| 1 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.In cement mortar |
| 2 | Scarping plaster in lime or cement mortar from brick/ stone masonry s |
| 3 | Carriage of Materials by mechanical transport including loading, unloading and stacking :: Earth Beyo nd 5 Km upto 10 Km. per Km. |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level : |
| 5 | 1:1½:3 (1 Cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size). |
| 6 | 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) |
| 7 | Steel work welded in built up sections/ framed work including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works. |
| 8 | Brick work with FPS bricks of class designation 75 in foundation and plinth in Cement mortar 1:6 (1 cement : 6 coarse sand) |
| 9 | Cement plastering including T&P, scaffolding, material and complete labour, including cost of water, curing, racking of joints etc. with 12 mm cement plaster of mix : including Providing /mixing of synthetic fibers compulsorily complying with IS 16481:2022 of 06 mm/12 mm length to be mixed @ 0.25% by weight of Cement i.e. 125 gms per 50 kg Cement up to 900 gms per cum of Concrete/ mortar1:6 (1 cement : 6 fine/ coarse sand) |
| 10 | Kota stone slab flooring 25mm thick over 20 mm (average) thick base laid over and jointed with grey cement slurry mixed with pigment to match the shade of the slab including rubbing and polishing complete with base of cement mortar 1 : 4 (1 cement : 4 coarse sand) :Area of each slab 900 to 2000 sqcm |
| 11 | Finishing walls with Acrylic Smooth exterior paint of required shade New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including base coat of water proofing cement paint applied @ 2.20 kg/ 10 sqm). |
| 12 | Providing and laying water proofing treatment on roofs of slabs by applying cement slurry mixed with water proofing cement compound consisting of applying : a) after surface preparation, first layer of slurry of cement @ 0.488 kg/sqm mixed with water proofing cement compound @ 0.253 kg/sqm. b) laying second layer of Fibre glass cloth when the first layer is still green. Overlaps of joints of fibre cloth should not be less than 10 cm. c) third layer of 1.5 mm thickness consisting of slurry of cement @ 1.289 kg/sqm mixed with water proofing cement compound @ 0.670 kg/sqm and coarse sand @ 1.289 kg/sqm. This will be allowed to air cure for 4 hours followed by water curing for 48 hours. The entire treatment will be taken upto 30cm on parapet wall and tucked into groove in parapet all around. d) fourth and final layer of brick tiling with cement mortar (which will be paid for separately For the purpose of measurement the entire treated surface will be measured. |
| 13 | High Intensity retro reflective Type IV sign plate made out of 2.00 mm thick aluminium sheet face to be fully covered with blue/green high intensity grade retro reflective sheet and logo/matters, boarder made of with similar type of white sheeting after etching treatment of aluminium sheet, the black side is to be painted with epoxy grey paint. the plate is to be fixed on 40X40X5 mm angle iron frame with help of aluminium rivets.C.P. Brass bibcock 15 mm |
| 14 | Painting two coats on specified surface with synthetic enamel paint of approved brand and shade, after thorough cleaning and necessary filling to give even shade as per clause 803 of MoRT&H Specification including all material, labour.On steel surface Please Enable Macros to View BoQ information |