| 1 | Excavation work in excavation by manual means for foundations, drains, pipes, cables etc. (not exceeding 1.5m in width) and for shafts wells cesspits and the like not exceeding 10 sqm on plan, depth upto 1.5 M including the disposal of excavated earth upto 1 M from the cutting edge, disposed earth to be levelled and neatly dressed in all kinds of soil. |
| 2 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering- All work upto plinth level. 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size incl all lifts and carriages. |
| 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering- All work upto plinth level.1:3:6 (1 cement :3 coarse sand : 6 graded stone aggregate 40mm nominal size) incl all lifts and carriages. |
| 4 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts,struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchors blocks, plain window sills, fillets etcupto floor V level, including curing but excluding the cost of centring, shuttering and finishing with. 1:1½:3 (1 cement :1½ coarse sand: 3 graded stone aggregate 20 mm nominal size) |
| 5 | Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete Cold twisted bars |
| 6 | Painting of pillars (with superior exterior paint) including cost of labour charges including painting of Forest Department LOGO and the front face of the pillar with stencil. For mainline BPs, Red Shade: Adventure 2189 (Nerolac) and for chak BPs Yellow shade: Bumble Bee 2014. ( Nerolac) Exterior Emulsion paint is recommended incl carriage complete job. |
| 7 | Centering and shuttering including strutting propping etc and removal of form work for columns, piers, abutments, pillars, posts and struts |
| 8 | Carriage of Sand from source to site of work by M.T./H.L average |
| 9 | Carriage of Stone agg. av. (bajri) from source to site of work by M.T./H.L average Please Enable Macros to View BoQ information |