| 1 | 2.28.1 : Surface dressing of the ground including removing vegetation and in equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m.All kinds of soil |
| 2 | 2.8.1 : Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil |
| 3 | 2.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, cub.m 325.531 2 12 3906.37 CONTR consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. |
| 4 | 4.3.2 : Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) |
| 6 | 13.1.1 : 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand) |
| 7 | 13.48.1 : Finishing with Deluxe Multi surface paint system for interiors and exteriors using primer as per manufacturers specifications:Two or more coats applied on walls @ 1.25 ltr/10 sqm over and including one coat of special primer applied @ 0.75 ltr /10 sqm |
| 8 | Supplying and stacking at site 40 mm single size broken stone as per the direction of departmental staff at site for measurement at places pointed out at site including cost of mechanical transportation, loading, unloading nd stacking charges. As per the direction of departmental officials at site |
| 9 | Spreading 40 mm aggregate in the yard for depth of 150 mm with lead up to 50 m as per the direction of departmental officials at site. |
| 10 | Supplying and stacking 6 mm single size aggregate at site as per the direction of departmental staff at site for measurement at places pointed out at site including cost of mechanical transportation, loading, unloading and stacking charges. As per the direction of departmental officials. |
| 11 | Spreading 6 mm aggregate in the yard for depth of 100 mm with lead up to 50 m as per the direction of departmental officials at site Please Enable Macros to View BoQ information |