| 1 | Reconstruction of VRB at 0.488, 0.850, 1.600, 2.809, 3.800, 4.670, 5.962, 7.550, 8.350, 8.816, 9.954, 10.809, 12.370, 13.004, 14.345, 14.740, 15.262, 17.084, 17.953 and 18.765 km :Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the structure for Canal VRB, DRB, PRB and other hydraulic structures as per directed by Engineer in charge. (Complete Rate) |
| 2 | Providing & Laying in position cement concrete of specified grade excluding the cost of centering and shuttering in ratio 1:3:6 (1 cement: 3 coarse sand : 6 graded size 20-40mm nominal size) including all labour, material and T&P and royalty for proper completion of work as per directed by Engineer-in -Charge. (Complete Rate) |
| 3 | Brick work (Class M-150) in 1:4 cement mortar upto 3 m lift and 60 m lead of material including cost of all labour, material and T&P for proper completion of work as per directed by Engineer-in -Charge. (Complete Rate) |
| 4 | Centering and shuttering of R.C.C. Work including rent of shuttering material, labour and T&P required for proper completion of work for slab, lintels, sun shads, column & wall etc as per directed by Engineer-in -Charge.(Complete Rate) |
| 5 | Providing & Laying in position reinforced cement concrete of specified grade excluding the cost of centering and shuttering in ratio 1:1.5:3 (1 cement: 1.5 coarse sand : 3 graded size 20mm nominal size) including all cost of labour, material and T&P etc. and royalty for proper completion of work as per directed by Engineer-in -Charge. (Complete Rate) |
| 6 | Steel reinforcement for RCC work including straightening, cutting, bending,binding and placing in position including all cost of wires, steel, labour and T&P etc. complete for proper completion of work. |
| 7 | Pointing on brick work or brick flooring with cement mortar 1:3(1 cement : 3 sand) including all cost of labour, material and T&P etc. for proper completion of work as per direction of Engineer-in- Charge. |
| 8 | Dismentaling of Brick work in cement mortar and including stacking of material with a distance of 60 M as per direction of Engineer-in-Charge. |
| 9 | Painting work with two coat of acrylic smooth exterior paint of standard quality including cleaning the surface of all dirt, dust and other foreign matter, papering and stopping including all cost of material, labour and T&P etc. required for proper completion of work as per directed by Engineer-in-Charge. |
| 10 | Earth work in side embankment / diversion/ Dismantling etc. in ordinary soil, excavation to be in the form of irregular pits and earth work in embankment to be in 20 cm. layers, including ramming and dressing the surface to the required level and slopes and also including 1.5 m. lift and 30 m. lead. as directed by the Engineer-in-charge. |
| 11 | Printing/Painting/Writing of letters upto 10 cm height including all cost of labour and T&P etc. for proper completion of work as per direction of Engineer-in-Charge |
| 12 | C.C. lining in 20 m length in upstream and Downstream of Each Culvert:Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the structure for Canal VRB, DRB, PRB and other hydraulic structures as per directed by Engineer in charge. (Complete Rate) |
| 13 | Providing & Laying in position cement concrete of specified grade excluding the cost of centering and shuttering in ratio 1:2:4 (1 cement: 2 coarse sand : 4 graded size 20mm nominal size) including all labour, material and T&P and royalty for proper completion of work as per direction of Engineer-in-Charge. |
| 14 | Supplying /Laying of LDPE film 200 micron of 1st grade including all materials, labour and T&P etc. for proper completion of work as per directed by Engineer-in-Charge. |
| 15 | 75mm thick Cement concrete (M15) 1:2:4 (1 cement: 2 sand:4 aggregate of size 9-20 mm ) lining including all lead lift material labour T&P etc required for proper completion of work as per ID specification & direction as per direction of Engineer in Charge. (Complete) |
| 16 | Preparation of sub grade including all labour and T&P but excluding cost of earth work for proper completion of work as per directed by Engineer-in-Charge. |
| 17 | Making expansion joint filled with filling compound including all materials, labour and T&P etc. for proper completion of work as per directed by Engineer-in-Charge. |
| 18 | Centering and shuttering of CC work including rent of shuttering, material, labour T&P etc required for proper completion of work as per ID specification & direction as per direction of Engineer in Charge. |
| 19 | Dry brick on edge flooring in required pattern with bricks of class150 on a bed of 12 mm mud morter, including fillings joint with local sand, with common burnt clay non modular bricks inclusive of all lead lift material, labour T&P etc required for proper completion of work as per ID specification & direction as per direction of Engineer in Charge. |
| 20 | Supply and Fixing Retro reflective sign Board are made of 2mm thick ACP sheet to be fully covered with enginurs, grade Retro Reflective as per colour required by I/O. The retro reflective sheet shall be processed on base aluminium leased as per recommendation. Text and sign. Text and sign symbols will be computerized and fabricated on N.T. grade. The sheet with lives of extra frame of angle iron 32x32x3 mm duly painted. One a two posts of M.S. heavy duty steel pipe 1½\\" 3000mm long double side size (Size 5'x4') |
| 21 | Earthwork for Brick on Edge Work :Earth work in cutting or in embankment in ordinary soil, earth work in embankment to be in 20 cm. layers, including ramming and dressing the surface to the required level and slopes and also including 1.5 m. lift and 30 m. lead: The earth from cutting to be used in making embankment or to be deposited as spoil bank within 30 m. distance as directed by the Engineer-in-charge. |
| 22 | Uprooting sarpat moonj & jhunds form canal including its disposal etc. including all cost of materials, labour and T&P etc. required for proper completion of work as per directed by Engineer-in-Charge. |
| 23 | Outlet, Boundary Pillar and RCC Kilometer stone :Construction of Outlet as per site requirment including all cost of material, labour, T&P etc. complete as per ID specification, design and Drawing. |
| 24 | Fixing of RCC Precast Boundary Pillar including all cost of materials, labour and T&P etc. required for proper completion of work as per directed by Engineer-in-Charge. |
| 25 | Fixing of RCC Kilometer stone including all cost of materials, labour and T&P etc. required for proper completion of work as per directed by Engineer-in-Charge. Please Enable Macros to View BoQ information |