| 1 | Site clearance for cutting bushes cleaning the sites etc complete. |
| 2 | Drilling a perfectly vertical 150 mm dia bore hole in weathered rock formation from ground level |
| 3 | Supplying & lowering of 125 mm dia PVC casing pipe without slots in perfectly vertical position including cost of pipe etc complete |
| 4 | Supplying & lowering of 125 mm dia PVC casing pipe with slots in perfectly vertical position including cost of pipe etc complete |
| 5 | Supplying & fitting of 150 mm. dia ( IS 1239) GI Pipe |
| 6 | Earth work excavation in stony earth and gravel mixed with stone and boulder not exceeding on 0.014 cum in volume within 50m initial lead and 1.5m initial lift including rough dressing and breaking clods and max. 5 cm to 7 cm and lying in layer not exceed 0.3 mtr in depth as per Specification approved by the department. |
| 7 | Cutting the disintegrated rocks not requiring blasting to be removed by pick axes and craw bars and depositing materials within 50m and 1.5m initial lift including rough dressing as per direction of EIC.a) 2nd depth - |
| 8 | Cutting the disintegrated rocks not requiring blasting to be removed by pick axes and craw bars and depositing materials within 50m and 1.5m initial lift including rough dressing as per direction of EIC.b) 3rd depth - |
| 9 | Filling the F & P with sand well watered and rammed etc complete |
| 10 | C.C. (1:3:6) with 40 mm. size crusher broken granite chips in platform including cost, carriage, royalty of all materials and all labour charges etc complete |
| 11 | Supplying & spreading of 40mm metal for filter in recharge pit including cost, conveyance, royalty etc complete. |
| 12 | Supplying & spreading of 12 mm chips for filter in recharge pit including cost, conveyance, royalty etc complete. |
| 13 | Supplying & spreading of filter media (Pebbles/Gravel) 6mm to 10 mm size |
| 14 | Lying of R C C Ring 5ft dia. made up of 6 mm dia MS rod for storage cum recharge pit including cost, transporting etc complete. |
| 15 | Fly ash Brick masonry in C.M (1:6) including cost, carriage, royalty of all materials & labour charges etc. complete. |
| 16 | Rigid smooth Centering,shuttering work for RCC work - |
| 17 | Cement concrete (1:1.5:3) with 12mm. Size H.G. C.B. chips for RCC works including all cost, conveyance , royalty of materials etc. complete. |
| 18 | Supplying, cutting, bending and binding of HYSD bars for reinforcement including cost of binding wire etc. complete. |
| 19 | 12 mm. thick cement plaster over brick work in C.M. (1:6) |
| 20 | Fitting of Chequered tiles on floor on 25 mm thick bed of cement mortar 1:1 including cost, carriage, royalty of all materials & all labour charges etc. complete. |
| 21 | Primer one coat over wall surface - |
| 22 | Wall painting two coats with weather paint of approved shade on wall surface - |
| 23 | Supplying & fitting of Manhole cover of size 0.60x0.60 m with locking arrangement |
| 24 | Filling foundation and plinth with excavated materils including well watered and rammed with all labour, T&P etc. complete as per the direction of Engineer-in-charge. |
| 25 | Supplying & laying & fixing of 160 mm (OD) PVC Pipes (4 kg /cm2) of Including all cost for socket, bend, solvent. transportation of pipes etc complete . |
| 26 | Supplying & fitting of MS well Cap |
| 27 | Fabrication, Carraige & Installation of Protection Chamber made of 18 gauge steel with handle & locking arrangements including denting, priming & colouring with writing of well id & other deptt. information etc. |
| 28 | Washing & Cleaning /No |
| 29 | Provision for dewatering by Pump Please Enable Macros to View BoQ information |