| 1 | Supply part for retrofitting of LT Panel by supply and installation | Supply part for retrofitting of LT Panel by supply & installation of 1250A,50KA,EDO ACB along with suitable bus bar rating at North & SS2 LT Panels as per technical specification & SOW. |
| 2 | Service part for retrofitting of LT Panel by supply and installation | Service part for retrofitting of LT Panel by supply & installation of 1250A,50KA,EDO ACB along with suitable bus bar rating at North & SS2 LT Panels as per technical specification & SOW. |
| 3 | Supply of Main Incoming LT Power Distribution Panels slipway | Supply of Main Incoming LT Power Distribution Panels slipway-2&3 as per Technical Spec & SOW. |
| 4 | Install, replace, test and commissioning of Main Incoming LT Power Distribution Panels slipway | Install, replace, test and commissioning of Main Incoming LT Power Distribution Panels slipway-2&3 (4Nos.) as per Technical Spec & SOW. |
| 5 | Supply of welding and Lighting panels slipway | Supply of welding and Lighting panels slipway-2&3 (17Nos) as per Technical Spec & SOW. |
| 6 | Install, replace, test and commissioning of welding and Lighting panels slipway | Install, replace, test and commissioning of welding and Lighting panels slipway-2&3 (17Nos) as per Technical Spec & SOW. |
| 7 | Supply of 3.5C X 400 Sq.mm Aluminum cable from Substation-02 to slipway | Supply of 3.5C X 400 Sq.mm Aluminum cable (from Substation-02 to slipway-2&3 Main Incoming panels) as per technical specification & SOW. |
| 8 | Laying, fixing, testing and commissioning of 3.5C X 400 Sq.mm Aluminum cable from Substation-02 to slipway | Laying, fixing, testing and commissioning of 3.5C X 400 Sq.mm Aluminum cable (from Substation-02 to slipway-2&3 Main Incoming panels) as per technical specification & SOW. |
| 9 | Supply of 3.5CX 185 Sq.mm Aluminum cable from slipway-2 and 3 Main Incoming panels to welding and Lighting panels | Supply of 3.5CX 185 Sq.mm Aluminum cable (from slipway-2&3 Main Incoming panels to welding and Lighting panels) as per technical specification & SOW. |
| 10 | Laying, fixing, testing and commissioning of 3.5CX 185 Sq.mm Aluminum cable from slipway-2 and 3 Main Incoming panels to welding and Lighting panels | Laying, fixing, testing and commissioning of 3.5CX 185 Sq.mm Aluminum cable (from slipway-2&3 Main Incoming panels to welding and Lighting panels) as per technical specification & SOW. |
| 11 | Supply and Fitment of suitable End termination kits - Straight Through Joints Kits of required quantity to all the Incoming and Outgoing cables at both ends of Slipway-02, Slipway-03, Substations, etc | Supply and Fitment of suitable End termination kits / Straight Through Joints Kits of required quantity to all the Incoming & Outgoing cables at both ends of Slipway-02, Slipway-03, Substations, etc., as per Tech Spec. & SOW |
| 12 | Providing earth pits with 75mm CI pipe as Is standards | Providing earth pits with 75mm CI pipe as Is standards as per technical specification & SOW. |
| 13 | Supply and laying of GI flat 50 x10 mm necessary joints with nut and bolts from earth pit to Panel boards | Supply and laying of GI flat 50 x10 mm necessary joints with nut and bolts from earth pit to Panel boards as per technical specification & SOW |
| 14 | Repair and excavation of cable trench of 75mm thick up to 90cm depth | Repair and excavation of cable trench (of 75mm thick) up to 90cm depth as per technical specification & SOW. |
| 15 | Fixing of perforated cable tray on slipways 02 and 03 and securing of cables with metal ties and capping and casing to be provided | Fixing of perforated cable tray on slipways 02 & 03 and securing of cables with metal ties and capping & casing to be provided as per technical specification & SOW. |
| 16 | Foundation for all LT panels i.e. steel foundations with concrete pedestal for panels all incoming and welding and lighting panels | Foundation for all LT panels i.e. steel foundations with concrete pedestal for panels (all incoming and welding & lighting panels as per technical specification & SOW. |