| 1 | Earth work in excavation in all kinds of soil with all lead & lift including dressing and levelling the bed and depositing the excavated materials away from the work site including labour, cost, carriage, royalty, cess & all other taxes as applicable etc. complete as per specification and direction of the Engineer-in-charge. |
| 2 | Quarrying, collecting, supplying hard granite stone boulder of size 30cm & above and 0.028cum in volume from approved quarry free from weather skin surface and other deleterious materials, dumping the stones including surface packing in all heights and depths including filling the interstices with small stones, wedging and packing surface to proper line and levels including fixing wave breakers etc. including cost, conveyance, labour, T&P required for the work, royalty, EMF, DMF & additional charges, cess, taxes of all materials of approved quality with uniform colour and texture with all leads, lifts, delifts including dumping in water, hire charges of boat with boat man and lunch with driver and all other incidental charges and other taxes as applicable etc. complete as per the specification and direction of the Engineer-in-charge. (Measurement to be taken after deducting 1/6th voids from the finished level section). |
| 3 | Quarrying, collecting, supplying & stacking of hard granite stone boulder of size 15cm to 30cm from approved quarry free from weather skin surface and other deleterious materials, packing the stones to required profile in all heights and depths including filling the interstices with small stones, wedging and hammering etc. including cost, conveyance, labour, T&P required for the work, royalty, EMF, DMF & additional charges, taxes, cess, hire and running charges and transportation of all materials of approved quality with uniform colour and texture with all leads, lifts, delifts handling and re-handling etc. including all other incidental charges and other taxes as applicable required to complete the work as per the specification and direction of the Engineer-in-charge. |
| 4 | Filling in foundation and plinth with good quality of sand laying in layers duly compacted, watering and ramming with all leads, lifts & delifts including labour, cost, carriage, royalty, EMF, DMF & additional charges, cess & all other taxes as applicable etc. complete as per specification and direction of the Engineer-in-Charge. |
| 5 | Providing & laying cement concrete conforming to M15 grade in approved surface using 20 mm & downgraded black hard granite crusher broken stone aggregates and sharp sand of approved grading from approved quarry for CC work conforming to specification, mixing by concrete mixture including hoisting and laying concrete in position, compacting with vibrator, with all leads, lifts, delifts for mixing concrete including royalty, EMF, DMF & additional charges, all other taxes as applicable & cess including dewatering by suitable means, supplying T&P, curing for specified days by suitable means with supervision charges with cost of construction and dismantling of gangway and scaffolding, chute with all materials, approach road, diversion road, site illumination, hire and running charges of machineries required for the work as per approved drawing and specification etc complete with all cost incidental to the work and direction of the Engineer-in-Charge. |
| 6 | Providing & laying cement concrete conforming to M20 grade in approved surface using 20 mm & downgraded black hard granite crusher broken stone aggregates and sharp sand of approved grading from approved quarry for CC work conforming to specification, mixing by concrete mixture including hoisting and laying concrete in position, compacting with vibrator, with all leads, lifts, delifts for mixing concrete including royalty, EMF, DMF & additional charges, all other taxes as applicable & cess including dewatering by suitable means, supplying T&P, curing for specified days by suitable means with supervision charges with cost of construction and dismantling of gangway and scaffolding, chute with all materials, approach road, diversion road, site illumination, hire and running charges of machineries required for the work as per approved drawing and specification etc complete with all cost incidental to the work and direction of the Engineer-in-Charge. |
| 7 | Rigid and smooth centering shuttering for RCC / CC work including false work and dismantling then after casting including all labours, cost, cess & all other taxes as applicable and hire charges of wood etc. complete as per specification and direction of the Engineer-in-Charge. |
| 8 | Providing & laying laterite stone masonary in cement Motar (1:4) in foundation and plinth including all cost of materials with all leads, lifts, delifts for mixing cement Motar including all conveyance, royalty, EMF, DMF & additional charges, all other taxes as applicable & cess, T&P, curing for specified days by suitable means with supervision charges with cost of construction and dismantling of gangway and scaffolding, approach road, diversion road, site illumination, hire and running charges of machineries required for the work as per approved drawing etc. complete as per specification and direction of the Engineer-in-Charge. |
| 9 | Providing & laying 16mm thick cement plaster (1:6) over brick or stone masonary including all cost of materials with all leads, lifts, delifts for mixing cement Motar including all conveyance, royalty, EMF, DMF & additional charges, all other taxes as applicable & cess, T&P, curing for specified days by suitable means with supervision charges with cost of construction and dismantling of gangway and scaffolding, approach road, diversion road, site illumination, hire and running charges of machineries required for the work as per approved drawing etc. complete as per specification and direction of the Engineer-in-Charge. Please Enable Macros to View BoQ information |