as directed. Note : (1) spares such as nults and bolts shall be included and driver if any shall be measured in item No 18&19(2) Necessary ladder or vehicle arrangement shall be provided by contractor and rate for the same deemed to be included. Please Enable Macros to View BoQ information |