| 1 | Works Details |
| 2 | Less Credit of Old Bricks |
| 3 | Less Credit of Brick Bats |
| 4 | Supply and erection of Horizontal spindle split casing type puming sets minimum Four (4) Star rating duties coupled to AC squrrel cage induction type motor with 1440 RPM, 3 phase 50 Hz and accessories as described in Schedule No.II complete in all respect with priming arrangement with complete base frame .Raw Water Pump set 700 LPM 12 Mtrs Head-.. |
| 5 | Credit for Surplus Soil |
| 6 | Less Credit of old pumping machinary 1300 lpm x 12 m head |
| 7 | Less credit of old pumping machinery 1300 lpm x 40 m head (clear water pump set) |
| 8 | Credit of old steel scraping |
| 9 | Credit of old Material |
| 10 | Less Credit of old Valve 200 mm |
| 11 | Credit of Old Starter |
| 12 | Water Treatment Plant (WTP) - Designing, Testing, Construction and Commissioning of 1.00 MLD capacity water treatment plant including inlet channel alum dozing, flash mixing, clari floculator, filtter box, over head reservoir for back wash, waste water tank, including all civil work pumping machinery and electric cabling, control panel, entire piping network of suitable size, supplying, laying, cutting and jointing of DI pipes from raw water pump to inlet box of WTP, WTP to CWT and Suction well for CW including, DI specials suitable size sluice valves, hodies, manhole covers, air scour equipment, chemical house including chlorination equipment and arrangement of flow measurement and sand bed with automation complete in all respects as per approved NIT. (Sluice valve of make IVCAWAG)..... |
| 13 | Credit of Old pumping machinery 2500 lpm x 12 m head unserviciable/ burnt/ irrepairable pump set including dismantling , carraige etc...... |
| 14 | Operation and Maintenance for complete scope of work of 1MLD WTP mentioned in the DNIT in the village Disinfectionmaterial supplied by the PHED as per schedule-IV for a period of5 years after 12 months during defect liability period and 3months trial run period. (will be charged to the A/mtc estimate).complete in all respects as per approved NIT.1) Operation and maintenance during defect liabilityperiod after 3 month trial run period ( operation only) |
| 15 | 1st year Operation and maintenance after defect liability period |
| 16 | 2nd year Operation and maintenance |
| 17 | 3rd year Operation and maintenance |
| 18 | 4th year Operation and maintenance |
| 19 | 5th year Operation and maintenance |
| 20 | Item Description |
| 21 | HSR Item Please Enable Macros to View BoQ information |